Return Main Menu

Project Infusion Building Upgradation-1
Item: 01 (A09G) Dismantle Door,Window,Protection
Basis:1 sft
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Dismantle, Door Window
1.000
sft
3.00
3.00
Sub-Total(L1)
3.00
32.29
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Scaffolding
0.000
set
100.00
0.00
Sub-Total(M1)
0.00
0.00
Total(1)
32.29
Add over head on Total(1)
2.5 %
0.81
Total(2)
33.10
Add Profit on Total(2)
8.0 %
2.65
Total(3)
35.75
Add VAT on Unit Price
4.0 %
1.56
Add Income Tax on Unit Price
4.5 %
1.76
Unit Price
39.07
Say
39
per M2
Item: 02 (A09F) Dismantling - 250mm Brick Wall
Basis:1 cft
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Dismatle - B/W
1.000
cft
3.50
3.50
Sub-Total(L1)
3.50
123.60
Total(1)
123.60
Add over head on Total(1)
2.5 %
3.09
Total(2)
126.69
Add Profit on Total(2)
8.0 %
10.14
Total(3)
136.83
Add VAT on Unit Price
4.0 %
5.98
Add Income Tax on Unit Price
4.5 %
6.73
Unit Price
149.54
Say
150
per M2
Item: 03 (A06C) 250mm thick B-wall (1:5) - Supers
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
1200.000
no.
3.80
4560.00
Sand - Local - Mymensingh
40.000
cft
13.00
520.00
Cement
6.000
bag
343.00
2058.00
Sub-Total(A1)
7138.00
2520.78
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
B/w:15.5-27ft Scffld(Part
100.000
cft
6.00
600.00
Sub-Total(L0)
600.00
211.89
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Scaffolding
1.000
set
100.00
100.00
Sub-Total(M1)
100.00
35.32
Total(1)
2767.99
Add over head on Total(1)
2.5 %
69.20
Total(2)
2837.19
Add Profit on Total(2)
8.0 %
226.98
Total(3)
3064.16
Add VAT on Unit Price
4.0 %
133.95
Add Income Tax on Unit Price
4.5 %
150.70
Unit Price
3348.81
Say
3349
per M3
Item: 04 (A06F) 125 B/Wall (1:4)
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
500.000
no.
3.80
1900.00
Sand - Local - Mymensingh
17.000
cft
13.00
221.00
Cement
3.000
bag
343.00
1029.00
Sub-Total(A1)
3150.00
339.07
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
125mm thick Brick Work
100.000
sft
6.00
600.00
Sub-Total(L0)
600.00
64.58
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Scaffolding
0.000
set
100.00
0.00
Sub-Total(M1)
0.00
0.00
Total(1)
403.65
Add over head on Total(1)
2.5 %
10.09
Total(2)
413.74
Add Profit on Total(2)
8.0 %
33.10
Total(3)
446.84
Add VAT on Unit Price
4.0 %
19.53
Add Income Tax on Unit Price
4.5 %
21.98
Unit Price
488.35
Say
488
per M2
Item: 05 (A08YC) Lintel Sunshade (1:2:4)
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
22.500
cft
13.00
292.50
Cement
18.000
bag
343.00
6174.00
Sand - Sylhet
22.500
cft
24.00
540.00
Stone-chips
90.000
cft
80.00
7200.00
Sub-Total(A1)
14206.50
5017.03
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
100.000
cft
2.00
200.00
Sub-Total(E1)
200.00
70.63
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
RCC Work
100.000
cft
6.00
600.00
Form work
490.190
sft
8.00
3921.52
Sub-Total(L1)
4521.52
1596.77
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Scaffolding
1.000
set
100.00
100.00
Sub-Total(M1)
100.00
35.32
Total(1)
6719.75
Add over head on Total(1)
2.5 %
167.99
Total(2)
6887.74
Add Profit on Total(2)
8.0 %
551.02
Total(3)
7438.76
Add VAT on Unit Price
4.0 %
325.19
Add Income Tax on Unit Price
4.5 %
365.84
Unit Price
8129.79
Say
8130
per M3
Item: 06 (A10A) Re-bar Grade 60
Basis:1000 kg.
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
GI Wire
10.000
kg
90.00
900.00
Re-bar G60
1050.000
kg
40.20
42210.00
Sub-Total(A1)
43110.00
35.32
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Re-bar Work
1000.000
kg
1.65
1650.00
Local carrying Rod
0.000
kg
0.25
0.00
Sub-Total(L0)
1650.00
35.32
Total(1)
70.63
Add over head on Total(1)
2.5 %
1.77
Total(2)
72.40
Add Profit on Total(2)
8.0 %
5.79
Total(3)
78.19
Add VAT on Unit Price
4.0 %
3.42
Add Income Tax on Unit Price
4.5 %
3.85
Unit Price
85.45
Say
85
per TON
Item: 07 (A12B) Plaster 12mm thick (1:4)
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
7.500
cft
13.00
97.50
Cement
1.000
bag
343.00
343.00
Sub-Total(A1)
440.50
47.42
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Plaster Work
100.000
sft
3.00
300.00
Sub-Total(L1)
300.00
32.29
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Scaffolding
1.000
set
100.00
100.00
Sub-Total(M1)
100.00
10.76
Total(1)
90.47
Add over head on Total(1)
2.5 %
2.26
Total(2)
92.73
Add Profit on Total(2)
8.0 %
7.42
Total(3)
100.15
Add VAT on Unit Price
4.0 %
4.38
Add Income Tax on Unit Price
4.5 %
4.93
Unit Price
109.46
Say
109
per M2
Item: 08 (A13E) Plastic paint
Basis:100 sft
A3.Material-Paint
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Plastron Sealer
0.800
Ltr
160.00
128.00
Plastic Emulsion
1.330
Ltr
170.00
226.10
Enamel paint
0.610
Ltr
170.00
103.70
Snowcel
2.500
kg
7.60
19.00
Thinner-T6/T7
0.800
Ltr
46.00
36.80
Water Paper
0.500
nos
40.00
20.00
Chalk powder
2.500
kg
18.00
45.00
Mosaic stone
0.100
no
110.00
11.00
Sub-Total(A3)
589.60
63.46
L6.Labour Paints
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Plastic Painting
100.000
sft
2.50
250.00
Sub-Total(L6)
250.00
26.91
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Scaffolding
1.000
set
100.00
100.00
Sub-Total(M1)
100.00
10.76
Total(1)
101.14
Add over head on Total(1)
2.5 %
2.53
Total(2)
103.67
Add Profit on Total(2)
8.0 %
8.29
Total(3)
111.96
Add VAT on Unit Price
4.0 %
4.89
Add Income Tax on Unit Price
4.5 %
5.51
Unit Price
122.36
Say
122
per M2
Item: 09 (A13B) Epoxy paint to floor
Basis:100 sft
A3.Material-Paint
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Epoxy Primer
2.000
Ltr
170.00
340.00
Epoxy Enamel
3.080
Ltr
387.00
1191.96
Thinner-T6/T7
1.600
Ltr
46.00
73.60
Chalk powder
1.330
kg
18.00
23.94
Mosaic stone
0.200
no
110.00
22.00
Scrap
1.000
L.s
30.00
30.00
Sub-Total(A3)
1681.50
181.00
L6.Labour Paints
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Epoxy Paint-Floor
100.000
sft
7.00
700.00
Sub-Total(L6)
700.00
75.35
Total(1)
256.34
Add over head on Total(1)
2.5 %
6.41
Total(2)
262.75
Add Profit on Total(2)
8.0 %
21.02
Total(3)
283.77
Add VAT on Unit Price
4.0 %
12.41
Add Income Tax on Unit Price
4.5 %
13.96
Unit Price
310.14
Say
310
per M2
Item: 10 (A13G) Epoxy paint to wall (New)
Basis:100 sft
A3.Material-Paint
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Epoxy Primer
2.000
Ltr
170.00
340.00
Epoxy Enamel
3.080
Ltr
387.00
1191.96
Thinner-T6/T7
1.600
Ltr
46.00
73.60
Chalk powder
1.330
kg
18.00
23.94
Mosaic stone
0.200
no
110.00
22.00
Scrap
1.000
L.s
30.00
30.00
Sub-Total(A3)
1681.50
181.00
L6.Labour Paints
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Epoxy Paint to wall
100.000
sft
10.00
1000.00
Sub-Total(L6)
1000.00
107.64
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Scaffolding
1.000
set
100.00
100.00
Sub-Total(M1)
100.00
10.76
Total(1)
299.40
Add over head on Total(1)
2.5 %
7.49
Total(2)
306.89
Add Profit on Total(2)
8.0 %
24.55
Total(3)
331.44
Add VAT on Unit Price
4.0 %
14.49
Add Income Tax on Unit Price
4.5 %
16.30
Unit Price
362.23
Say
362
per M2
Item: 11 (A13F) Weather coat paint
Basis:100 sft
A3.Material-Paint
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Plastron Sealer
0.500
Ltr
160.00
80.00
Enamel paint
0.250
Ltr
170.00
42.50
Snowcel
2.500
kg
7.60
19.00
Thinner-T6/T7
0.500
Ltr
46.00
23.00
Weather Coat (ColorBank)
1.420
Ltr
227.85
323.55
Sub-Total(A3)
488.05
52.53
L6.Labour Paints
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Weather coat painting
100.000
sft
4.00
400.00
Sub-Total(L6)
400.00
43.06
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Scaffolding
1.000
set
100.00
100.00
Sub-Total(M1)
100.00
10.76
Total(1)
106.35
Add over head on Total(1)
2.5 %
2.66
Total(2)
109.01
Add Profit on Total(2)
8.0 %
8.72
Total(3)
117.73
Add VAT on Unit Price
4.0 %
5.15
Add Income Tax on Unit Price
4.5 %
5.79
Unit Price
128.67
Say
129
per M2
Item: 12 (A11A) Alum(PC)-Swing Door Frosted Glass
Basis:1 sft
S2.Alum,SS/MS,FalseCeil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Al.(PC) Swing Door,FrsGls
1.000
sft
400.00
400.00
Sub-Total(S2)
400.00
4305.60
Total(1)
4305.60
Add over head on Total(1)
2.5 %
107.64
Total(2)
4413.24
Add Profit on Total(2)
8.0 %
353.06
Total(3)
4766.30
Add VAT on Unit Price
4.0 %
208.36
Add Income Tax on Unit Price
4.5 %
234.41
Unit Price
5209.07
Say
5209
per M2
Item: 13 (A11C) Alum (PC) Sliding/fixed window
Basis:1 sft
S2.Alum,SS/MS,FalseCeil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Alum.Fixed Window-PowdrCt
1.000
sft
175.00
175.00
Sub-Total(S2)
175.00
1883.70
Total(1)
1883.70
Add over head on Total(1)
2.5 %
47.09
Total(2)
1930.79
Add Profit on Total(2)
8.0 %
154.46
Total(3)
2085.26
Add VAT on Unit Price
4.0 %
91.16
Add Income Tax on Unit Price
4.5 %
102.55
Unit Price
2278.97
Say
2279
per M2