BREAKDOWN OF UNIT PRICE
Item: (A01B1) Mobilization-Demobilization
Basis:1 no.
A1.Material Cost-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Deforme Bar Grade-400(60)
9999.999
kg
59.00
589999.94
Viti Sand (FM=0.5-0.8)
9999.999
cft
15.00
149999.99
Ready Mix Concrete-3500ps
4344.000
cft
250.00
1086000.00
GI Wire
70.000
kg
120.00
8400.00
Sub-Total(A1)
1834399.93
1834399.93
B2.Labour-Substructur-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
RCC Work
4344.000
cft
45.00
195480.00
Re-bar fabricating
9999.999
kg
10.00
99999.99
Form Work-Substructure
6516.000
sft
35.00
228060.00
Sand Filling
9999.999
cft
10.00
99999.99
Sub-Total(B2)
623539.98
623539.98
D1.Design/Prelims
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Office-Labor shed-Store
6458.000
sft
810.00
5230980.00
Site Protection-Bolli-Dru
574.175
rft
993.00
570155.78
Site Electrificatio-CCTV
1.000
LS
99999.99
99999.99
Water-Electricity-Sanitar
1.000
LS
99999.99
99999.99
Demobilization
1.000
LS
99999.99
99999.99
Sub-Total(D1)
6101135.75
6101135.75
D2.Others-Structure
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Wooden Form
6516.000
sft
36.25
236205.00
Sub-Total(D2)
236205.00
236205.00
E1.Equipment Cost
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Compactor
9999.999
cft
5.00
50000.00
Sub-Total(E1)
50000.00
50000.00
Total(1)
8845280.65
Add over head on Total(1)
5.0 %
442264.03
Total(2)
9287544.68
Add Profit on Total(2)
10.0 %
928754.47
Total(3)
10216299.15
Add VAT on Unit Price
5.5 %
627817.27
Add Income Tax on Unit Price
5.0 %
570742.97
Unit Price
11414859.38
Say
11414859
per LS