Costing for BPL RM + PM Warehouse (Sub-structure)
Item Description BOQ Qty Bill Qty Unit S.Rate(Tk.) A.Rate(Tk.) BOQ Amount Bill Amount Con. Amount
A101
Filling Sand
123955.650
89810.918
cft
8.50
5.60
1,053,623.03
538,865.51
568,808.18
A102
Brick
13251.600
10115.629
no.
3.80
3.00
50,356.08
37,427.83
83,220.00
A103
Sand - Local - Mymensingh
882.059
466.239
cft
13.00
12.00
11,466.77
6,061.11
11,959.56
A105
Cement
5098.325
3994.402
bag
343.00
246.00
1,748,725.48
946,673.27
935,292.00
A106
Sand - Sylhet
9734.581
7702.440
cft
24.00
16.00
233,629.94
138,643.92
140,849.92
A107
Stone-chips
19574.109
15404.880
cft
80.00
70.00
1,565,928.72
1,001,317.20
905,012.50
A112
GI Wire
1050.000
930.390
kg
90.00
70.00
94,500.00
48,380.28
210.00
A114
Re-bar G60
110250.000
97690.950
kg
40.20
26.50
4,432,050.00
2,588,810.18
2,588,473.63
A136
Sika Rapid-01
0.000
0.000
kg
200.00
20.00
0.00
0.00
40.00
A138
Plastocrete super-Sika
6.997
0.000
kg
155.00
0.00
1,084.54
0.00
0.00
E101
Mini Roller Compaction
271925.500
88459.572
cft
1.00
0.00
271,925.50
53,075.74
0.00
E102
Mixer m/c and vibrator
19469.463
16353.141
cft
2.00
0.00
38,938.93
32,706.28
0.00
E103
Mini Dumper
8828.750
5472.942
cft
2.00
0.00
17,657.50
10,945.88
0.00
E106
Batching Plant , Vibrator
3284.295
1559.510
cft
8.00
0.00
26,274.36
15,595.10
0.00
E118
Diesel
1031.323
1381.732
Ltr
26.00
20.00
26,814.40
31,779.84
9,320.00
E119
Mobil
225.016
301.469
Ltr
70.00
110.00
15,751.12
21,102.83
2,750.00
E120
Hydraulic Oil
93.757
125.612
Ltr
80.00
80.00
7,500.56
10,048.96
1,680.00
E121
Break Oil
0.000
0.000
tin
120.00
120.00
0.00
0.00
120.00
E122
Grease
0.000
0.000
kg
0.00
100.00
0.00
0.00
595.00
E127
Excavator
18.751
25.122
day
8000.00
0.00
150,008.00
200,976.00
0.00
E131
Mini Dumper-Sand carrying
353150.000
38748.501
cft
1.00
0.00
353,150.00
19,374.25
0.00
E137
Piston Ring, Rubber Cushi
0.000
0.000
LS
99999.99
0.00
0.00
0.00
0.00
L001
Re-bar Work
105000.000
93039.000
kg
1.65
1.65
173,250.00
158,166.30
142,121.86
L002
Formwork upto 10ft from P
56348.261
44082.313
sft
8.00
6.00
450,786.09
264,493.88
213,530.10
L004
Ordinary Labour Supply
0.000
472.540
nos.
100.00
95.00
0.00
44,891.30
75,715.00
L005
Head Mason Supply
0.000
236.270
nos.
200.00
200.00
0.00
47,254.00
0.00
L006
O.T. (5 hr.) - Labour
0.000
0.000
nos.
50.00
50.00
0.00
0.00
3,275.00
L008
Dismentling F/W/Mar tile
3444.480
1147.119
sft
10.00
3.00
34,444.80
3,441.36
0.00
L009
Sand Screening
1412.247
670.589
cft
1.00
0.00
1,412.25
670.59
0.00
L010
Bitumen Paint
914.940
573.560
sft
1.00
3.50
914.94
573.56
0.00
L011
Carpenter Helper
0.000
0.000
nos.
150.00
110.00
0.00
0.00
-21,450.00
L015
Carpenter Supply
0.000
0.000
nos.
120.00
120.00
0.00
0.00
1,920.00
L016
RCC Casting.
22601.600
17912.651
cft
8.00
0.00
180,812.80
107,475.91
0.00
L026
Ceramic B/W+pointing
0.000
0.000
sft
15.00
0.00
0.00
0.00
0.00
L027
D.P.C.
699.660
0.000
sft
3.00
0.00
2,098.98
0.00
0.00
L028
125mm thick Brick Work
107.640
0.000
sft
6.00
0.00
645.84
0.00
0.00
L101
Earth Work in Excavation
7769.300
6526.212
cft
1.80
0.00
13,984.74
11,747.18
0.00
L102
Filling
706300.000
77497.002
cft
1.00
0.00
706,300.00
38,748.50
0.00
L106
CC (50mm) With NCF
706.300
0.000
sft
3.00
0.00
2,118.90
0.00
0.00
L107
CC Work
35.315
0.000
cft
5.00
0.00
176.58
0.00
0.00
L135
Dismantling RCC Pile head
59.032
58.233
cft
30.00
0.00
1,770.96
1,746.99
0.00
M102
Steel Forms
10723.400
4756.507
sft
5.00
0.00
53,617.00
23,782.54
0.00
M106
Steel Scaffolding
1.076
0.000
set
100.00
0.00
107.60
0.00
0.00
M123
Steel pipe with B-plate
0.000
0.000
no
11.00
0.00
0.00
0.00
0.00
M124
wood use 5-time-Garjan
72.643
66.112
cft
850.00
0.00
61,746.55
56,195.20
0.00
M125
B-plate with pipe
0.000
0.000
no
16.00
0.00
0.00
0.00
0.00
M126
Wood shutter-3time
7.766
0.000
cft
350.00
0.00
2,718.10
0.00
0.00
M127
Steel form,S-structure
45624.861
39325.806
sft
10.00
0.00
456,248.61
393,258.06
0.00
M128
Steel beam,S-structure
0.000
0.000
no
40.00
0.00
0.00
0.00
0.00
M129
Stone Cutting Disc - 175
59.032
58.233
no
70.00
0.00
4,132.24
4,076.31
0.00
M130
Diamond Cuting Disc- 175
5.903
5.823
no
2200.00
0.00
12,986.60
12,810.60
0.00
M132
Wood use-6time mango
172.125
157.104
cft
350.00
0.00
60,243.75
54,986.40
0.00
M133
Cheisel - Hammer
59.032
58.233
no
55.00
0.00
3,246.76
3,202.82
0.00
S259
MS Round Shutter Supply
0.000
0.000
sft
145.00
145.00
0.00
0.00
5,333.10
Total:
12,323,148.99
9,453,523.07
5,668,775.85