BREAKDOWN OF UNIT PRICE
Item: (B01AA) Shore Pile-Temporary Casing Drive
Basis:3 rft
B3.Labour-Substructur-2
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
ShoreTemporary casing Drv
3.281
rft
2714.11
8904.99
Sub-Total(B3)
8904.99
8904.99
Total(1)
8904.99
Add over head on Total(1)
5.0 %
445.25
Total(2)
9350.24
Add Profit on Total(2)
10.0 %
935.02
Total(3)
10285.27
Add VAT on Unit Price
5.5 %
632.06
Add Income Tax on Unit Price
5.0 %
574.60
Unit Price
11491.92
Say
11492
per Rm