Costing for 3no.Adl Pile-Solid Track-II Utility Bldg | |||||||||
Item | Description | BOQ Qty | Bill Qty | Unit | S.Rate(Tk.) | A.Rate(Tk.) | BOQ Amount | Bill Amount | Con. Amount | A105 | Cement |
102.555 |
101.902 |
bag | 343.00 |
237.00 |
35,176.37 |
25,067.89 |
22,515.00 |
A106 | Sand - Sylhet |
200.448 |
199.172 |
cft | 24.00 |
15.50 |
4,810.75 |
3,585.10 |
3,487.50 |
A107 | Stone-chips |
400.896 |
398.345 |
cft | 80.00 |
65.00 |
32,071.68 |
27,884.15 |
21,206.25 |
A112 | GI Wire |
16.000 |
14.480 |
kg | 90.00 |
0.00 |
1,440.00 |
1,013.60 |
0.00 |
A114 | Re-bar G60 |
2100.000 |
1900.500 |
kg | 40.20 |
39.00 |
84,420.00 |
69,368.25 |
73,671.00 |
E103 | Mini Dumper |
100.000 |
100.000 |
cft | 2.00 |
0.00 |
200.00 |
400.00 |
0.00 |
E105 | Welding M/c |
2000.000 |
1810.000 |
kg | 0.50 |
0.00 |
1,000.00 |
905.00 |
0.00 |
E138 | Rig,Mixer M/c |
466.158 |
463.192 |
cft | 10.00 |
0.00 |
4,661.58 |
4,631.92 |
0.00 |
E139 | Bored Piling Equipment |
200.141 |
198.501 |
rft | 30.00 |
0.00 |
6,004.23 |
5,955.03 |
0.00 |
L001 | Re-bar Work |
2000.000 |
1810.000 |
kg | 1.65 |
0.00 |
3,300.00 |
4,525.00 |
0.00 |
L004 | Ordinary Labour Supply |
100.000 |
100.000 |
nos. | 100.00 |
0.00 |
10,000.00 |
12,000.00 |
0.00 |
L016 | RCC Casting. |
466.158 |
463.192 |
cft | 8.00 |
0.00 |
3,729.26 |
3,705.54 |
0.00 |
L125 | Pile Boring - 500mm dia |
200.141 |
198.501 |
rft | 90.00 |
0.00 |
18,012.69 |
17,865.09 |
0.00 |
M109 | Welding Electrode VM 8-no |
6.000 |
5.430 |
pack | 520.00 |
0.00 |
3,120.00 |
2,715.00 |
0.00 |
M110 | Bentonite |
200.141 |
198.501 |
kg | 20.00 |
0.00 |
4,002.82 |
3,970.02 |
0.00 |
---|---|---|---|---|---|---|---|---|---|
Total: | 211,949.38 |
202,346.11 |
120,879.75 |
;