Project Finishing works of 2nd floor (A-Bldg.) |
Item: 01 (A18A1) Dismantling of Rcc Stair roof |
|
Basis:1
cft |
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Dismantling RCC |
1.000 |
cft |
30.00 |
30.00 |
|
|
Sub-Total(L1) |
30.00
|
1059.45
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Scaffolding |
0.070 |
set |
100.00 |
7.00 |
|
|
Sub-Total(M1) |
7.00
|
247.21
|
|
|
|
Total(1) |
|
1306.66 |
|
Add over head on Total(1)
|
3.0 % |
39.20 |
|
|
|
Total(2) |
|
1345.85 |
|
Add Profit on Total(2) |
8.0 % |
107.67
|
|
|
|
Total(3) |
|
1453.52 |
|
Add VAT on Unit Price |
4.5 % |
71.48 |
Add Income Tax on Unit Price
|
4.0 % |
63.54 |
|
|
|
Unit Price |
|
1588.55
|
|
|
|
Say |
|
Item: 02 (A09F1) Dismantling 250mm brick wall |
|
Basis:1
cft |
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Dismantle B/W 250mm thk |
1.000 |
cft |
5.00 |
5.00 |
|
|
Sub-Total(L1) |
5.00
|
176.58
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Scaffolding |
0.000 |
set |
100.00 |
0.00 |
|
|
Sub-Total(M1) |
0.00
|
0.00
|
|
|
|
Total(1) |
|
176.58 |
|
Add over head on Total(1)
|
3.0 % |
5.30 |
|
|
|
Total(2) |
|
181.87 |
|
Add Profit on Total(2) |
8.0 % |
14.55
|
|
|
|
Total(3) |
|
196.42 |
|
Add VAT on Unit Price |
4.5 % |
9.66 |
Add Income Tax on Unit Price
|
4.0 % |
8.59 |
|
|
|
Unit Price |
|
214.67
|
|
|
|
Say |
|
Item: 03 (A06F) 125 B/Wall (1:4) |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Brick |
500.000 |
no. |
3.80 |
1900.00 |
|
Sand - Local - Mymensingh |
17.000 |
cft |
13.00 |
221.00 |
|
Cement |
3.000 |
bag |
343.00 |
1029.00 |
|
|
Sub-Total(A1) |
3150.00
|
339.07
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
125mm thick Brick Work |
100.000 |
sft |
6.00 |
600.00 |
|
|
Sub-Total(L0) |
600.00
|
64.58
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Scaffolding |
0.000 |
set |
100.00 |
0.00 |
|
|
Sub-Total(M1) |
0.00
|
0.00
|
|
|
|
Total(1) |
|
403.65 |
|
Add over head on Total(1)
|
3.0 % |
12.11 |
|
|
|
Total(2) |
|
415.76 |
|
Add Profit on Total(2) |
8.0 % |
33.26
|
|
|
|
Total(3) |
|
449.02 |
|
Add VAT on Unit Price |
4.5 % |
22.08 |
Add Income Tax on Unit Price
|
4.0 % |
19.63 |
|
|
|
Unit Price |
|
490.73
|
|
|
|
Say |
|
Item: 04 (A06C) 250mm thick B-wall (1:5) - Supers |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Brick |
1200.000 |
no. |
3.80 |
4560.00 |
|
Sand - Local - Mymensingh |
40.000 |
cft |
13.00 |
520.00 |
|
Cement |
6.000 |
bag |
343.00 |
2058.00 |
|
|
Sub-Total(A1) |
7138.00
|
2520.78
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
B/w:15.5-27ft Scffld(Part |
100.000 |
cft |
6.00 |
600.00 |
|
|
Sub-Total(L0) |
600.00
|
211.89
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Scaffolding |
1.000 |
set |
100.00 |
100.00 |
|
|
Sub-Total(M1) |
100.00
|
35.32
|
|
|
|
Total(1) |
|
2767.99 |
|
Add over head on Total(1)
|
3.0 % |
83.04 |
|
|
|
Total(2) |
|
2851.03 |
|
Add Profit on Total(2) |
8.0 % |
228.08
|
|
|
|
Total(3) |
|
3079.11 |
|
Add VAT on Unit Price |
4.5 % |
151.43 |
Add Income Tax on Unit Price
|
4.0 % |
134.61 |
|
|
|
Unit Price |
|
3365.15
|
|
|
|
Say |
|
Item: 05 (A12A) Plaster(1:5) 20mm thick |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
8.250 |
cft |
13.00 |
107.25 |
|
Cement |
1.100 |
bag |
343.00 |
377.30 |
|
|
Sub-Total(A1) |
484.55
|
52.16
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
OutPlaster 30.5ft |
100.000 |
sft |
4.50 |
450.00 |
|
|
Sub-Total(L0) |
450.00
|
48.44
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Scaffolding |
1.500 |
set |
100.00 |
150.00 |
|
|
Sub-Total(M1) |
150.00
|
16.15
|
|
|
|
Total(1) |
|
116.74 |
|
Add over head on Total(1)
|
3.0 % |
3.50 |
|
|
|
Total(2) |
|
120.24 |
|
Add Profit on Total(2) |
8.0 % |
9.62
|
|
|
|
Total(3) |
|
129.86 |
|
Add VAT on Unit Price |
4.5 % |
6.39 |
Add Income Tax on Unit Price
|
4.0 % |
5.68 |
|
|
|
Unit Price |
|
141.93
|
|
|
|
Say |
|
Item: 06 (A12E) 8mm thick plaster(1:4) |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
5.000 |
cft |
13.00 |
65.00 |
|
Cement |
1.000 |
bag |
343.00 |
343.00 |
|
|
Sub-Total(A1) |
408.00
|
43.92
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
InPlaster 44.5ft |
100.000 |
sft |
4.00 |
400.00 |
|
|
Sub-Total(L0) |
400.00
|
43.06
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Scaffolding |
0.600 |
set |
100.00 |
60.00 |
|
|
Sub-Total(M1) |
60.00
|
6.46
|
|
|
|
Total(1) |
|
93.43 |
|
Add over head on Total(1)
|
3.0 % |
2.80 |
|
|
|
Total(2) |
|
96.23 |
|
Add Profit on Total(2) |
8.0 % |
7.70
|
|
|
|
Total(3) |
|
103.93 |
|
Add VAT on Unit Price |
4.5 % |
5.11 |
Add Income Tax on Unit Price
|
4.0 % |
4.54 |
|
|
|
Unit Price |
|
113.59
|
|
|
|
Say |
|
Item: 07 (A03D1) 38mm patent stone (1:1.5:3) |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
3.440 |
cft |
13.00 |
44.72 |
|
Cement |
2.750 |
bag |
343.00 |
943.25 |
|
Sand - Sylhet |
3.440 |
cft |
24.00 |
82.56 |
|
Brick-chips |
10.310 |
cft |
40.00 |
412.40 |
|
|
Sub-Total(A1) |
1482.93
|
159.62
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mixer m/c and vibrator |
12.500 |
cft |
2.00 |
25.00 |
|
Mini Dumper |
12.500 |
cft |
2.00 |
25.00 |
|
|
Sub-Total(E1) |
50.00
|
5.38
|
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
CC Work |
12.500 |
cft |
5.00 |
62.50 |
|
|
Sub-Total(L1) |
62.50
|
6.73
|
|
|
|
Total(1) |
|
171.73 |
|
Add over head on Total(1)
|
3.0 % |
5.15 |
|
|
|
Total(2) |
|
176.88 |
|
Add Profit on Total(2) |
8.0 % |
14.15
|
|
|
|
Total(3) |
|
191.03 |
|
Add VAT on Unit Price |
4.5 % |
9.40 |
Add Income Tax on Unit Price
|
4.0 % |
8.35 |
|
|
|
Unit Price |
|
208.78
|
|
|
|
Say |
|
Item: 08 (A08Z2) Rcc Lintel-slab (1:1.5:3)-1%rod |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
14.333 |
cft |
13.00 |
186.33 |
|
Cement |
22.000 |
bag |
343.00 |
7546.00 |
|
Sand - Sylhet |
28.667 |
cft |
24.00 |
688.01 |
|
Stone-chips |
86.000 |
cft |
80.00 |
6880.00 |
|
GI Wire |
2.500 |
kg |
90.00 |
225.00 |
|
Re-bar G60 |
233.860 |
kg |
40.20 |
9401.17 |
|
|
Sub-Total(A1) |
24926.51
|
8802.80
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mixer m/c and vibrator |
100.000 |
cft |
2.00 |
200.00 |
|
Mini Dumper |
100.000 |
cft |
2.00 |
200.00 |
|
|
Sub-Total(E1) |
400.00
|
141.26
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Re-bar Work |
233.860 |
kg |
1.65 |
385.87 |
|
RCC Casting. |
100.000 |
cft |
8.00 |
800.00 |
|
|
Sub-Total(L0) |
1185.87
|
418.79
|
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Form work |
400.000 |
sft |
8.00 |
3200.00 |
|
|
Sub-Total(L1) |
3200.00
|
1130.08
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Wood use-6time mango |
5.330 |
cft |
350.00 |
1865.50 |
|
|
Sub-Total(M1) |
1865.50
|
658.80
|
|
|
|
Total(1) |
|
11151.73 |
|
Add over head on Total(1)
|
3.0 % |
334.55 |
|
|
|
Total(2) |
|
11486.28 |
|
Add Profit on Total(2) |
8.0 % |
918.90
|
|
|
|
Total(3) |
|
12405.18 |
|
Add VAT on Unit Price |
4.5 % |
610.09 |
Add Income Tax on Unit Price
|
4.0 % |
542.30 |
|
|
|
Unit Price |
|
13557.58
|
|
|
|
Say |
|
Item: 09 (A13K1) Bone tiles paint |
|
Basis:183
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
3.000 |
cft |
13.00 |
39.00 |
|
Cement |
4.000 |
bag |
343.00 |
1372.00 |
|
Brick-chips |
3.500 |
cft |
40.00 |
140.00 |
|
Febond SBR |
10.000 |
Ltr |
50.00 |
500.00 |
|
|
Sub-Total(A1) |
2051.00
|
120.97
|
A3.Material-Paint |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Plastron Sealer |
4.000 |
Ltr |
160.00 |
640.00 |
|
Thinner-T6/T7 |
2.000 |
Ltr |
46.00 |
92.00 |
|
Weather Coat (ColorBank) |
8.000 |
Ltr |
227.85 |
1822.80 |
|
4" Brush |
2.000 |
no |
100.00 |
200.00 |
|
|
Sub-Total(A3) |
2754.80
|
162.48
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Compressor for Paint |
2.000 |
day |
200.00 |
400.00 |
|
|
Sub-Total(E1) |
400.00
|
23.59
|
L6.Labour Paints |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Painter Supply |
12.000 |
no. |
200.00 |
2400.00 |
|
Skill Painter |
2.000 |
No |
350.00 |
700.00 |
|
|
Sub-Total(L6) |
3100.00
|
182.84
|
|
|
|
Total(1) |
|
489.88 |
|
Add over head on Total(1)
|
3.0 % |
14.70 |
|
|
|
Total(2) |
|
504.58 |
|
Add Profit on Total(2) |
8.0 % |
40.37
|
|
|
|
Total(3) |
|
544.95 |
|
Add VAT on Unit Price |
4.5 % |
26.80 |
Add Income Tax on Unit Price
|
4.0 % |
23.82 |
|
|
|
Unit Price |
|
595.57
|
|
|
|
Say |
|
Item: 10 (A13F) Weather coat paint |
|
Basis:100
sft |
A3.Material-Paint |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Plastron Sealer |
0.500 |
Ltr |
160.00 |
80.00 |
|
Enamel paint |
0.250 |
Ltr |
170.00 |
42.50 |
|
Snowcel |
2.500 |
kg |
7.60 |
19.00 |
|
Thinner-T6/T7 |
0.500 |
Ltr |
46.00 |
23.00 |
|
Weather Coat (ColorBank) |
1.420 |
Ltr |
227.85 |
323.55 |
|
|
Sub-Total(A3) |
488.05
|
52.53
|
L6.Labour Paints |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Weather coat painting |
100.000 |
sft |
4.00 |
400.00 |
|
|
Sub-Total(L6) |
400.00
|
43.06
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Scaffolding |
1.000 |
set |
100.00 |
100.00 |
|
|
Sub-Total(M1) |
100.00
|
10.76
|
|
|
|
Total(1) |
|
106.35 |
|
Add over head on Total(1)
|
3.0 % |
3.19 |
|
|
|
Total(2) |
|
109.54 |
|
Add Profit on Total(2) |
8.0 % |
8.76
|
|
|
|
Total(3) |
|
118.31 |
|
Add VAT on Unit Price |
4.5 % |
5.82 |
Add Income Tax on Unit Price
|
4.0 % |
5.17 |
|
|
|
Unit Price |
|
129.30
|
|
|
|
Say |
|
Item: 11 (A13G) Epoxy paint to wall (New) |
|
Basis:100
sft |
A3.Material-Paint |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Epoxy Primer |
2.000 |
Ltr |
170.00 |
340.00 |
|
Epoxy Enamel |
3.080 |
Ltr |
387.00 |
1191.96 |
|
Thinner-T6/T7 |
1.600 |
Ltr |
46.00 |
73.60 |
|
Chalk powder |
1.330 |
kg |
18.00 |
23.94 |
|
Mosaic stone |
0.200 |
no |
110.00 |
22.00 |
|
Scrap |
1.000 |
L.s |
30.00 |
30.00 |
|
|
Sub-Total(A3) |
1681.50
|
181.00
|
L6.Labour Paints |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Epoxy Paint to wall |
100.000 |
sft |
10.00 |
1000.00 |
|
|
Sub-Total(L6) |
1000.00
|
107.64
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Scaffolding |
1.000 |
set |
100.00 |
100.00 |
|
|
Sub-Total(M1) |
100.00
|
10.76
|
|
|
|
Total(1) |
|
299.40 |
|
Add over head on Total(1)
|
3.0 % |
8.98 |
|
|
|
Total(2) |
|
308.38 |
|
Add Profit on Total(2) |
8.0 % |
24.67
|
|
|
|
Total(3) |
|
333.05 |
|
Add VAT on Unit Price |
4.5 % |
16.38 |
Add Income Tax on Unit Price
|
4.0 % |
14.56 |
|
|
|
Unit Price |
|
363.99
|
|
|
|
Say |
|
Item: 12 (A13I) Anti-dust sealent paint |
|
Basis:100
sft |
A3.Material-Paint |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Epoxy Clear Laquer |
3.000 |
Ltr |
385.00 |
1155.00 |
|
|
Sub-Total(A3) |
1155.00
|
124.32
|
L6.Labour Paints |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Anti-dust Selant |
100.000 |
sft |
1.50 |
150.00 |
|
|
Sub-Total(L6) |
150.00
|
16.15
|
|
|
|
Total(1) |
|
140.47 |
|
Add over head on Total(1)
|
3.0 % |
4.21 |
|
|
|
Total(2) |
|
144.68 |
|
Add Profit on Total(2) |
8.0 % |
11.57
|
|
|
|
Total(3) |
|
156.26 |
|
Add VAT on Unit Price |
4.5 % |
7.68 |
Add Income Tax on Unit Price
|
4.0 % |
6.83 |
|
|
|
Unit Price |
|
170.77
|
|
|
|
Say |
|
Item: 13 (A07C1) Hom-600x600 FT (M-Chaina) |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
6.250 |
cft |
13.00 |
81.25 |
|
Cement |
2.500 |
bag |
343.00 |
857.50 |
|
White-Cement |
3.600 |
kg |
16.25 |
58.50 |
|
UnglazPolishTile-Monalisa |
105.000 |
sft |
100.00 |
10500.00 |
|
|
Sub-Total(A1) |
11497.25
|
1237.56
|
L2.Labour-Tile/Sanitary |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Floor Tiles (600x600mm) |
100.000 |
sft |
20.00 |
2000.00 |
|
|
Sub-Total(L2) |
2000.00
|
215.28
|
|
|
|
Total(1) |
|
1452.84 |
|
Add over head on Total(1)
|
3.0 % |
43.59 |
|
|
|
Total(2) |
|
1496.43 |
|
Add Profit on Total(2) |
8.0 % |
119.71
|
|
|
|
Total(3) |
|
1616.14 |
|
Add VAT on Unit Price |
4.5 % |
79.48 |
Add Income Tax on Unit Price
|
4.0 % |
70.65 |
|
|
|
Unit Price |
|
1766.28
|
|
|
|
Say |
|
Item: 14 (A07A) Glazed Wall Tiles |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
7.030 |
cft |
13.00 |
91.39 |
|
Cement |
1.870 |
bag |
343.00 |
641.41 |
|
White-Cement |
3.600 |
kg |
16.25 |
58.50 |
|
|
Sub-Total(A1) |
791.30
|
85.18
|
A2.Material-Mosaic/Tile |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Glazed Wall Tiles-RAK |
105.000 |
sft |
36.00 |
3780.00 |
|
|
Sub-Total(A2) |
3780.00
|
406.88
|
L2.Labour-Tile/Sanitary |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Floor/ Wall Tiles fitting |
100.000 |
sft |
20.00 |
2000.00 |
|
|
Sub-Total(L2) |
2000.00
|
215.28
|
|
|
|
Total(1) |
|
707.33 |
|
Add over head on Total(1)
|
3.0 % |
21.22 |
|
|
|
Total(2) |
|
728.55 |
|
Add Profit on Total(2) |
8.0 % |
58.28
|
|
|
|
Total(3) |
|
786.84 |
|
Add VAT on Unit Price |
4.5 % |
38.70 |
Add Income Tax on Unit Price
|
4.0 % |
34.40 |
|
|
|
Unit Price |
|
859.93
|
|
|
|
Say |
|
Item: 15 (A14A) Laminated Gypsum Board Ceiling |
|
Basis:100
sft |
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Scaffolding |
1.000 |
set |
100.00 |
100.00 |
|
|
Sub-Total(M1) |
100.00
|
10.76
|
S2.Alum,SS/MS,FalseCeil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Lamint GypsumBoardCeiling |
100.000 |
sft |
42.00 |
4200.00 |
|
|
Sub-Total(S2) |
4200.00
|
452.09
|
|
|
|
Total(1) |
|
462.85 |
|
Add over head on Total(1)
|
3.0 % |
13.89 |
|
|
|
Total(2) |
|
476.74 |
|
Add Profit on Total(2) |
8.0 % |
38.14
|
|
|
|
Total(3) |
|
514.88 |
|
Add VAT on Unit Price |
4.5 % |
25.32 |
Add Income Tax on Unit Price
|
4.0 % |
22.51 |
|
|
|
Unit Price |
|
562.71
|
|
|
|
Say |
|
Item: 16 (A14C) Plaster board ceiling |
|
Basis:100
sft |
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Scaffolding |
1.000 |
set |
100.00 |
100.00 |
|
|
Sub-Total(M1) |
100.00
|
10.76
|
S2.Alum,SS/MS,FalseCeil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Plaster Board Ceiling |
100.000 |
sft |
125.00 |
12500.00 |
|
|
Sub-Total(S2) |
12500.00
|
1345.50
|
|
|
|
Total(1) |
|
1356.26 |
|
Add over head on Total(1)
|
3.0 % |
40.69 |
|
|
|
Total(2) |
|
1396.95 |
|
Add Profit on Total(2) |
8.0 % |
111.76
|
|
|
|
Total(3) |
|
1508.71 |
|
Add VAT on Unit Price |
4.5 % |
74.20 |
Add Income Tax on Unit Price
|
4.0 % |
65.95 |
|
|
|
Unit Price |
|
1648.86
|
|
|
|
Say |
|
Item: 17 (A13D) Epoxy paint to Ceiling |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
White-Cement |
1.000 |
kg |
16.25 |
16.25 |
|
|
Sub-Total(A1) |
16.25
|
1.75
|
A3.Material-Paint |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Epoxy Primer |
2.000 |
Ltr |
170.00 |
340.00 |
|
Epoxy Enamel |
3.080 |
Ltr |
387.00 |
1191.96 |
|
Thinner-T6/T7 |
1.600 |
Ltr |
46.00 |
73.60 |
|
Chalk powder |
1.330 |
kg |
18.00 |
23.94 |
|
Mosaic stone |
0.200 |
no |
110.00 |
22.00 |
|
Scrap |
1.000 |
L.s |
30.00 |
30.00 |
|
Bakram |
1.000 |
yds |
25.00 |
25.00 |
|
Aica |
0.500 |
kg |
120.00 |
60.00 |
|
|
Sub-Total(A3) |
1766.50
|
190.15
|
L6.Labour Paints |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
EpoxyPaint-P.boardCeiling |
100.000 |
sft |
12.00 |
1200.00 |
|
|
Sub-Total(L6) |
1200.00
|
129.17
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Scaffolding |
1.000 |
set |
100.00 |
100.00 |
|
|
Sub-Total(M1) |
100.00
|
10.76
|
|
|
|
Total(1) |
|
331.83 |
|
Add over head on Total(1)
|
3.0 % |
9.95 |
|
|
|
Total(2) |
|
341.78 |
|
Add Profit on Total(2) |
8.0 % |
27.34
|
|
|
|
Total(3) |
|
369.12 |
|
Add VAT on Unit Price |
4.5 % |
18.15 |
Add Income Tax on Unit Price
|
4.0 % |
16.14 |
|
|
|
Unit Price |
|
403.41
|
|
|
|
Say |
|
Item: 18 (A11C1) Alum(PC) Sliding/Fiexd Window Ref |
|
Basis:1
sft |
S2.Alum,SS/MS,FalseCeil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Al Win F/Sliding W- R-gls |
1.000 |
sft |
250.00 |
250.00 |
|
|
Sub-Total(S2) |
250.00
|
2691.00
|
|
|
|
Total(1) |
|
2691.00 |
|
Add over head on Total(1)
|
3.0 % |
80.73 |
|
|
|
Total(2) |
|
2771.73 |
|
Add Profit on Total(2) |
8.0 % |
221.74
|
|
|
|
Total(3) |
|
2993.47 |
|
Add VAT on Unit Price |
4.5 % |
147.22 |
Add Income Tax on Unit Price
|
4.0 % |
130.86 |
|
|
|
Unit Price |
|
3271.55
|
|
|
|
Say |
|
Item: 19A (A11A1) Alum(PC) Swg Door Frst+clr glss |
|
Basis:1
sft |
|
|
|
Total(1) |
|
0.00 |
|
Add over head on Total(1)
|
3.0 % |
80.73 |
|
|
|
Total(2) |
|
2771.73 |
|
Add Profit on Total(2) |
8.0 % |
221.74
|
|
|
|
Total(3) |
|
2993.47 |
|
Add VAT on Unit Price |
4.5 % |
147.22 |
Add Income Tax on Unit Price
|
4.0 % |
130.86 |
|
|
|
Unit Price |
|
3271.55
|
|
|
|
Say |
|
Item: 20A (A11U1) Al PC Partition Frost Glass-2500 |
|
Basis:1
sft |
|
|
|
Total(1) |
|
0.00 |
|
Add over head on Total(1)
|
3.0 % |
80.73 |
|
|
|
Total(2) |
|
2771.73 |
|
Add Profit on Total(2) |
8.0 % |
221.74
|
|
|
|
Total(3) |
|
2993.47 |
|
Add VAT on Unit Price |
4.5 % |
147.22 |
Add Income Tax on Unit Price
|
4.0 % |
130.86 |
|
|
|
Unit Price |
|
3271.55
|
|
|
|
Say |
|
Item: 20B (A11W) Al.PC) Partition Frost Glass-2100 |
|
Basis:1
sft |
S2.Alum,SS/MS,FalseCeil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Al.(PC)Partition,FrstGls |
1.000 |
sft |
220.00 |
220.00 |
|
|
Sub-Total(S2) |
220.00
|
2368.08
|
|
|
|
Total(1) |
|
2368.08 |
|
Add over head on Total(1)
|
3.0 % |
71.04 |
|
|
|
Total(2) |
|
2439.12 |
|
Add Profit on Total(2) |
8.0 % |
195.13
|
|
|
|
Total(3) |
|
2634.25 |
|
Add VAT on Unit Price |
4.5 % |
129.55 |
Add Income Tax on Unit Price
|
4.0 % |
115.16 |
|
|
|
Unit Price |
|
2878.96
|
|
|
|
Say |
|
Item: 20C (A11V1) Al PC Partition Frost Glass-1500 |
|
Basis:1
sft |
|
|
|
Total(1) |
|
0.00 |
|
Add over head on Total(1)
|
3.0 % |
71.04 |
|
|
|
Total(2) |
|
2439.12 |
|
Add Profit on Total(2) |
8.0 % |
195.13
|
|
|
|
Total(3) |
|
2634.25 |
|
Add VAT on Unit Price |
4.5 % |
129.55 |
Add Income Tax on Unit Price
|
4.0 % |
115.16 |
|
|
|
Unit Price |
|
2878.96
|
|
|
|
Say |
|
Item: 21 (A11M) MS Emergency Exit door |
|
Basis:1
no. |
C2.MS/SS Work i/c matr |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Hollow Metal Door |
26.000 |
sft |
350.00 |
9100.00 |
|
Push Bar1 |
1.000 |
no. |
10000.00 |
10000.00 |
|
|
Sub-Total(C2) |
19100.00
|
19100.00
|
|
|
|
Total(1) |
|
19100.00 |
|
Add over head on Total(1)
|
3.0 % |
573.00 |
|
|
|
Total(2) |
|
19673.00 |
|
Add Profit on Total(2) |
8.0 % |
1573.84
|
|
|
|
Total(3) |
|
21246.84 |
|
Add VAT on Unit Price |
4.5 % |
1044.93 |
Add Income Tax on Unit Price
|
4.0 % |
928.82 |
|
|
|
Unit Price |
|
23220.59
|
|
|
|
Say |
|
Item: 22 (B01A) uPVC Pipe - 150mm dia |
|
Basis:319
rft |
B1.Plumbing/Sanitr Pipe |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
uPVC Pipe 150 dia |
328.280 |
rft |
115.00 |
37752.20 |
|
uPVC Bend 150mm dia |
3.000 |
no. |
560.00 |
1680.00 |
|
uPVC Tee - 150mm dia |
21.000 |
no |
950.00 |
19950.00 |
|
uPVC End Cap -150 dia |
2.000 |
no |
920.00 |
1840.00 |
|
Clamp |
73.000 |
no |
35.00 |
2555.00 |
|
Standing Urinal |
1.000 |
no |
150.00 |
150.00 |
|
Hole making (150 dia) |
21.000 |
no |
350.00 |
7350.00 |
|
S-cement tube |
5.000 |
no |
190.00 |
950.00 |
|
Solvent cement -500 ml |
2.000 |
pot |
490.00 |
980.00 |
|
|
Sub-Total(B1) |
73207.20
|
19100.00
|
L4.Labour-Sanitary |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
uPVC Pipe Fitting -150mm |
318.720 |
rft |
20.00 |
6374.40 |
|
|
Sub-Total(L4) |
6374.40
|
19100.00
|
|
|
|
Total(1) |
|
38200.00 |
|
Add over head on Total(1)
|
3.0 % |
1146.00 |
|
|
|
Total(2) |
|
39346.00 |
|
Add Profit on Total(2) |
8.0 % |
3147.68
|
|
|
|
Total(3) |
|
42493.68 |
|
Add VAT on Unit Price |
4.5 % |
2089.85 |
Add Income Tax on Unit Price
|
4.0 % |
1857.65 |
|
|
|
Unit Price |
|
46441.18
|
|
|
|
Say |
|
Item: 23 (A07F1) M-Ceramics Tiles (M-31) |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
6.600 |
cft |
13.00 |
85.80 |
|
Cement |
4.500 |
bag |
343.00 |
1543.50 |
|
Pudloo |
0.000 |
kg |
70.00 |
0.00 |
|
|
Sub-Total(A1) |
1629.30
|
175.38
|
A2.Material-Mosaic/Tile |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Ceramic Paty-Tiles,M-31 |
500.000 |
no |
13.50 |
6750.00 |
|
Ceramic Ridge tiles |
18.000 |
no |
17.60 |
316.80 |
|
|
Sub-Total(A2) |
7066.80
|
760.67
|
L2.Labour-Tile/Sanitary |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
C-roof tiles |
100.000 |
sft |
15.00 |
1500.00 |
|
RCC Floor chiping |
100.000 |
Sft |
1.00 |
100.00 |
|
Local Carrying |
100.000 |
sft |
2.00 |
200.00 |
|
|
Sub-Total(L2) |
1800.00
|
193.75
|
|
|
|
Total(1) |
|
1129.80 |
|
Add over head on Total(1)
|
3.0 % |
33.89 |
|
|
|
Total(2) |
|
1163.69 |
|
Add Profit on Total(2) |
8.0 % |
93.10
|
|
|
|
Total(3) |
|
1256.79 |
|
Add VAT on Unit Price |
4.5 % |
61.81 |
Add Income Tax on Unit Price
|
4.0 % |
54.94 |
|
|
|
Unit Price |
|
1373.54
|
|
|
|
Say |
|
Item: 24 (F011) MS Grating |
|
Basis:1
no. |
B1.Plumbing/Sanitr Pipe |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
MS Grating |
1.000 |
no |
150.00 |
150.00 |
|
|
Sub-Total(B1) |
150.00
|
150.00
|
|
|
|
Total(1) |
|
150.00 |
|
Add over head on Total(1)
|
3.0 % |
4.50 |
|
|
|
Total(2) |
|
154.50 |
|
Add Profit on Total(2) |
8.0 % |
12.36
|
|
|
|
Total(3) |
|
166.86 |
|
Add VAT on Unit Price |
4.5 % |
8.21 |
Add Income Tax on Unit Price
|
4.0 % |
7.29 |
|
|
|
Unit Price |
|
182.36
|
|
|
|
Say |
|
Item: 25A (A18H3) Dismantling CC Floor |
|
Basis:1
sft |
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Ordinary Labour Supply |
0.100 |
nos. |
100.00 |
10.00 |
|
|
Sub-Total(L0) |
10.00
|
107.64
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Cheisel - Hammer |
0.100 |
no |
55.00 |
5.50 |
|
|
Sub-Total(M1) |
5.50
|
59.20
|
|
|
|
Total(1) |
|
166.84 |
|
Add over head on Total(1)
|
3.0 % |
5.01 |
|
|
|
Total(2) |
|
171.85 |
|
Add Profit on Total(2) |
8.0 % |
13.75
|
|
|
|
Total(3) |
|
185.60 |
|
Add VAT on Unit Price |
4.5 % |
9.13 |
Add Income Tax on Unit Price
|
4.0 % |
8.11 |
|
|
|
Unit Price |
|
202.84
|
|
|
|
Say |
|
Item: 25B (A09H) Dismantling of 125mm b/wall |
|
Basis:1
sft |
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Ordinary Labour Supply |
0.060 |
nos. |
100.00 |
6.00 |
|
|
Sub-Total(L0) |
6.00
|
64.58
|
|
|
|
Total(1) |
|
64.58 |
|
Add over head on Total(1)
|
3.0 % |
1.94 |
|
|
|
Total(2) |
|
66.52 |
|
Add Profit on Total(2) |
8.0 % |
5.32
|
|
|
|
Total(3) |
|
71.84 |
|
Add VAT on Unit Price |
4.5 % |
3.53 |
Add Income Tax on Unit Price
|
4.0 % |
3.14 |
|
|
|
Unit Price |
|
78.52
|
|
|
|
Say |
|
Item: 25C (A10A) Re-bar Grade 60 |
|
Basis:1000
kg. |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
GI Wire |
10.000 |
kg |
90.00 |
900.00 |
|
Re-bar G60 |
1050.000 |
kg |
40.20 |
42210.00 |
|
|
Sub-Total(A1) |
43110.00
|
64.58
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Re-bar Work |
1000.000 |
kg |
1.65 |
1650.00 |
|
Local carrying Rod |
0.000 |
kg |
0.25 |
0.00 |
|
|
Sub-Total(L0) |
1650.00
|
64.58
|
|
|
|
Total(1) |
|
129.17 |
|
Add over head on Total(1)
|
3.0 % |
3.88 |
|
|
|
Total(2) |
|
133.04 |
|
Add Profit on Total(2) |
8.0 % |
10.64
|
|
|
|
Total(3) |
|
143.69 |
|
Add VAT on Unit Price |
4.5 % |
7.07 |
Add Income Tax on Unit Price
|
4.0 % |
6.28 |
|
|
|
Unit Price |
|
157.03
|
|
|
|
Say |
|