BREAKDOWN OF UNIT PRICE
Item: (B01BE) RCC(1:2:4)-Brckchp,Local Sand
Basis:100 cft
A1.Material Cost-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement-CEM-II/A,52.5-PCC
18.000
bag
375.00
6750.00
Local Sand (FM=1.2)
45.000
cft
18.00
810.00
Brick-M/c made
766.000
no.
9.50
7277.00
Sub-Total(A1)
14837.00
5239.69
B2.Labour-Substructur-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
RCC Work
100.000
cft
45.00
4500.00
Breaking Brick-Chips-20mm
90.000
cft
9.50
855.00
Sub-Total(B2)
5355.00
1891.12
E1.Equipment Cost
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Vibrator and Mixer M/c
100.000
cft
3.00
300.00
Sub-Total(E1)
300.00
105.95
Total(1)
7236.75
Add over head on Total(1)
5.0 %
361.84
Total(2)
7598.59
Add Profit on Total(2)
10.0 %
759.86
Total(3)
8358.45
Add VAT on Unit Price
5.5 %
513.65
Add Income Tax on Unit Price
5.0 %
466.95
Unit Price
9339.05
Say
9339
per Cum