MONTHLY MATERIAL STATEMENT DETAIL | |||||||||
Project: | CBD | ||||||||
Upto 14-October-2020 | |||||||||
SL. No | Name of Materials | Unit | Received | Consumption | Balance | ||||
Upto Previous Month | This Month | Total | Upto Previous Month | This Month | Total | ||||
A1 | Material Cost-Civil | ||||||||
01 | Viti Sand (FM=0.5-0.8) | cft | 774 | 3300 | |||||
2020-10-10 | 774.000 | ||||||||
2020-10-02 | 200 | ||||||||
2020-10-03 | 100 | ||||||||
2020-10-04 | 150 | ||||||||
2020-10-05 | 1500 | ||||||||
2020-10-06 | 50 | ||||||||
2020-10-07 | 100 | ||||||||
2020-10-10 | 200 | ||||||||
2020-10-11 | 500 | ||||||||
2020-10-12 | 300 | ||||||||
2020-10-13 | 200 | ||||||||
02 | Sylhet Sand (FM=2.2) | cft | 980 | 100 | |||||
2020-10-05 | 40 | ||||||||
2020-10-10 | 20 | ||||||||
2020-10-11 | 20 | ||||||||
2020-10-12 | 10 | ||||||||
2020-10-13 | 10 | ||||||||
03 | Local Sand (FM=1.2) | cft | 3162 | 480 | |||||
2020-10-03 | 380.000 | ||||||||
2020-10-04 | 460.000 | ||||||||
2020-10-11 | 2322.000 | ||||||||
2020-10-04 | 50 | ||||||||
2020-10-05 | 50 | ||||||||
2020-10-06 | 50 | ||||||||
2020-10-07 | 60 | ||||||||
2020-10-08 | 50 | ||||||||
2020-10-09 | 30 | ||||||||
2020-10-10 | 60 | ||||||||
2020-10-11 | 30 | ||||||||
2020-10-12 | 30 | ||||||||
2020-10-13 | 40 | ||||||||
2020-10-14 | 30 | ||||||||
04 | Stone-chips-20mm | cft | 384 | 110 | |||||
2020-10-04 | 50 | ||||||||
2020-10-05 | 60 | ||||||||
05 | Stone-chips-12mm down | cft | 540 | -35 | 50 | 15 | |||
2020-10-05 | 540.000 | ||||||||
2020-10-05 | 50 | ||||||||
06 | Brick | no. | 14000 | 10600 | |||||
2020-10-06 | 6000.000 | ||||||||
2020-10-12 | 2000.000 | ||||||||
2020-10-14 | 6000.000 | ||||||||
2020-10-06 | 1500 | ||||||||
2020-10-08 | 1200 | ||||||||
2020-10-09 | 400 | ||||||||
2020-10-10 | 3000 | ||||||||
2020-10-11 | 1500 | ||||||||
2020-10-13 | 1500 | ||||||||
2020-10-14 | 1500 | ||||||||
08 | Brick Chips-20mm | cft | 2029 | 645 | |||||
2020-10-04 | 535.000 | ||||||||
2020-10-06 | 434.000 | ||||||||
2020-10-08 | 1060.000 | ||||||||
2020-10-04 | 50 | ||||||||
2020-10-05 | 50 | ||||||||
2020-10-06 | 85 | ||||||||
2020-10-07 | 80 | ||||||||
2020-10-08 | 70 | ||||||||
2020-10-09 | 40 | ||||||||
2020-10-10 | 80 | ||||||||
2020-10-11 | 40 | ||||||||
2020-10-12 | 30 | ||||||||
2020-10-13 | 60 | ||||||||
2020-10-14 | 60 | ||||||||
10 | Cement-CEM-II/A,52.5-PCC | bag | 562 | 171 | |||||
2020-10-04 | 250.000 | ||||||||
2020-10-05 | 250.000 | ||||||||
2020-10-11 | 62.000 | ||||||||
2020-10-01 | 3 | ||||||||
2020-10-03 | 12 | ||||||||
2020-10-04 | 15 | ||||||||
2020-10-05 | 16 | ||||||||
2020-10-06 | 16 | ||||||||
2020-10-07 | 21 | ||||||||
2020-10-08 | 17 | ||||||||
2020-10-09 | 5 | ||||||||
2020-10-10 | 15 | ||||||||
2020-10-11 | 6 | ||||||||
2020-10-12 | 15 | ||||||||
2020-10-13 | 10 | ||||||||
2020-10-14 | 20 | ||||||||
11 | Deform Xtreme 500W(72) | kg | 196969 | 13000 | |||||
2020-10-13 | 10000 | ||||||||
2020-10-14 | 3000 | ||||||||
16 | GI Wire | kg | 50 | 20 | |||||
2020-10-02 | 2 | ||||||||
2020-10-03 | 1 | ||||||||
2020-10-06 | 7 | ||||||||
2020-10-07 | 2 | ||||||||
2020-10-08 | 2 | ||||||||
2020-10-09 | 1 | ||||||||
2020-10-11 | 2 | ||||||||
2020-10-12 | 2 | ||||||||
2020-10-13 | 1 | ||||||||
A2 | Bracing Steel | ||||||||
18 | MS Pipe -100mm Dia | rft | 5540 | 40 | |||||
2020-10-01 | 40 | ||||||||
47 | J-Hook | kg | 15 | 5 | |||||
C9 | Electrical Materials | ||||||||
21 | Electric Cable-95 NNY RM | rft | 1312 | 394 | |||||
2020-10-07 | 66 | ||||||||
2020-10-12 | 328 | ||||||||
22 | Electric Cable-16 NNY RM | rft | 1641 | 66 | |||||
2020-10-07 | 66 | ||||||||
24 | Electric Cable- 6 RM | rft | 1969 | 1476 | |||||
2020-10-06 | 656 | ||||||||
2020-10-11 | 492 | ||||||||
2020-10-12 | 328 | ||||||||
25 | Elecreic Cable-2.5 RM | rft | 4265 | 656 | |||||
2020-10-14 | 656 | ||||||||
27 | Electric Cable-1.5 RM | rft | 8859 | 2956 | |||||
2020-10-03 | 4 | ||||||||
2020-10-08 | 328 | ||||||||
2020-10-10 | 656 | ||||||||
2020-10-11 | 984 | ||||||||
2020-10-14 | 984 | ||||||||
28 | Electric Bulb-100 W | nos | 6 | 2 | |||||
2020-10-02 | 1 | ||||||||
2020-10-03 | 1 | ||||||||
32 | Circuit Braker-16 A | nos | 10 | 2 | |||||
2020-10-01 | 2 | ||||||||
37 | PVC Board-3 Gang | nos | 9 | 2 | |||||
2020-10-01 | 2 | ||||||||
38 | Cable Lux-N 95 | nos | 20 | 20 | |||||
2020-10-07 | 20 | ||||||||
41 | Cable Lux- 4 RM | nos | 15 | 20 | |||||
2020-10-12 | 20 | ||||||||
44 | Cable Tie-150 mm | pack | 10 | 19 | |||||
2020-10-06 | 5 | ||||||||
2020-10-07 | 6 | ||||||||
2020-10-08 | 4 | ||||||||
2020-10-11 | 4 | ||||||||
45 | Electric PVC Tape | nos | 12 | 39 | |||||
2020-10-14 | 12.000 | ||||||||
2020-10-01 | 1 | ||||||||
2020-10-03 | 2 | ||||||||
2020-10-06 | 10 | ||||||||
2020-10-07 | 10 | ||||||||
2020-10-08 | 7 | ||||||||
2020-10-09 | 2 | ||||||||
2020-10-11 | 6 | ||||||||
2020-10-12 | 1 | ||||||||
89 | Electric Holder | nos | 12 | 7 | |||||
2020-10-10 | 12.000 | ||||||||
2020-10-03 | 1 | ||||||||
2020-10-10 | 6 | ||||||||
93 | Circuit Braker-150 A | nos | 0 | 2 | |||||
2020-10-06 | 2 | ||||||||
94 | Circuit Braker-250 A | nos | 0 | 1 | |||||
2020-10-07 | 1 | ||||||||
99 | Circuit Braker-40 A | nos | 0 | 3 | |||||
2020-10-08 | 3 | ||||||||
D3 | Shuttering-Hardware | ||||||||
48 | Mango Wood for Shutter | cft | 287 | 95 | |||||
2020-10-10 | 287.000 | ||||||||
2020-10-10 | 40 | ||||||||
2020-10-11 | 35 | ||||||||
2020-10-12 | 20 | ||||||||
49 | Cutting Disk-350mm | nos | 60 | 4 | |||||
2020-10-14 | 4 | ||||||||
51 | Cutting Disk-100 | pcs | 400 | 67 | |||||
2020-10-01 | 400.000 | ||||||||
2020-10-01 | 10 | ||||||||
2020-10-02 | 5 | ||||||||
2020-10-03 | 5 | ||||||||
2020-10-04 | 6 | ||||||||
2020-10-05 | 10 | ||||||||
2020-10-06 | 6 | ||||||||
2020-10-07 | 5 | ||||||||
2020-10-09 | 5 | ||||||||
2020-10-11 | 5 | ||||||||
2020-10-12 | 5 | ||||||||
2020-10-14 | 5 | ||||||||
52 | Flexible(Curing) Pipe-25 | rft | 300 | 200 | |||||
2020-10-02 | 200 | ||||||||
57 | Welding Electrode-Pack | pack | 30 | 2 | |||||
2020-10-04 | 1 | ||||||||
2020-10-07 | 1 | ||||||||
60 | Paint Brush | nos | 4 | 8 | |||||
2020-10-02 | 4.000 | ||||||||
2020-10-02 | 4 | ||||||||
2020-10-08 | 2 | ||||||||
2020-10-09 | 2 | ||||||||
61 | Plastic Tripal | nos | 10 | 3 | |||||
2020-10-01 | 1 | ||||||||
2020-10-11 | 2 | ||||||||
62 | Jute Rope/ Sutli | kg | 10 | 7 | |||||
2020-10-06 | 2 | ||||||||
2020-10-09 | 2 | ||||||||
2020-10-11 | 2 | ||||||||
2020-10-12 | 1 | ||||||||
84 | Steel Nail-12~75mm | kg | 100 | 43 | |||||
2020-10-02 | 1 | ||||||||
2020-10-04 | 3 | ||||||||
2020-10-06 | 3 | ||||||||
2020-10-07 | 4 | ||||||||
2020-10-08 | 3 | ||||||||
2020-10-09 | 1 | ||||||||
2020-10-10 | 8 | ||||||||
2020-10-11 | 5 | ||||||||
2020-10-12 | 5 | ||||||||
2020-10-14 | 10 | ||||||||
85 | Red Oxide | litr | 2 | 1 | |||||
2020-10-02 | 2.000 | ||||||||
2020-10-02 | 1 | ||||||||
86 | Nylone Rope-25/20mm | kg | 2 | 2 | |||||
2020-10-02 | 2.000 | ||||||||
2020-10-09 | 2 | ||||||||
87 | Enamel-Mat | L | 0 | 12 | |||||
2020-10-03 | 4 | ||||||||
2020-10-08 | 4 | ||||||||
2020-10-09 | 4 | ||||||||
88 | Thinnner-T-6 | L | 0 | 7 | |||||
2020-10-03 | 3 | ||||||||
2020-10-08 | 4 | ||||||||
90 | Hessain Cloth | kg | 0 | 4 | |||||
2020-10-04 | 2 | ||||||||
2020-10-10 | 2 | ||||||||
95 | Hammer Bit-20mm | nos | 2 | 2 | |||||
2020-10-08 | 2.000 | ||||||||
2020-10-08 | 2 | ||||||||
96 | Hammer-04 lbs | nos | 0 | 5 | |||||
2020-10-08 | 3 | ||||||||
2020-10-09 | 2 | ||||||||
97 | Measurement Tape | nos | 5 | 6 | |||||
2020-10-08 | 3 | ||||||||
2020-10-09 | 3 | ||||||||
98 | Korat | nos | 10 | 2 | |||||
2020-10-08 | 2 | ||||||||
E1 | Equipment Cost | ||||||||
71 | Diesel-1 | litr | 180 | 187 | |||||
2020-10-04 | 30.000 | ||||||||
2020-10-07 | 60.000 | ||||||||
2020-10-11 | 30.000 | ||||||||
2020-10-14 | 60.000 | ||||||||
2020-10-01 | 12 | ||||||||
2020-10-03 | 10 | ||||||||
2020-10-04 | 12 | ||||||||
2020-10-05 | 10 | ||||||||
2020-10-06 | 15 | ||||||||
2020-10-07 | 20 | ||||||||
2020-10-08 | 12 | ||||||||
2020-10-09 | 15 | ||||||||
2020-10-10 | 23 | ||||||||
2020-10-11 | 10 | ||||||||
2020-10-12 | 23 | ||||||||
2020-10-13 | 10 | ||||||||
2020-10-14 | 15 | ||||||||
92 | Mobil | litr | 7 | 9 | |||||
2020-10-12 | 2.000 | ||||||||
2020-10-13 | 5.000 | ||||||||
2020-10-06 | 1 | ||||||||
2020-10-11 | 2 | ||||||||
2020-10-12 | 2 | ||||||||
2020-10-13 | 3 | ||||||||
2020-10-14 | 1 | ||||||||
E2 | Safety Material | ||||||||
72 | Safety Vest1 | nos | 100 | 111 | |||||
2020-10-04 | 36 | ||||||||
2020-10-05 | 19 | ||||||||
2020-10-06 | 7 | ||||||||
2020-10-07 | 12 | ||||||||
2020-10-08 | 10 | ||||||||
2020-10-10 | 12 | ||||||||
2020-10-14 | 15 | ||||||||
73 | Safety Helmet | nos | 50 | 94 | |||||
2020-10-04 | 36 | ||||||||
2020-10-05 | 19 | ||||||||
2020-10-06 | 5 | ||||||||
2020-10-07 | 12 | ||||||||
2020-10-08 | 10 | ||||||||
2020-10-10 | 10 | ||||||||
2020-10-14 | 2 | ||||||||
81 | Hand Gloves | pair | 100 | 100 | |||||
2020-10-04 | 10 | ||||||||
2020-10-05 | 10 | ||||||||
2020-10-06 | 10 | ||||||||
2020-10-07 | 15 | ||||||||
2020-10-08 | 10 | ||||||||
2020-10-09 | 10 | ||||||||
2020-10-11 | 15 | ||||||||
2020-10-12 | 10 | ||||||||
2020-10-14 | 10 | ||||||||
83 | Caution (Safety) Tape | roll | 30 | 1 | |||||
2020-10-02 | 1 | ||||||||
91 | Rubber Shoe-1 | pair | 100 | 60 | |||||
2020-10-04 | 30 | ||||||||
2020-10-05 | 10 | ||||||||
2020-10-06 | 10 | ||||||||
2020-10-07 | 5 | ||||||||
2020-10-12 | 5 |