BREAKDOWN OF UNIT PRICE
Item: (B01C0) MS Deform Bar-Grade-400
Basis:50 kg.
A1.Material Cost-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Deforme Bar Grade-400(60)
50.500
kg
59.00
2979.50
GI Wire
0.500
kg
120.00
60.00
Sub-Total(A1)
3039.50
60790.00
B2.Labour-Substructur-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Skilled Labour/ Helper
0.450
no.
550.00
247.50
Rod Binder
0.100
no.
700.00
70.00
Sub-Total(B2)
317.50
6350.00
D1.Design/Prelims
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage (Labour)
0.200
no.
700.00
140.00
Sub-Total(D1)
140.00
2800.00
Total(1)
69940.00
Add over head on Total(1)
5.0 %
3497.00
Total(2)
73437.00
Add Profit on Total(2)
10.0 %
7343.70
Total(3)
80780.70
Add VAT on Unit Price
5.5 %
4964.18
Add Income Tax on Unit Price
5.0 %
4512.89
Unit Price
90257.77
Say
90258
per Ton