Return Main Menu
BREAKDOWN OF UNIT PRICE
Item: (B01A1) Pile Boring-1500 mm dia
Basis:1 rft
B2.Labour-Substructur-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Pile Boring-1500mm
1.000
rft
4131.00
4131.00
Pile Earh Removal
20.000
cft
27.18
543.60
Sub-Total(B2)
4674.60
15337.36
Total(1)
15337.36
Add over head on Total(1)
5.0 %
766.87
Total(2)
16104.23
Add Profit on Total(2)
10.0 %
1610.42
Total(3)
17714.65
Add VAT on Unit Price
5.5 %
1088.61
Add Income Tax on Unit Price
5.0 %
989.65
Unit Price
19792.91
Say
19793
per Rm