Costing for BPL RM + PM Warehouse (Sub-structure) | |||||||||
Item | Description | BOQ Qty | Bill Qty | Unit | S.Rate(Tk.) | A.Rate(Tk.) | BOQ Amount | Bill Amount | Con. Amount | A101 | Filling Sand |
123955.650 |
89810.918 |
cft | 8.50 |
5.60 |
1,053,623.03 |
538,865.51 |
568,808.18 |
A102 | Brick |
13251.600 |
10115.629 |
no. | 3.80 |
3.00 |
50,356.08 |
37,427.83 |
83,220.00 |
A103 | Sand - Local - Mymensingh |
882.059 |
466.239 |
cft | 13.00 |
12.00 |
11,466.77 |
6,061.11 |
11,959.56 |
A105 | Cement |
5098.325 |
3994.402 |
bag | 343.00 |
246.00 |
1,748,725.48 |
946,673.27 |
935,292.00 |
A106 | Sand - Sylhet |
9734.581 |
7702.440 |
cft | 24.00 |
16.00 |
233,629.94 |
138,643.92 |
140,849.92 |
A107 | Stone-chips |
19574.109 |
15404.880 |
cft | 80.00 |
70.00 |
1,565,928.72 |
1,001,317.20 |
905,012.50 |
A112 | GI Wire |
1050.000 |
930.390 |
kg | 90.00 |
70.00 |
94,500.00 |
48,380.28 |
210.00 |
A114 | Re-bar G60 |
110250.000 |
97690.950 |
kg | 40.20 |
26.50 |
4,432,050.00 |
2,588,810.18 |
2,588,473.63 |
A136 | Sika Rapid-01 |
0.000 |
0.000 |
kg | 200.00 |
20.00 |
0.00 |
0.00 |
40.00 |
A138 | Plastocrete super-Sika |
6.997 |
0.000 |
kg | 155.00 |
0.00 |
1,084.54 |
0.00 |
0.00 |
E101 | Mini Roller Compaction |
271925.500 |
88459.572 |
cft | 1.00 |
0.00 |
271,925.50 |
53,075.74 |
0.00 |
E102 | Mixer m/c and vibrator |
19469.463 |
16353.141 |
cft | 2.00 |
0.00 |
38,938.93 |
32,706.28 |
0.00 |
E103 | Mini Dumper |
8828.750 |
5472.942 |
cft | 2.00 |
0.00 |
17,657.50 |
10,945.88 |
0.00 |
E106 | Batching Plant , Vibrator |
3284.295 |
1559.510 |
cft | 8.00 |
0.00 |
26,274.36 |
15,595.10 |
0.00 |
E118 | Diesel |
1031.323 |
1381.732 |
Ltr | 26.00 |
20.00 |
26,814.40 |
31,779.84 |
9,320.00 |
E119 | Mobil |
225.016 |
301.469 |
Ltr | 70.00 |
110.00 |
15,751.12 |
21,102.83 |
2,750.00 |
E120 | Hydraulic Oil |
93.757 |
125.612 |
Ltr | 80.00 |
80.00 |
7,500.56 |
10,048.96 |
1,680.00 |
E121 | Break Oil |
0.000 |
0.000 |
tin | 120.00 |
120.00 |
0.00 |
0.00 |
120.00 |
E122 | Grease |
0.000 |
0.000 |
kg | 0.00 |
100.00 |
0.00 |
0.00 |
595.00 |
E127 | Excavator |
18.751 |
25.122 |
day | 8000.00 |
0.00 |
150,008.00 |
200,976.00 |
0.00 |
E131 | Mini Dumper-Sand carrying |
353150.000 |
38748.501 |
cft | 1.00 |
0.00 |
353,150.00 |
19,374.25 |
0.00 |
E137 | Piston Ring, Rubber Cushi |
0.000 |
0.000 |
LS | 99999.99 |
0.00 |
0.00 |
0.00 |
0.00 |
L001 | Re-bar Work |
105000.000 |
93039.000 |
kg | 1.65 |
1.65 |
173,250.00 |
158,166.30 |
142,121.86 |
L002 | Formwork upto 10ft from P |
56348.261 |
44082.313 |
sft | 8.00 |
6.00 |
450,786.09 |
264,493.88 |
213,530.10 |
L004 | Ordinary Labour Supply |
0.000 |
472.540 |
nos. | 100.00 |
95.00 |
0.00 |
44,891.30 |
75,715.00 |
L005 | Head Mason Supply |
0.000 |
236.270 |
nos. | 200.00 |
200.00 |
0.00 |
47,254.00 |
0.00 |
L006 | O.T. (5 hr.) - Labour |
0.000 |
0.000 |
nos. | 50.00 |
50.00 |
0.00 |
0.00 |
3,275.00 |
L008 | Dismentling F/W/Mar tile |
3444.480 |
1147.119 |
sft | 10.00 |
3.00 |
34,444.80 |
3,441.36 |
0.00 |
L009 | Sand Screening |
1412.247 |
670.589 |
cft | 1.00 |
0.00 |
1,412.25 |
670.59 |
0.00 |
L010 | Bitumen Paint |
914.940 |
573.560 |
sft | 1.00 |
3.50 |
914.94 |
573.56 |
0.00 |
L011 | Carpenter Helper |
0.000 |
0.000 |
nos. | 150.00 |
110.00 |
0.00 |
0.00 |
-21,450.00 |
L015 | Carpenter Supply |
0.000 |
0.000 |
nos. | 120.00 |
120.00 |
0.00 |
0.00 |
1,920.00 |
L016 | RCC Casting. |
22601.600 |
17912.651 |
cft | 8.00 |
0.00 |
180,812.80 |
107,475.91 |
0.00 |
L026 | Ceramic B/W+pointing |
0.000 |
0.000 |
sft | 15.00 |
0.00 |
0.00 |
0.00 |
0.00 |
L027 | D.P.C. |
699.660 |
0.000 |
sft | 3.00 |
0.00 |
2,098.98 |
0.00 |
0.00 |
L028 | 125mm thick Brick Work |
107.640 |
0.000 |
sft | 6.00 |
0.00 |
645.84 |
0.00 |
0.00 |
L101 | Earth Work in Excavation |
7769.300 |
6526.212 |
cft | 1.80 |
0.00 |
13,984.74 |
11,747.18 |
0.00 |
L102 | Filling |
706300.000 |
77497.002 |
cft | 1.00 |
0.00 |
706,300.00 |
38,748.50 |
0.00 |
L106 | CC (50mm) With NCF |
706.300 |
0.000 |
sft | 3.00 |
0.00 |
2,118.90 |
0.00 |
0.00 |
L107 | CC Work |
35.315 |
0.000 |
cft | 5.00 |
0.00 |
176.58 |
0.00 |
0.00 |
L135 | Dismantling RCC Pile head |
59.032 |
58.233 |
cft | 30.00 |
0.00 |
1,770.96 |
1,746.99 |
0.00 |
M102 | Steel Forms |
10723.400 |
4756.507 |
sft | 5.00 |
0.00 |
53,617.00 |
23,782.54 |
0.00 |
M106 | Steel Scaffolding |
1.076 |
0.000 |
set | 100.00 |
0.00 |
107.60 |
0.00 |
0.00 |
M123 | Steel pipe with B-plate |
0.000 |
0.000 |
no | 11.00 |
0.00 |
0.00 |
0.00 |
0.00 |
M124 | wood use 5-time-Garjan |
72.643 |
66.112 |
cft | 850.00 |
0.00 |
61,746.55 |
56,195.20 |
0.00 |
M125 | B-plate with pipe |
0.000 |
0.000 |
no | 16.00 |
0.00 |
0.00 |
0.00 |
0.00 |
M126 | Wood shutter-3time |
7.766 |
0.000 |
cft | 350.00 |
0.00 |
2,718.10 |
0.00 |
0.00 |
M127 | Steel form,S-structure |
45624.861 |
39325.806 |
sft | 10.00 |
0.00 |
456,248.61 |
393,258.06 |
0.00 |
M128 | Steel beam,S-structure |
0.000 |
0.000 |
no | 40.00 |
0.00 |
0.00 |
0.00 |
0.00 |
M129 | Stone Cutting Disc - 175 |
59.032 |
58.233 |
no | 70.00 |
0.00 |
4,132.24 |
4,076.31 |
0.00 |
M130 | Diamond Cuting Disc- 175 |
5.903 |
5.823 |
no | 2200.00 |
0.00 |
12,986.60 |
12,810.60 |
0.00 |
M132 | Wood use-6time mango |
172.125 |
157.104 |
cft | 350.00 |
0.00 |
60,243.75 |
54,986.40 |
0.00 |
M133 | Cheisel - Hammer |
59.032 |
58.233 |
no | 55.00 |
0.00 |
3,246.76 |
3,202.82 |
0.00 |
S259 | MS Round Shutter Supply |
0.000 |
0.000 |
sft | 145.00 |
145.00 |
0.00 |
0.00 |
5,333.10 |
---|---|---|---|---|---|---|---|---|---|
Total: | 12,323,148.99 |
9,453,523.07 |
5,668,775.85 |
;