Return Main Menu
BREAKDOWN OF UNIT PRICE
Item: (B01B) RCC (1:1.5:3) in Pile excl reinf
Basis:100 cft
A1.Material Cost-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement-CEM-II/A,52.5-PCC
26.400
bag
375.00
9900.00
Sylhet Sand (FM=2.2)
51.600
cft
54.00
2786.40
Shingles1
103.200
cft
83.00
8565.60
Sub-Total(A1)
21252.00
7505.14
B2.Labour-Substructur-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Shingles/Chips Shifting
103.200
cft
5.00
516.00
Sub-Total(B2)
516.00
182.23
Total(1)
7687.37
Add over head on Total(1)
5.0 %
384.37
Total(2)
8071.74
Add Profit on Total(2)
10.0 %
807.17
Total(3)
8878.91
Add VAT on Unit Price
5.5 %
545.63
Add Income Tax on Unit Price
5.0 %
496.03
Unit Price
9920.57
Say
9921
per M3