Project Refurbishment of Upgradation (II) at BIL
Item: 01 (A09G) Dismantle Door,Window,Protection
Basis:1 sft
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Dismantle, Door Window
1.000
sft
3.00
3.00
Sub-Total(L1)
3.00
32.29
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Scaffolding
0.000
set
100.00
0.00
Sub-Total(M1)
0.00
0.00
Total(1)
32.29
Add over head on Total(1)
2.5 %
0.81
Total(2)
33.10
Add Profit on Total(2)
8.0 %
2.65
Total(3)
35.75
Add VAT on Unit Price
4.0 %
1.56
Add Income Tax on Unit Price
4.5 %
1.76
Unit Price
39.07
Say
39
per M2
Item: 02 (A09H) Dismantling of 125mm b/wall
Basis:1 sft
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
0.060
nos.
100.00
6.00
Sub-Total(L0)
6.00
64.58
Total(1)
64.58
Add over head on Total(1)
2.5 %
1.61
Total(2)
66.20
Add Profit on Total(2)
8.0 %
5.30
Total(3)
71.49
Add VAT on Unit Price
4.0 %
3.13
Add Income Tax on Unit Price
4.5 %
3.52
Unit Price
78.14
Say
78
per M2
Item: 03 (A09E5) Dist W-Flr and marble tiles
Basis:1 sft
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Dismentling F/W/Mar tile
1.000
sft
10.00
10.00
Sub-Total(L0)
10.00
107.64
Total(1)
107.64
Add over head on Total(1)
2.5 %
2.69
Total(2)
110.33
Add Profit on Total(2)
8.0 %
8.83
Total(3)
119.16
Add VAT on Unit Price
4.0 %
5.21
Add Income Tax on Unit Price
4.5 %
5.86
Unit Price
130.23
Say
130
per M2
Item: 04 (A06F) 125 B/Wall (1:4)
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
500.000
no.
3.80
1900.00
Sand - Local - Mymensingh
17.000
cft
13.00
221.00
Cement
3.000
bag
343.00
1029.00
Sub-Total(A1)
3150.00
339.07
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
125mm thick Brick Work
100.000
sft
6.00
600.00
Sub-Total(L0)
600.00
64.58
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Scaffolding
0.000
set
100.00
0.00
Sub-Total(M1)
0.00
0.00
Total(1)
403.65
Add over head on Total(1)
2.5 %
10.09
Total(2)
413.74
Add Profit on Total(2)
8.0 %
33.10
Total(3)
446.84
Add VAT on Unit Price
4.0 %
19.53
Add Income Tax on Unit Price
4.5 %
21.98
Unit Price
488.35
Say
488
per M2
Item: 05 (A06C) 250mm thick B-wall (1:5) - Supers
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
1200.000
no.
3.80
4560.00
Sand - Local - Mymensingh
40.000
cft
13.00
520.00
Cement
6.000
bag
343.00
2058.00
Sub-Total(A1)
7138.00
2520.78
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
B/w:15.5-27ft Scffld(Part
100.000
cft
6.00
600.00
Sub-Total(L0)
600.00
211.89
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Scaffolding
1.000
set
100.00
100.00
Sub-Total(M1)
100.00
35.32
Total(1)
2767.99
Add over head on Total(1)
2.5 %
69.20
Total(2)
2837.19
Add Profit on Total(2)
8.0 %
226.98
Total(3)
3064.16
Add VAT on Unit Price
4.0 %
133.95
Add Income Tax on Unit Price
4.5 %
150.70
Unit Price
3348.81
Say
3349
per M3
Item: 06 (A12A) Plaster(1:5) 20mm thick
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
8.250
cft
13.00
107.25
Cement
1.100
bag
343.00
377.30
Sub-Total(A1)
484.55
52.16
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
OutPlaster 30.5ft
100.000
sft
4.50
450.00
Sub-Total(L0)
450.00
48.44
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Scaffolding
1.500
set
100.00
150.00
Sub-Total(M1)
150.00
16.15
Total(1)
116.74
Add over head on Total(1)
2.5 %
2.92
Total(2)
119.66
Add Profit on Total(2)
8.0 %
9.57
Total(3)
129.23
Add VAT on Unit Price
4.0 %
5.65
Add Income Tax on Unit Price
4.5 %
6.36
Unit Price
141.24
Say
141
per M2
Item: 07 (A13E) Plastic paint
Basis:100 sft
A3.Material-Paint
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Plastron Sealer
0.800
Ltr
160.00
128.00
Plastic Emulsion
1.330
Ltr
170.00
226.10
Enamel paint
0.610
Ltr
170.00
103.70
Snowcel
2.500
kg
7.60
19.00
Thinner-T6/T7
0.800
Ltr
46.00
36.80
Water Paper
0.500
nos
40.00
20.00
Chalk powder
2.500
kg
18.00
45.00
Mosaic stone
0.100
no
110.00
11.00
Sub-Total(A3)
589.60
63.46
L6.Labour Paints
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Plastic Painting
100.000
sft
2.50
250.00
Sub-Total(L6)
250.00
26.91
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Scaffolding
1.000
set
100.00
100.00
Sub-Total(M1)
100.00
10.76
Total(1)
101.14
Add over head on Total(1)
2.5 %
2.53
Total(2)
103.67
Add Profit on Total(2)
8.0 %
8.29
Total(3)
111.96
Add VAT on Unit Price
4.0 %
4.89
Add Income Tax on Unit Price
4.5 %
5.51
Unit Price
122.36
Say
122
per M2
Item: 08 (A13G) Epoxy paint to wall (New)
Basis:100 sft
A3.Material-Paint
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Epoxy Primer
2.000
Ltr
170.00
340.00
Epoxy Enamel
3.080
Ltr
387.00
1191.96
Thinner-T6/T7
1.600
Ltr
46.00
73.60
Chalk powder
1.330
kg
18.00
23.94
Mosaic stone
0.200
no
110.00
22.00
Scrap
1.000
L.s
30.00
30.00
Sub-Total(A3)
1681.50
181.00
L6.Labour Paints
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Epoxy Paint to wall
100.000
sft
10.00
1000.00
Sub-Total(L6)
1000.00
107.64
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Scaffolding
1.000
set
100.00
100.00
Sub-Total(M1)
100.00
10.76
Total(1)
299.40
Add over head on Total(1)
2.5 %
7.49
Total(2)
306.89
Add Profit on Total(2)
8.0 %
24.55
Total(3)
331.44
Add VAT on Unit Price
4.0 %
14.49
Add Income Tax on Unit Price
4.5 %
16.30
Unit Price
362.23
Say
362
per M2
Item: 09 (A07C) Homogenous Floor Tiles
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
6.250
cft
13.00
81.25
Cement
2.500
bag
343.00
857.50
White-Cement
3.600
kg
16.25
58.50
Sub-Total(A1)
997.25
107.34
A2.Material-Mosaic/Tile
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Homogenious Tiles
110.000
sft
46.00
5060.00
Sub-Total(A2)
5060.00
544.66
L2.Labour-Tile/Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Floor/ Wall Tiles fitting
100.000
sft
20.00
2000.00
Sub-Total(L2)
2000.00
215.28
Total(1)
867.28
Add over head on Total(1)
2.5 %
21.68
Total(2)
888.96
Add Profit on Total(2)
8.0 %
71.12
Total(3)
960.08
Add VAT on Unit Price
4.0 %
41.97
Add Income Tax on Unit Price
4.5 %
47.22
Unit Price
1049.27
Say
1049
per M2
Item: 10 (A07A) Glazed Wall Tiles
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
7.030
cft
13.00
91.39
Cement
1.870
bag
343.00
641.41
White-Cement
3.600
kg
16.25
58.50
Sub-Total(A1)
791.30
85.18
A2.Material-Mosaic/Tile
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Glazed Wall Tiles-RAK
105.000
sft
36.00
3780.00
Sub-Total(A2)
3780.00
406.88
L2.Labour-Tile/Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Floor/ Wall Tiles fitting
100.000
sft
20.00
2000.00
Sub-Total(L2)
2000.00
215.28
Total(1)
707.33
Add over head on Total(1)
2.5 %
17.68
Total(2)
725.02
Add Profit on Total(2)
8.0 %
58.00
Total(3)
783.02
Add VAT on Unit Price
4.0 %
34.23
Add Income Tax on Unit Price
4.5 %
38.51
Unit Price
855.76
Say
856
per M2
Item: 11 (A14A) Laminated Gypsum Board Ceiling
Basis:100 sft
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Scaffolding
1.000
set
100.00
100.00
Sub-Total(M1)
100.00
10.76
S2.Alum,SS/MS,FalseCeil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Lamint GypsumBoardCeiling
100.000
sft
42.00
4200.00
Sub-Total(S2)
4200.00
452.09
Total(1)
462.85
Add over head on Total(1)
2.5 %
11.57
Total(2)
474.42
Add Profit on Total(2)
8.0 %
37.95
Total(3)
512.38
Add VAT on Unit Price
4.0 %
22.40
Add Income Tax on Unit Price
4.5 %
25.20
Unit Price
559.98
Say
560
per M2
Item: 12 (A11C) Alum (PC) Sliding/fixed window
Basis:1 sft
S2.Alum,SS/MS,FalseCeil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Alum.Fixed Window-PowdrCt
1.000
sft
175.00
175.00
Sub-Total(S2)
175.00
1883.70
Total(1)
1883.70
Add over head on Total(1)
2.5 %
47.09
Total(2)
1930.79
Add Profit on Total(2)
8.0 %
154.46
Total(3)
2085.26
Add VAT on Unit Price
4.0 %
91.16
Add Income Tax on Unit Price
4.5 %
102.55
Unit Price
2278.97
Say
2279
per M2
Item: 13 (A11G) Alum(PC) swing door Plastic-Glass
Basis:1 sft
S2.Alum,SS/MS,FalseCeil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Alum.Swing doorGlass-Plas
1.000
sft
470.00
470.00
Sub-Total(S2)
470.00
5059.08
Total(1)
5059.08
Add over head on Total(1)
2.5 %
126.48
Total(2)
5185.56
Add Profit on Total(2)
8.0 %
414.84
Total(3)
5600.40
Add VAT on Unit Price
4.0 %
244.83
Add Income Tax on Unit Price
4.5 %
275.43
Unit Price
6120.66
Say
6121
per M2
Item: 14 (A11S) PVC Door i/c Lock(750)
Basis:1 no.
S2.Alum,SS/MS,FalseCeil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
PVC Door
1.000
no.
3000.00
3000.00
Sub-Total(S2)
3000.00
3000.00
Total(1)
3000.00
Add over head on Total(1)
2.5 %
75.00
Total(2)
3075.00
Add Profit on Total(2)
8.0 %
246.00
Total(3)
3321.00
Add VAT on Unit Price
4.0 %
145.18
Add Income Tax on Unit Price
4.5 %
163.33
Unit Price
3629.51
Say
3630
per NO
Item: 15A (B01B) uPVC Pipe 100 dia
Basis:300 rft
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
uPVC Pipe 100mm dia
315.000
rft
58.00
18270.00
Solvent cement -500 ml
8.000
pot
490.00
3920.00
uPVC Plainn Tee-100mm Dia
16.000
no.
278.00
4448.00
uPVC Long Trap - 100mm Di
6.000
no.
370.00
2220.00
uPVC Door Bend - 100mm di
24.000
no.
290.00
6960.00
uPVC Bend 45D -100mm dia
6.000
no.
175.00
1050.00
Sub-Total(B1)
36868.00
3000.00
L4.Labour-Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
uPVC Pipe fitting-100 mm
300.000
rft
15.00
4500.00
Sub-Total(L4)
4500.00
3000.00
Total(1)
6000.00
Add over head on Total(1)
2.5 %
150.00
Total(2)
6150.00
Add Profit on Total(2)
8.0 %
492.00
Total(3)
6642.00
Add VAT on Unit Price
4.0 %
290.36
Add Income Tax on Unit Price
4.5 %
326.66
Unit Price
7259.02
Say
7259
per RM
Item: 15B (B01C) uPVc pipe 50 dia
Basis:100 rft
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
uPVc pipe 50 dia
105.000
rft
25.00
2625.00
uPVC Bend - 50mm dia
16.000
no.
47.00
752.00
Sub-Total(B1)
3377.00
3000.00
L4.Labour-Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
uPVC pipe - 50mm
100.000
rft
15.00
1500.00
Sub-Total(L4)
1500.00
3000.00
Total(1)
6000.00
Add over head on Total(1)
2.5 %
150.00
Total(2)
6150.00
Add Profit on Total(2)
8.0 %
492.00
Total(3)
6642.00
Add VAT on Unit Price
4.0 %
290.36
Add Income Tax on Unit Price
4.5 %
326.66
Unit Price
7259.02
Say
7259
per RM
Item: 15C (B01C1) uPVC Pipe 38mm dia
Basis:75 rft
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
uPVC Bend - 50mm dia
20.000
no.
47.00
940.00
uPVC Pipe - 40mm dia
78.750
rft
16.25
1279.69
Sub-Total(B1)
2219.69
3000.00
L4.Labour-Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
uPVC Pipe fitting 37mm di
75.000
rft
5.00
375.00
Sub-Total(L4)
375.00
3000.00
Total(1)
6000.00
Add over head on Total(1)
2.5 %
150.00
Total(2)
6150.00
Add Profit on Total(2)
8.0 %
492.00
Total(3)
6642.00
Add VAT on Unit Price
4.0 %
290.36
Add Income Tax on Unit Price
4.5 %
326.66
Unit Price
7259.02
Say
7259
per RM
Item: 16A (B15O) 40mm dia GI pipe
Basis:50 rft
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
GI Pipe-40mm dia
52.500
rft
90.00
4725.00
40mm dia G-Valve
1.000
No
410.00
410.00
40mm dia Tee
20.000
No
65.00
1300.00
40mm Union
1.000
No
70.00
70.00
Tread Tape
6.000
Dezn
120.00
720.00
Sub-Total(B1)
7225.00
3000.00
L4.Labour-Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
G.I Pipe fitting 37mm dia
50.000
rft
13.00
650.00
11/2" dia G.I gate valve
1.000
No
40.00
40.00
Sub-Total(L4)
690.00
3000.00
Total(1)
6000.00
Add over head on Total(1)
2.5 %
150.00
Total(2)
6150.00
Add Profit on Total(2)
8.0 %
492.00
Total(3)
6642.00
Add VAT on Unit Price
4.0 %
290.36
Add Income Tax on Unit Price
4.5 %
326.66
Unit Price
7259.02
Say
7259
per RM
Item: 16B (B15A3) 25mm dia GI Pipe
Basis:100 rft
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
GI Pipe - 25mm dia
105.000
rft
50.00
5250.00
Tread Tape
6.000
Dezn
120.00
720.00
25mm G-Valve
1.000
No
230.00
230.00
25mm Union
1.000
No
50.00
50.00
25mm El-bow
25.000
No
25.00
625.00
Sub-Total(B1)
6875.00
3000.00
B2.Sanitary fittings
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
GI Fittings - 25mm dia
100.000
rft
5.00
500.00
Sub-Total(B2)
500.00
3000.00
L4.Labour-Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
GI Pipe fiting - 25mm dia
1.000
rft
11.00
11.00
1" dia G.I gate Valve
1.000
No
35.00
35.00
Sub-Total(L4)
46.00
3000.00
Total(1)
9000.00
Add over head on Total(1)
2.5 %
225.00
Total(2)
9225.00
Add Profit on Total(2)
8.0 %
738.00
Total(3)
9963.00
Add VAT on Unit Price
4.0 %
435.54
Add Income Tax on Unit Price
4.5 %
489.98
Unit Price
10888.52
Say
10889
per RM
Item: 16C (B15) 20mm dia G.I pipe
Basis:160 rft
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
20mm G.I pipe
168.000
rft
40.00
6720.00
Tread Tape
9.000
Dezn
120.00
1080.00
20mm G-Valve
4.000
No
235.00
940.00
20mm Tee
40.000
No
25.00
1000.00
20mm Union
4.000
No
35.00
140.00
Sub-Total(B1)
9880.00
3000.00
L4.Labour-Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
GI Pipe fitting - 20mm di
160.000
rft
10.00
1600.00
GI Gate Valve fitting 20
4.000
No
30.00
120.00
Sub-Total(L4)
1720.00
3000.00
Total(1)
6000.00
Add over head on Total(1)
2.5 %
150.00
Total(2)
6150.00
Add Profit on Total(2)
8.0 %
492.00
Total(3)
6642.00
Add VAT on Unit Price
4.0 %
290.36
Add Income Tax on Unit Price
4.5 %
326.66
Unit Price
7259.02
Say
7259
per RM
Item: 16D (B15A) 12mm dia G.I pipe
Basis:160 rft
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
12mm G.I pipe
168.000
rft
30.00
5040.00
Tread Tape
9.000
Dezn
120.00
1080.00
12mm G-Valve
4.000
No
160.00
640.00
12mm Tee
100.000
No
12.00
1200.00
12mm Union
10.000
No
10.00
100.00
Sub-Total(B1)
8060.00
3000.00
L4.Labour-Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
GI Pipe fitting - 12mmdia
160.000
rft
9.00
1440.00
Sub-Total(L4)
1440.00
3000.00
Total(1)
6000.00
Add over head on Total(1)
2.5 %
150.00
Total(2)
6150.00
Add Profit on Total(2)
8.0 %
492.00
Total(3)
6642.00
Add VAT on Unit Price
4.0 %
290.36
Add Income Tax on Unit Price
4.5 %
326.66
Unit Price
7259.02
Say
7259
per RM
Item: 17 (A22B) Ins. pit B type 750x750-in-in
Basis:1 no.
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
32.000
no.
3.80
121.60
Sand - Local - Mymensingh
3.780
cft
13.00
49.14
Polythene
0.180
kg
77.00
13.86
Cement
4.740
bag
343.00
1625.82
Sand - Sylhet
6.000
cft
24.00
144.00
Stone-chips
17.900
cft
80.00
1432.00
Re-bar - G40
48.300
kg
38.50
1859.55
GI Wire
0.330
kg
90.00
29.70
Sub-Total(A1)
5275.67
5275.67
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
CI Cover 300 mm dia
1.000
no.
750.00
750.00
Sub-Total(B1)
750.00
750.00
C1.Steel Structures
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Galvanized Angle 38x38
2.580
rft
125.00
322.50
MS Grating 200x75
1.000
no.
100.00
100.00
Sub-Total(C1)
422.50
422.50
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
20.490
cft
2.00
40.98
Sub-Total(E1)
40.98
40.98
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Re-bar Work
46.000
kg
1.65
75.90
Formwork upto 10ft from P
53.740
sft
8.00
429.92
Dismentling F/W/Mar tile
16.140
sft
10.00
161.40
Neat Cement Finishing
16.140
sft
1.00
16.14
RCC Casting.
20.490
cft
8.00
163.92
Sub-Total(L0)
847.28
847.28
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Earth Work in Excavation
83.160
cft
1.80
149.69
Filling
42.450
cft
1.00
42.45
Brck flat soling
11.860
sft
0.60
7.12
Patent stone with NCF
4.035
sft
3.00
12.11
Sub-Total(L1)
211.36
211.36
L4.Labour-Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Manhole Cover fixing
1.000
no.
300.00
300.00
Sub-Total(L4)
300.00
300.00
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Forms
53.740
sft
5.00
268.70
Sub-Total(M1)
268.70
268.70
Total(1)
8116.49
Add over head on Total(1)
2.5 %
202.91
Total(2)
8319.40
Add Profit on Total(2)
8.0 %
665.55
Total(3)
8984.95
Add VAT on Unit Price
4.0 %
392.78
Add Income Tax on Unit Price
4.5 %
441.88
Unit Price
9819.62
Say
9820
per NO
Item: 18 (B15F) L-pan BISF Standerd
Basis:1 no.
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Long pan BISF with fittin
1.000
no
850.00
850.00
C.I Cistern
1.000
no
1050.00
1050.00
Connecting pipe
1.000
no
150.00
150.00
Sub-Total(B1)
2050.00
2050.00
L4.Labour-Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Long Pan fitting
1.000
no.
250.00
250.00
Cistern fitting
1.000
no
100.00
100.00
CI Trap fitting
1.000
no
100.00
100.00
Sub-Total(L4)
450.00
450.00
Total(1)
2500.00
Add over head on Total(1)
2.5 %
62.50
Total(2)
2562.50
Add Profit on Total(2)
8.0 %
205.00
Total(3)
2767.50
Add VAT on Unit Price
4.0 %
120.98
Add Income Tax on Unit Price
4.5 %
136.11
Unit Price
3024.59
Say
3025
per NO
Item: 19 (B15F1) Commode - BISF
Basis:1 no.
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Connecting pipe
1.000
no
150.00
150.00
Commode BISF
1.000
no.
3500.00
3500.00
Sub-Total(B1)
3650.00
3650.00
L4.Labour-Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Commode fitting
1.000
no.
200.00
200.00
Sub-Total(L4)
200.00
200.00
Total(1)
3850.00
Add over head on Total(1)
2.5 %
96.25
Total(2)
3946.25
Add Profit on Total(2)
8.0 %
315.70
Total(3)
4261.95
Add VAT on Unit Price
4.0 %
186.31
Add Income Tax on Unit Price
4.5 %
209.60
Unit Price
4657.87
Say
4658
per NO
Item: 20 (B15Q) Standing Urinal with flush
Basis:1 no.
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Standing Uri- with flush
1.000
No
3500.00
3500.00
Sub-Total(B1)
3500.00
3500.00
L4.Labour-Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Standing Urrinal
1.000
No
200.00
200.00
Sub-Total(L4)
200.00
200.00
Total(1)
3700.00
Add over head on Total(1)
2.5 %
92.50
Total(2)
3792.50
Add Profit on Total(2)
8.0 %
303.40
Total(3)
4095.90
Add VAT on Unit Price
4.0 %
179.06
Add Income Tax on Unit Price
4.5 %
201.44
Unit Price
4476.39
Say
4476
per NO
Item: 21 (B15S) Mirror Glass
Basis:1 sft
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mirror glass
1.000
Sft
100.00
100.00
Sub-Total(B1)
100.00
1076.40
Total(1)
1076.40
Add over head on Total(1)
2.5 %
26.91
Total(2)
1103.31
Add Profit on Total(2)
8.0 %
88.26
Total(3)
1191.57
Add VAT on Unit Price
4.0 %
52.09
Add Income Tax on Unit Price
4.5 %
58.60
Unit Price
1302.27
Say
1302
per M2
Item: 22 (B15B) CP angle stop cock N-64
Basis:1 no.
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Angle stop cock
1.000
no
350.00
350.00
Sub-Total(B1)
350.00
350.00
L4.Labour-Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Stop cock fitting
1.000
no
50.00
50.00
Sub-Total(L4)
50.00
50.00
Total(1)
400.00
Add over head on Total(1)
2.5 %
10.00
Total(2)
410.00
Add Profit on Total(2)
8.0 %
32.80
Total(3)
442.80
Add VAT on Unit Price
4.0 %
19.36
Add Income Tax on Unit Price
4.5 %
21.78
Unit Price
483.93
Say
484
per NO
Item: 23 (B15C) CP Piller cock N-42
Basis:1 no.
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Piller cock
1.000
no
410.00
410.00
Sub-Total(B1)
410.00
410.00
L4.Labour-Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Piller cock1
1.000
no
50.00
50.00
Sub-Total(L4)
50.00
50.00
Total(1)
460.00
Add over head on Total(1)
2.5 %
11.50
Total(2)
471.50
Add Profit on Total(2)
8.0 %
37.72
Total(3)
509.22
Add VAT on Unit Price
4.0 %
22.26
Add Income Tax on Unit Price
4.5 %
25.04
Unit Price
556.52
Say
557
per NO
Item: 24 (B15D) Bib cock N-54
Basis:1 no.
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Bib cock
1.000
no
380.00
380.00
Sub-Total(B1)
380.00
380.00
L4.Labour-Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Bib Cock fitting
1.000
no.
50.00
50.00
Sub-Total(L4)
50.00
50.00
Total(1)
430.00
Add over head on Total(1)
2.5 %
10.75
Total(2)
440.75
Add Profit on Total(2)
8.0 %
35.26
Total(3)
476.01
Add VAT on Unit Price
4.0 %
20.81
Add Income Tax on Unit Price
4.5 %
23.41
Unit Price
520.23
Say
520
per NO
Item: 25 (B15R) Moving shower
Basis:1 no.
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Moving shower
1.000
No
1200.00
1200.00
Sub-Total(B1)
1200.00
1200.00
Total(1)
1200.00
Add over head on Total(1)
2.5 %
30.00
Total(2)
1230.00
Add Profit on Total(2)
8.0 %
98.40
Total(3)
1328.40
Add VAT on Unit Price
4.0 %
58.07
Add Income Tax on Unit Price
4.5 %
65.33
Unit Price
1451.80
Say
1452
per NO
Item: 26 (B15K) C.I Gratting 100 dia
Basis:1 no.
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
100mm dia CI gratting
1.000
no
150.00
150.00
Sub-Total(B1)
150.00
150.00
L4.Labour-Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
CP Gratting fitting
1.000
no
45.00
45.00
Sub-Total(L4)
45.00
45.00
Total(1)
195.00
Add over head on Total(1)
2.5 %
4.88
Total(2)
199.88
Add Profit on Total(2)
8.0 %
15.99
Total(3)
215.87
Add VAT on Unit Price
4.0 %
9.44
Add Income Tax on Unit Price
4.5 %
10.62
Unit Price
235.92
Say
236
per NO
Item: 27I (A09N) Slab, false slab (1:1.5:3)
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
14.333
cft
13.00
186.33
Cement
22.000
bag
343.00
7546.00
Sand - Sylhet
28.667
cft
24.00
688.01
Stone-chips
86.000
cft
80.00
6880.00
Sub-Total(A1)
15300.34
5403.31
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
100.000
cft
2.00
200.00
Sub-Total(E1)
200.00
70.63
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
RCC Casting-Superstructur
100.000
sft
10.00
1000.00
FormWork:24-33ft from PL
242.000
sft
10.00
2420.00
Sub-Total(L0)
3420.00
1207.77
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Forms
242.000
sft
5.00
1210.00
Steel Scaffolding
4.000
set
100.00
400.00
B-plate with pipe
20.000
no
16.00
320.00
Steel beam,S-structure
12.000
no
40.00
480.00
Sub-Total(M1)
2410.00
851.09
Total(1)
7532.81
Add over head on Total(1)
2.5 %
188.32
Total(2)
7721.13
Add Profit on Total(2)
8.0 %
617.69
Total(3)
8338.82
Add VAT on Unit Price
4.0 %
364.54
Add Income Tax on Unit Price
4.5 %
410.11
Unit Price
9113.46
Say
9113
per M3
Item: 27II (A08Y) Beam, Lintel (1:1.5:3)
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement
22.000
bag
343.00
7546.00
Sand - Sylhet
46.000
cft
24.00
1104.00
Stone-chips
91.000
cft
80.00
7280.00
Sub-Total(A1)
15930.00
5625.68
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
100.000
cft
2.00
200.00
Mini Dumper
100.000
cft
2.00
200.00
Sub-Total(E1)
400.00
141.26
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
1.000
nos.
100.00
100.00
RCC Casting-Superstructur
100.000
sft
10.00
1000.00
FormWork:24-33ft from PL
357.000
sft
10.00
3570.00
Sub-Total(L0)
4670.00
1649.21
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Forms
357.000
sft
5.00
1785.00
Steel pipe with B-plate
15.000
no
11.00
165.00
Wood shutter-3time
2.000
cft
350.00
700.00
Steel beam,S-structure
8.000
no
40.00
320.00
Sub-Total(M1)
2970.00
1048.86
Total(1)
8465.01
Add over head on Total(1)
2.5 %
211.63
Total(2)
8676.63
Add Profit on Total(2)
8.0 %
694.13
Total(3)
9370.76
Add VAT on Unit Price
4.0 %
409.65
Add Income Tax on Unit Price
4.5 %
460.86
Unit Price
10241.27
Say
10241
per M3
Item: 28 (A10A) Re-bar Grade 60
Basis:1000 kg.
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
GI Wire
10.000
kg
90.00
900.00
Re-bar G60
1050.000
kg
40.20
42210.00
Sub-Total(A1)
43110.00
1048.86
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Re-bar Work
1000.000
kg
1.65
1650.00
Local carrying Rod
0.000
kg
0.25
0.00
Sub-Total(L0)
1650.00
1048.86
Total(1)
2097.71
Add over head on Total(1)
2.5 %
52.44
Total(2)
2150.15
Add Profit on Total(2)
8.0 %
172.01
Total(3)
2322.17
Add VAT on Unit Price
4.0 %
101.52
Add Income Tax on Unit Price
4.5 %
114.20
Unit Price
2537.89
Say
2538
per TON