02B |
Reinforced cement concrete work(1:2.4) in Grade Beam having minimum crushing strength 20 Mpa (cylinder) at 28 days with Holcim Cement, 20mm down graded stone chips, sand (F.M.not less than 1.8 ) including washing, breaking of chips, screening of sand, mixing, laying, compacting, maintaining levels, curing for minimum 28 days etc. all complete as per direction of the Engineering -in-charge .
|
12.00 |
M3 |
6000.00 |
72,000.00 |
04 |
Minimum 12 mm thick cement plaster (1:4) to wall maintaining sharp angle at corners, joints, kobla etc. with steel trowel finish including supplying of all materials, sand screening, curing for minimum 10 days. |
275.00 |
M2 |
80.00 |
22,000.00 |