Return Main Menu

Project Infusion Building Upgradation-4
Item: 01 (A09G) Dismantle Door,Window,Protection
Basis:1 sft
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Dismantle, Door Window
1.000
sft
3.00
3.00
Sub-Total(L1)
3.00
32.29
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Scaffolding
0.000
set
100.00
0.00
Sub-Total(M1)
0.00
0.00
Total(1)
32.29
Add over head on Total(1)
2.5 %
0.81
Total(2)
33.10
Add Profit on Total(2)
8.0 %
2.65
Total(3)
35.75
Add VAT on Unit Price
4.0 %
1.56
Add Income Tax on Unit Price
4.5 %
1.76
Unit Price
39.07
Say
39
per M2
Item: 02 (A09F) Dismantling - 250mm Brick Wall
Basis:1 cft
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Dismatle - B/W
1.000
cft
3.50
3.50
Sub-Total(L1)
3.50
123.60
Total(1)
123.60
Add over head on Total(1)
2.5 %
3.09
Total(2)
126.69
Add Profit on Total(2)
8.0 %
10.14
Total(3)
136.83
Add VAT on Unit Price
4.0 %
5.98
Add Income Tax on Unit Price
4.5 %
6.73
Unit Price
149.54
Say
150
per M2
Item: 03 (A01) Earth work in Excavation
Basis:1000 cft
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Earth Work in Excavation
1000.000
cft
1.80
1800.00
Sub-Total(L1)
1800.00
63.57
Total(1)
63.57
Add over head on Total(1)
2.5 %
1.59
Total(2)
65.16
Add Profit on Total(2)
8.0 %
5.21
Total(3)
70.37
Add VAT on Unit Price
4.0 %
3.08
Add Income Tax on Unit Price
4.5 %
3.46
Unit Price
76.91
Say
77
per M3
Item: 04 (A02B) Brick Flat Soling
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Filling Sand
5.000
cft
8.50
42.50
Brick
300.000
no.
3.80
1140.00
Sub-Total(A1)
1182.50
127.28
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
0.100
nos.
100.00
10.00
Head Mason Supply
0.250
nos.
200.00
50.00
Sub-Total(L0)
60.00
6.46
Total(1)
133.74
Add over head on Total(1)
2.5 %
3.34
Total(2)
137.09
Add Profit on Total(2)
8.0 %
10.97
Total(3)
148.05
Add VAT on Unit Price
4.0 %
6.47
Add Income Tax on Unit Price
4.5 %
7.28
Unit Price
161.81
Say
162
per M2
Item: 05 (A02F) Single layer polythene
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Polythene
1.500
kg
77.00
115.50
Sub-Total(A1)
115.50
12.43
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
0.020
nos.
100.00
2.00
Sub-Total(L0)
2.00
0.22
Total(1)
12.65
Add over head on Total(1)
2.5 %
0.32
Total(2)
12.96
Add Profit on Total(2)
8.0 %
1.04
Total(3)
14.00
Add VAT on Unit Price
4.0 %
0.61
Add Income Tax on Unit Price
4.5 %
0.69
Unit Price
15.30
Say
15
per M2
Item: 06 (A06C) 250mm thick B-wall (1:5) - Supers
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
1200.000
no.
3.80
4560.00
Sand - Local - Mymensingh
40.000
cft
13.00
520.00
Cement
6.000
bag
343.00
2058.00
Sub-Total(A1)
7138.00
2520.78
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
B/w:15.5-27ft Scffld(Part
100.000
cft
6.00
600.00
Sub-Total(L0)
600.00
211.89
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Scaffolding
1.000
set
100.00
100.00
Sub-Total(M1)
100.00
35.32
Total(1)
2767.99
Add over head on Total(1)
2.5 %
69.20
Total(2)
2837.19
Add Profit on Total(2)
8.0 %
226.98
Total(3)
3064.16
Add VAT on Unit Price
4.0 %
133.95
Add Income Tax on Unit Price
4.5 %
150.70
Unit Price
3348.81
Say
3349
per M3
Item: 07 (A06F) 125 B/Wall (1:4)
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
500.000
no.
3.80
1900.00
Sand - Local - Mymensingh
17.000
cft
13.00
221.00
Cement
3.000
bag
343.00
1029.00
Sub-Total(A1)
3150.00
339.07
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
125mm thick Brick Work
100.000
sft
6.00
600.00
Sub-Total(L0)
600.00
64.58
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Scaffolding
0.000
set
100.00
0.00
Sub-Total(M1)
0.00
0.00
Total(1)
403.65
Add over head on Total(1)
2.5 %
10.09
Total(2)
413.74
Add Profit on Total(2)
8.0 %
33.10
Total(3)
446.84
Add VAT on Unit Price
4.0 %
19.53
Add Income Tax on Unit Price
4.5 %
21.98
Unit Price
488.35
Say
488
per M2
Item: 08 (A03I) 75mm thick cc (1:3:6)-U-footing
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
15.000
cft
13.00
195.00
Cement
12.000
bag
343.00
4116.00
Sand - Sylhet
30.000
cft
24.00
720.00
Brick-chips
90.000
cft
40.00
3600.00
Sub-Total(A1)
8631.00
3048.04
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
100.000
cft
2.00
200.00
Mini Dumper
100.000
cft
2.00
200.00
Sub-Total(E1)
400.00
141.26
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand Screening
45.000
cft
1.00
45.00
Sub-Total(L0)
45.00
15.89
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
CC Work
100.000
cft
5.00
500.00
Sub-Total(L1)
500.00
176.58
Total(1)
3381.76
Add over head on Total(1)
2.5 %
84.54
Total(2)
3466.31
Add Profit on Total(2)
8.0 %
277.30
Total(3)
3743.61
Add VAT on Unit Price
4.0 %
163.66
Add Income Tax on Unit Price
4.5 %
184.11
Unit Price
4091.38
Say
4091
per M3
Item: 09 (A12H) 12mm Plaster (1:6)
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
11.250
cft
13.00
146.25
Cement
1.000
bag
343.00
343.00
Sub-Total(A1)
489.25
52.66
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Dismentling F/W/Mar tile
100.000
sft
10.00
1000.00
Sub-Total(L0)
1000.00
107.64
Total(1)
160.30
Add over head on Total(1)
2.5 %
4.01
Total(2)
164.31
Add Profit on Total(2)
8.0 %
13.14
Total(3)
177.46
Add VAT on Unit Price
4.0 %
7.76
Add Income Tax on Unit Price
4.5 %
8.73
Unit Price
193.94
Say
194
per M2
Item: 10 (A08YC) Lintel Sunshade (1:2:4)
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
22.500
cft
13.00
292.50
Cement
18.000
bag
343.00
6174.00
Sand - Sylhet
22.500
cft
24.00
540.00
Stone-chips
90.000
cft
80.00
7200.00
Sub-Total(A1)
14206.50
5017.03
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
100.000
cft
2.00
200.00
Sub-Total(E1)
200.00
70.63
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
RCC Work
100.000
cft
6.00
600.00
Form work
490.190
sft
8.00
3921.52
Sub-Total(L1)
4521.52
1596.77
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Scaffolding
1.000
set
100.00
100.00
Sub-Total(M1)
100.00
35.32
Total(1)
6719.75
Add over head on Total(1)
2.5 %
167.99
Total(2)
6887.74
Add Profit on Total(2)
8.0 %
551.02
Total(3)
7438.76
Add VAT on Unit Price
4.0 %
325.19
Add Income Tax on Unit Price
4.5 %
365.84
Unit Price
8129.79
Say
8130
per M3
Item: 11 (A13G) Epoxy paint to wall (New)
Basis:100 sft
A3.Material-Paint
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Epoxy Primer
2.000
Ltr
170.00
340.00
Epoxy Enamel
3.080
Ltr
387.00
1191.96
Thinner-T6/T7
1.600
Ltr
46.00
73.60
Chalk powder
1.330
kg
18.00
23.94
Mosaic stone
0.200
no
110.00
22.00
Scrap
1.000
L.s
30.00
30.00
Sub-Total(A3)
1681.50
181.00
L6.Labour Paints
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Epoxy Paint to wall
100.000
sft
10.00
1000.00
Sub-Total(L6)
1000.00
107.64
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Scaffolding
1.000
set
100.00
100.00
Sub-Total(M1)
100.00
10.76
Total(1)
299.40
Add over head on Total(1)
2.5 %
7.49
Total(2)
306.89
Add Profit on Total(2)
8.0 %
24.55
Total(3)
331.44
Add VAT on Unit Price
4.0 %
14.49
Add Income Tax on Unit Price
4.5 %
16.30
Unit Price
362.23
Say
362
per M2
Item: 12 (A13F) Weather coat paint
Basis:100 sft
A3.Material-Paint
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Plastron Sealer
0.500
Ltr
160.00
80.00
Enamel paint
0.250
Ltr
170.00
42.50
Snowcel
2.500
kg
7.60
19.00
Thinner-T6/T7
0.500
Ltr
46.00
23.00
Weather Coat (ColorBank)
1.420
Ltr
227.85
323.55
Sub-Total(A3)
488.05
52.53
L6.Labour Paints
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Weather coat painting
100.000
sft
4.00
400.00
Sub-Total(L6)
400.00
43.06
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Scaffolding
1.000
set
100.00
100.00
Sub-Total(M1)
100.00
10.76
Total(1)
106.35
Add over head on Total(1)
2.5 %
2.66
Total(2)
109.01
Add Profit on Total(2)
8.0 %
8.72
Total(3)
117.73
Add VAT on Unit Price
4.0 %
5.15
Add Income Tax on Unit Price
4.5 %
5.79
Unit Price
128.67
Say
129
per M2
Item: 13 (A07C) Homogenous Floor Tiles
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
6.250
cft
13.00
81.25
Cement
2.500
bag
343.00
857.50
White-Cement
3.600
kg
16.25
58.50
Sub-Total(A1)
997.25
107.34
A2.Material-Mosaic/Tile
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Homogenious Tiles
110.000
sft
46.00
5060.00
Sub-Total(A2)
5060.00
544.66
L2.Labour-Tile/Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Floor/ Wall Tiles fitting
100.000
sft
20.00
2000.00
Sub-Total(L2)
2000.00
215.28
Total(1)
867.28
Add over head on Total(1)
2.5 %
21.68
Total(2)
888.96
Add Profit on Total(2)
8.0 %
71.12
Total(3)
960.08
Add VAT on Unit Price
4.0 %
41.97
Add Income Tax on Unit Price
4.5 %
47.22
Unit Price
1049.27
Say
1049
per M2
Item: 14 (A07A) Glazed Wall Tiles
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
7.030
cft
13.00
91.39
Cement
1.870
bag
343.00
641.41
White-Cement
3.600
kg
16.25
58.50
Sub-Total(A1)
791.30
85.18
A2.Material-Mosaic/Tile
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Glazed Wall Tiles-RAK
105.000
sft
36.00
3780.00
Sub-Total(A2)
3780.00
406.88
L2.Labour-Tile/Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Floor/ Wall Tiles fitting
100.000
sft
20.00
2000.00
Sub-Total(L2)
2000.00
215.28
Total(1)
707.33
Add over head on Total(1)
2.5 %
17.68
Total(2)
725.02
Add Profit on Total(2)
8.0 %
58.00
Total(3)
783.02
Add VAT on Unit Price
4.0 %
34.23
Add Income Tax on Unit Price
4.5 %
38.51
Unit Price
855.76
Say
856
per M2
Item: 15 (A14A) Laminated Gypsum Board Ceiling
Basis:100 sft
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Scaffolding
1.000
set
100.00
100.00
Sub-Total(M1)
100.00
10.76
S2.Alum,SS/MS,FalseCeil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Lamint GypsumBoardCeiling
100.000
sft
42.00
4200.00
Sub-Total(S2)
4200.00
452.09
Total(1)
462.85
Add over head on Total(1)
2.5 %
11.57
Total(2)
474.42
Add Profit on Total(2)
8.0 %
37.95
Total(3)
512.38
Add VAT on Unit Price
4.0 %
22.40
Add Income Tax on Unit Price
4.5 %
25.20
Unit Price
559.98
Say
560
per M2
Item: 16 (A11M) MS Emergency Exit door
Basis:1 no.
C2.MS/SS Work i/c matr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Hollow Metal Door
26.000
sft
350.00
9100.00
Push Bar1
1.000
no.
10000.00
10000.00
Sub-Total(C2)
19100.00
19100.00
Total(1)
19100.00
Add over head on Total(1)
2.5 %
477.50
Total(2)
19577.50
Add Profit on Total(2)
8.0 %
1566.20
Total(3)
21143.70
Add VAT on Unit Price
4.0 %
924.31
Add Income Tax on Unit Price
4.5 %
1039.85
Unit Price
23107.87
Say
23108
per NO
Item: 17 (A11S) PVC Door i/c Lock(750)
Basis:1 no.
S2.Alum,SS/MS,FalseCeil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
PVC Door
1.000
no.
3000.00
3000.00
Sub-Total(S2)
3000.00
3000.00
Total(1)
3000.00
Add over head on Total(1)
2.5 %
75.00
Total(2)
3075.00
Add Profit on Total(2)
8.0 %
246.00
Total(3)
3321.00
Add VAT on Unit Price
4.0 %
145.18
Add Income Tax on Unit Price
4.5 %
163.33
Unit Price
3629.51
Say
3630
per NO
Item: 18 (A11J) Alum(PC)-Swing door Pastc-Frst gl
Basis:1 sft
S2.Alum,SS/MS,FalseCeil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Al(PC) SwDoorPlst-frstGls
1.000
sft
431.00
431.00
Sub-Total(S2)
431.00
4639.28
Total(1)
4639.28
Add over head on Total(1)
2.5 %
115.98
Total(2)
4755.27
Add Profit on Total(2)
8.0 %
380.42
Total(3)
5135.69
Add VAT on Unit Price
4.0 %
224.51
Add Income Tax on Unit Price
4.5 %
252.57
Unit Price
5612.77
Say
5613
per M2
Item: 19 (B01A) uPVC Pipe - 150mm dia
Basis:319 rft
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
uPVC Pipe 150 dia
328.280
rft
115.00
37752.20
uPVC Bend 150mm dia
3.000
no.
560.00
1680.00
uPVC Tee - 150mm dia
21.000
no
950.00
19950.00
uPVC End Cap -150 dia
2.000
no
920.00
1840.00
Clamp
73.000
no
35.00
2555.00
Standing Urinal
1.000
no
150.00
150.00
Hole making (150 dia)
21.000
no
350.00
7350.00
S-cement tube
5.000
no
190.00
950.00
Solvent cement -500 ml
2.000
pot
490.00
980.00
Sub-Total(B1)
73207.20
4639.28
L4.Labour-Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
uPVC Pipe Fitting -150mm
318.720
rft
20.00
6374.40
Sub-Total(L4)
6374.40
4639.28
Total(1)
9278.57
Add over head on Total(1)
2.5 %
231.96
Total(2)
9510.53
Add Profit on Total(2)
8.0 %
760.84
Total(3)
10271.37
Add VAT on Unit Price
4.0 %
449.02
Add Income Tax on Unit Price
4.5 %
505.15
Unit Price
11225.55
Say
11226
per RM
Item: 19A (B01B) uPVC Pipe 100 dia
Basis:300 rft
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
uPVC Pipe 100mm dia
315.000
rft
58.00
18270.00
Solvent cement -500 ml
8.000
pot
490.00
3920.00
uPVC Plainn Tee-100mm Dia
16.000
no.
278.00
4448.00
uPVC Long Trap - 100mm Di
6.000
no.
370.00
2220.00
uPVC Door Bend - 100mm di
24.000
no.
290.00
6960.00
uPVC Bend 45D -100mm dia
6.000
no.
175.00
1050.00
Sub-Total(B1)
36868.00
4639.28
L4.Labour-Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
uPVC Pipe fitting-100 mm
300.000
rft
15.00
4500.00
Sub-Total(L4)
4500.00
4639.28
Total(1)
9278.57
Add over head on Total(1)
2.5 %
231.96
Total(2)
9510.53
Add Profit on Total(2)
8.0 %
760.84
Total(3)
10271.37
Add VAT on Unit Price
4.0 %
449.02
Add Income Tax on Unit Price
4.5 %
505.15
Unit Price
11225.55
Say
11226
per RM
Item: 19B (B01C) uPVc pipe 50 dia
Basis:100 rft
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
uPVc pipe 50 dia
105.000
rft
25.00
2625.00
uPVC Bend - 50mm dia
16.000
no.
47.00
752.00
Sub-Total(B1)
3377.00
4639.28
L4.Labour-Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
uPVC pipe - 50mm
100.000
rft
15.00
1500.00
Sub-Total(L4)
1500.00
4639.28
Total(1)
9278.57
Add over head on Total(1)
2.5 %
231.96
Total(2)
9510.53
Add Profit on Total(2)
8.0 %
760.84
Total(3)
10271.37
Add VAT on Unit Price
4.0 %
449.02
Add Income Tax on Unit Price
4.5 %
505.15
Unit Price
11225.55
Say
11226
per RM
Item: 20 (B15) 20mm dia G.I pipe
Basis:160 rft
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
20mm G.I pipe
168.000
rft
40.00
6720.00
Tread Tape
9.000
Dezn
120.00
1080.00
20mm G-Valve
4.000
No
235.00
940.00
20mm Tee
40.000
No
25.00
1000.00
20mm Union
4.000
No
35.00
140.00
Sub-Total(B1)
9880.00
4639.28
L4.Labour-Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
GI Pipe fitting - 20mm di
160.000
rft
10.00
1600.00
GI Gate Valve fitting 20
4.000
No
30.00
120.00
Sub-Total(L4)
1720.00
4639.28
Total(1)
9278.57
Add over head on Total(1)
2.5 %
231.96
Total(2)
9510.53
Add Profit on Total(2)
8.0 %
760.84
Total(3)
10271.37
Add VAT on Unit Price
4.0 %
449.02
Add Income Tax on Unit Price
4.5 %
505.15
Unit Price
11225.55
Say
11226
per RM
Item: 20A (B15A) 12mm dia G.I pipe
Basis:160 rft
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
12mm G.I pipe
168.000
rft
30.00
5040.00
Tread Tape
9.000
Dezn
120.00
1080.00
12mm G-Valve
4.000
No
160.00
640.00
12mm Tee
100.000
No
12.00
1200.00
12mm Union
10.000
No
10.00
100.00
Sub-Total(B1)
8060.00
4639.28
L4.Labour-Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
GI Pipe fitting - 12mmdia
160.000
rft
9.00
1440.00
Sub-Total(L4)
1440.00
4639.28
Total(1)
9278.57
Add over head on Total(1)
2.5 %
231.96
Total(2)
9510.53
Add Profit on Total(2)
8.0 %
760.84
Total(3)
10271.37
Add VAT on Unit Price
4.0 %
449.02
Add Income Tax on Unit Price
4.5 %
505.15
Unit Price
11225.55
Say
11226
per RM
Item: 21 (B15B) CP angle stop cock N-64
Basis:1 no.
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Angle stop cock
1.000
no
350.00
350.00
Sub-Total(B1)
350.00
350.00
L4.Labour-Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Stop cock fitting
1.000
no
50.00
50.00
Sub-Total(L4)
50.00
50.00
Total(1)
400.00
Add over head on Total(1)
2.5 %
10.00
Total(2)
410.00
Add Profit on Total(2)
8.0 %
32.80
Total(3)
442.80
Add VAT on Unit Price
4.0 %
19.36
Add Income Tax on Unit Price
4.5 %
21.78
Unit Price
483.93
Say
484
per NO
Item: 22 (B15C) CP Piller cock N-42
Basis:1 no.
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Piller cock
1.000
no
410.00
410.00
Sub-Total(B1)
410.00
410.00
L4.Labour-Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Piller cock1
1.000
no
50.00
50.00
Sub-Total(L4)
50.00
50.00
Total(1)
460.00
Add over head on Total(1)
2.5 %
11.50
Total(2)
471.50
Add Profit on Total(2)
8.0 %
37.72
Total(3)
509.22
Add VAT on Unit Price
4.0 %
22.26
Add Income Tax on Unit Price
4.5 %
25.04
Unit Price
556.52
Say
557
per NO
Item: 23 (B15D) Bib cock N-54
Basis:1 no.
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Bib cock
1.000
no
380.00
380.00
Sub-Total(B1)
380.00
380.00
L4.Labour-Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Bib Cock fitting
1.000
no.
50.00
50.00
Sub-Total(L4)
50.00
50.00
Total(1)
430.00
Add over head on Total(1)
2.5 %
10.75
Total(2)
440.75
Add Profit on Total(2)
8.0 %
35.26
Total(3)
476.01
Add VAT on Unit Price
4.0 %
20.81
Add Income Tax on Unit Price
4.5 %
23.41
Unit Price
520.23
Say
520
per NO
Item: 24 (B15E) Wshing H-Basin BISF SuperVt
Basis:1 no.
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Washing h-basin with fitt
1.000
no
2150.00
2150.00
CP Bashin wast
1.000
No
95.00
95.00
Connection pipe
1.000
No
80.00
80.00
Sub-Total(B1)
2325.00
2325.00
L4.Labour-Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Basin fitting
1.000
no.
150.00
150.00
Sub-Total(L4)
150.00
150.00
Total(1)
2475.00
Add over head on Total(1)
2.5 %
61.88
Total(2)
2536.88
Add Profit on Total(2)
8.0 %
202.95
Total(3)
2739.83
Add VAT on Unit Price
4.0 %
119.77
Add Income Tax on Unit Price
4.5 %
134.75
Unit Price
2994.34
Say
2994
per NO
Item: 25 (B15F) L-pan BISF Standerd
Basis:1 no.
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Long pan BISF with fittin
1.000
no
850.00
850.00
C.I Cistern
1.000
no
1050.00
1050.00
Connecting pipe
1.000
no
150.00
150.00
Sub-Total(B1)
2050.00
2050.00
L4.Labour-Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Long Pan fitting
1.000
no.
250.00
250.00
Cistern fitting
1.000
no
100.00
100.00
CI Trap fitting
1.000
no
100.00
100.00
Sub-Total(L4)
450.00
450.00
Total(1)
2500.00
Add over head on Total(1)
2.5 %
62.50
Total(2)
2562.50
Add Profit on Total(2)
8.0 %
205.00
Total(3)
2767.50
Add VAT on Unit Price
4.0 %
120.98
Add Income Tax on Unit Price
4.5 %
136.11
Unit Price
3024.59
Say
3025
per NO
Item: 26 (B15G) Mirror (600x1200x5mm)
Basis:1 no.
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mirror-300x1200
1.000
no
750.00
750.00
Sub-Total(B1)
750.00
750.00
L4.Labour-Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mirror Fitting-450x300
1.000
no.
50.00
50.00
Sub-Total(L4)
50.00
50.00
Total(1)
800.00
Add over head on Total(1)
2.5 %
20.00
Total(2)
820.00
Add Profit on Total(2)
8.0 %
65.60
Total(3)
885.60
Add VAT on Unit Price
4.0 %
38.71
Add Income Tax on Unit Price
4.5 %
43.55
Unit Price
967.87
Say
968
per NO
Item: 26A (B15H) Mirror (2500x1200x5mm)
Basis:1 no.
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mirror-2400x1200
1.000
no
2500.00
2500.00
Sub-Total(B1)
2500.00
2500.00
L4.Labour-Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mirror Fitting-450x300
1.000
no.
50.00
50.00
Sub-Total(L4)
50.00
50.00
Total(1)
2550.00
Add over head on Total(1)
2.5 %
63.75
Total(2)
2613.75
Add Profit on Total(2)
8.0 %
209.10
Total(3)
2822.85
Add VAT on Unit Price
4.0 %
123.40
Add Income Tax on Unit Price
4.5 %
138.83
Unit Price
3085.08
Say
3085
per NO
Item: 27 (B15I) Soap Case N-113
Basis:1 no.
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Soap Case
1.000
no
500.00
500.00
Sub-Total(B1)
500.00
500.00
L4.Labour-Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Soap Tray fitting
1.000
no.
50.00
50.00
Sub-Total(L4)
50.00
50.00
Total(1)
550.00
Add over head on Total(1)
2.5 %
13.75
Total(2)
563.75
Add Profit on Total(2)
8.0 %
45.10
Total(3)
608.85
Add VAT on Unit Price
4.0 %
26.62
Add Income Tax on Unit Price
4.5 %
29.94
Unit Price
665.41
Say
665
per NO
Item: 28 (B15J) Toilet paper holder
Basis:1 no.
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
T-Paper Holder
1.000
no
350.00
350.00
Sub-Total(B1)
350.00
350.00
L4.Labour-Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Paper holder fitting
1.000
no.
50.00
50.00
Sub-Total(L4)
50.00
50.00
Total(1)
400.00
Add over head on Total(1)
2.5 %
10.00
Total(2)
410.00
Add Profit on Total(2)
8.0 %
32.80
Total(3)
442.80
Add VAT on Unit Price
4.0 %
19.36
Add Income Tax on Unit Price
4.5 %
21.78
Unit Price
483.93
Say
484
per NO
Item: 29 (B15K) C.I Gratting 100 dia
Basis:1 no.
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
100mm dia CI gratting
1.000
no
150.00
150.00
Sub-Total(B1)
150.00
150.00
L4.Labour-Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
CP Gratting fitting
1.000
no
45.00
45.00
Sub-Total(L4)
45.00
45.00
Total(1)
195.00
Add over head on Total(1)
2.5 %
4.88
Total(2)
199.88
Add Profit on Total(2)
8.0 %
15.99
Total(3)
215.87
Add VAT on Unit Price
4.0 %
9.44
Add Income Tax on Unit Price
4.5 %
10.62
Unit Price
235.92
Say
236
per NO
Item: 30 (A22B) Ins. pit B type 750x750-in-in
Basis:1 no.
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
32.000
no.
3.80
121.60
Sand - Local - Mymensingh
3.780
cft
13.00
49.14
Polythene
0.180
kg
77.00
13.86
Cement
4.740
bag
343.00
1625.82
Sand - Sylhet
6.000
cft
24.00
144.00
Stone-chips
17.900
cft
80.00
1432.00
Re-bar - G40
48.300
kg
38.50
1859.55
GI Wire
0.330
kg
90.00
29.70
Sub-Total(A1)
5275.67
5275.67
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
CI Cover 300 mm dia
1.000
no.
750.00
750.00
Sub-Total(B1)
750.00
750.00
C1.Steel Structures
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Galvanized Angle 38x38
2.580
rft
125.00
322.50
MS Grating 200x75
1.000
no.
100.00
100.00
Sub-Total(C1)
422.50
422.50
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
20.490
cft
2.00
40.98
Sub-Total(E1)
40.98
40.98
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Re-bar Work
46.000
kg
1.65
75.90
Formwork upto 10ft from P
53.740
sft
8.00
429.92
Dismentling F/W/Mar tile
16.140
sft
10.00
161.40
Neat Cement Finishing
16.140
sft
1.00
16.14
RCC Casting.
20.490
cft
8.00
163.92
Sub-Total(L0)
847.28
847.28
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Earth Work in Excavation
83.160
cft
1.80
149.69
Filling
42.450
cft
1.00
42.45
Brck flat soling
11.860
sft
0.60
7.12
Patent stone with NCF
4.035
sft
3.00
12.11
Sub-Total(L1)
211.36
211.36
L4.Labour-Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Manhole Cover fixing
1.000
no.
300.00
300.00
Sub-Total(L4)
300.00
300.00
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Forms
53.740
sft
5.00
268.70
Sub-Total(M1)
268.70
268.70
Total(1)
8116.49
Add over head on Total(1)
2.5 %
202.91
Total(2)
8319.40
Add Profit on Total(2)
8.0 %
665.55
Total(3)
8984.95
Add VAT on Unit Price
4.0 %
392.78
Add Income Tax on Unit Price
4.5 %
441.88
Unit Price
9819.62
Say
9820
per NO
Item: 31 (A08V1) Septic tank(5x2.5x1.5m)-out-out
Basis:1 no.
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Filling Sand
910.000
cft
8.50
7735.00
Brick
511.000
no.
3.80
1941.80
Sand - Local - Mymensingh
47.000
cft
13.00
611.00
Polythene
2.500
kg
77.00
192.50
Cement
66.000
bag
343.00
22638.00
Sand - Sylhet
175.000
cft
24.00
4200.00
Re-bar G60
727.320
kg
40.20
29238.26
Sub-Total(A1)
66556.56
66556.56
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
CI Cover -450MM DIA
2.000
no.
2500.00
5000.00
Sub-Total(B1)
5000.00
5000.00
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
327.770
cft
2.00
655.54
Mini Dumper
327.770
cft
2.00
655.54
Sub-Total(E1)
1311.08
1311.08
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Re-bar Work
692.680
kg
1.65
1142.92
Sub-Total(L0)
1142.92
1142.92
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Earth Work in Excavation
1483.230
cft
1.80
2669.81
Filling
900.530
cft
1.00
900.53
Brck flat soling
171.850
sft
0.60
103.11
Polythene laying
171.850
sft
0.20
34.37
CC (50mm) With NCF
1.000
sft
3.00
3.00
Plaster Work
694.280
sft
3.00
2082.84
NCF
792.500
sft
1.00
792.50
RCC Work
327.770
cft
6.00
1966.62
Form work
743.150
sft
8.00
5945.20
Sub-Total(L1)
14497.98
14497.98
L4.Labour-Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Manhole Cover fixing
3.000
no.
300.00
900.00
Sub-Total(L4)
900.00
900.00
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Forms
743.150
sft
5.00
3715.75
Shoring for Excavation
409.030
sft
2.15
879.41
Sub-Total(M1)
4595.16
4595.16
M2.Steel Structures
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
G.I Plingth protection
1.000
sft
130.00
130.00
Sub-Total(M2)
130.00
130.00
Total(1)
94133.71
Add over head on Total(1)
2.5 %
2353.34
Total(2)
96487.06
Add Profit on Total(2)
8.0 %
7718.96
Total(3)
104206.02
Add VAT on Unit Price
4.0 %
4555.45
Add Income Tax on Unit Price
4.5 %
5124.89
Unit Price
113886.36
Say
113886
per NO