BOQ (Press Item for Analysis)

BOQ for Brick wall and Fencing for Boundary wall
Item Description Quantity Unit Rate(Tk) Amount(Tk)
01
Reinforced cement concrete work(1:2.4) in Grade Beam having minimum crushing strength 20 Mpa (cylinder) at 28 days with Holcim Cement, 20mm down graded stone chips, sand (F.M.not less than 1.8 ) including washing, breaking of chips, screening of sand, mixing, laying, compacting, maintaining levels, curing for minimum 28 days etc. all complete as per direction of the Engineering -in-charge .
45.00
M3
8200.00
369,000.00
01B
27.00
M3
8200.00
221,400.00
02
1650.00
M2
810.00
1,336,500.00
03
3300.00
M2
65.00
214,500.00
04
Supplying and fabrication of deformed bar of Grade 60 with minimum Fy=415 Mpa of different sizes and length in all R.C.C works including straightening, cutting, bending, binding, making of chairs and placing of spacers with supply of G.I wire(22 BWG) and welding, placing in positing where specific, hooking, cranking. lapping etc. all complete as per drawing, specification and direction of the Engineer M.S. Road (fy=415 Mpa)
13.00
TON
52500.00
682,500.00
05
510.00
M2
4500.00
2,295,000.00
06
190.00
NO
155.00
29,450.00
07
Weather coat painting of best quality & approved colour to outside walls and other places where necessary over a coat of primer after cleaning, sand papering the surface as per manufacturer,s specification all complete as per direction of the EIC.
800.00
M2
120.00
96,000.00
Total:
5,244,350.00