BREAKDOWN OF UNIT PRICE
Item: (B01AG) Shore Pile-Additional1
Basis:1 no.
B0.Sub-Contractor-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Trial Shore Pile-1000mm
1.000
no.
99999.99
99999.99
Obstacle Remove-Shore Cas
9999.999
rft
2722.95
27229497.28
Shore Pile temp casing dr
7969.550
rft
2714.11
21630235.35
Shore pile excavat-fillin
9999.999
cft
50.00
499999.95
Shore/Seal Pile mud remov
9999.999
cft
27.18
271799.97
Shore/Seal Pile dewaterin
180.000
day
4480.00
806400.00
Shor Pile Air Supply
180.000
day
3500.00
630000.00
Shore Pile Salvage Removl
1.000
LS
99999.99
99999.99
Sub-Total(B0)
51267932.53
51267932.53
Total(1)
51267932.53
Add over head on Total(1)
5.0 %
2563396.63
Total(2)
53831329.16
Add Profit on Total(2)
10.0 %
5383132.92
Total(3)
59214462.07
Add VAT on Unit Price
5.5 %
3638877.56
Add Income Tax on Unit Price
5.0 %
3308070.51
Unit Price
66161410.14
Say
66161410
per LS