BOQ (Press Item for Analysis)

BOQ for BEL Store At Technology Park
Item Description Quantity Unit Rate(Tk) Amount(Tk)
01
Earth work in excavation of foundation trenches of any dimension upto required depth including removal of soil to a required distance within the site with necessary shoring and bailing out of water, if necessary as per drawing and instruction of the EIC.
10.00
M3
78.00
780.00
02
Back filling (excluding sand Supply)
160.00
M3
65.00
10,400.00
03
Single layer (3") 1st class ordinary brick flat soling in floor and other places where necessary including sorting and soaking of bricks, Levelling, laying & filling the intertstices with sand as per direction of EIC.
100.00
M2
136.00
13,600.00
04
Supplying and laying of single layer polythene sheet weighing one Kilogram per 6.5 square metre (min. 0.05 mm thick) in floor and foundation above the brick flat soling all complete as per direction of Engineer-in-charge.
100.00
M2
13.00
1,300.00
05
95.00
M2
230.00
21,850.00
06
250 mm thick ordinary brick work (1:5) including supplying of bricks, sorting and soaking of bricks (minimum 24 hours), curing for min 10 days. Bricks to be soaked for 24 hours in two stages of 12 hours. Fresh water to be used for each stage of soaking. All complete as per direction of the EIC.
14.00
M3
2506.00
35,084.00
07
50mm thick cement concrete damp proof course (1:1.5:3) in cement concrete with cement, sand (F.M. 1.2), stone chips including breaking chips, screening, mixing, casting, curing and inished etc. ail complete as per drawing, specification and direction of the Engineer.
8.00
M2
184.00
1,472.00
08
125 mm thick ordinary brick work (1:4) including supplying and carrying of bricks, sorting and soaking of bricks (Min 24 hours), curing (Minimum 10 days). Bricks to be soaked for 24 hours in two stages of 12 hours. Fresh water to be used for each stage of soaking. All complete as per drawing and direction of the Engineer-In-Charge.
170.00
M2
412.00
70,040.00
09
2.00
M3
8250.00
16,500.00
10
110.00
M2
295.00
32,450.00
11
MS Angle Purlin including Fabrication.
1.60
TON
45000.00
72,000.00
12
MS Door - Old
9.50
M2
1204.00
11,438.00
13
MS Window - Old
5.00
M2
1140.00
5,700.00
Total:
292,614.00