Return Main Menu

Project Brick wall and Fencing for Boundary wall
Item: 02 (A06F1) 125 Ceramic B/Wall (1:4)
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
25.500
cft
13.00
331.50
Cement
4.500
bag
343.00
1543.50
Re-bar - G40
9.114
kg
38.50
350.89
Ceramic Brick 10-Hole
500.000
nos
6.80
3400.00
Sub-Total(A1)
5625.89
605.57
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ceramic 10-Hole B/W
100.000
sft
10.00
1000.00
Sub-Total(L0)
1000.00
107.64
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Scaffolding
0.500
set
100.00
50.00
Sub-Total(M1)
50.00
5.38
Total(1)
718.59
Add over head on Total(1)
3.0 %
21.56
Total(2)
740.15
Add Profit on Total(2)
8.0 %
59.21
Total(3)
799.36
Add VAT on Unit Price
4.5 %
37.67
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
837.03
Say
837
per M2
Item: 01 (A08C1) RCC (1:2:4) in S-column
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
22.500
cft
13.00
292.50
Cement
18.000
bag
343.00
6174.00
Sand - Sylhet
22.500
cft
24.00
540.00
Stone-chips
90.000
cft
80.00
7200.00
Sub-Total(A1)
14206.50
5017.03
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
100.000
cft
2.00
200.00
Mini Dumper
100.000
cft
2.00
200.00
Sub-Total(E1)
400.00
141.26
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Form work Foot-col-Str
476.267
sft
6.00
2857.60
RCC Casting.
100.000
cft
8.00
800.00
Sub-Total(L0)
3657.60
1291.68
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Forms
476.267
sft
5.00
2381.34
Sub-Total(M1)
2381.34
840.97
Total(1)
7290.94
Add over head on Total(1)
3.0 %
218.73
Total(2)
7509.66
Add Profit on Total(2)
8.0 %
600.77
Total(3)
8110.44
Add VAT on Unit Price
4.5 %
382.17
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
8492.60
Say
8493
per M3
Item: 01B (A08YB) Top beam boundary(1:2:4)
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
22.500
cft
13.00
292.50
Cement
18.000
bag
343.00
6174.00
Sand - Sylhet
22.500
cft
24.00
540.00
Stone-chips
90.000
cft
80.00
7200.00
Sub-Total(A1)
14206.50
5017.03
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
100.000
cft
2.00
200.00
Mini Dumper
100.000
cft
2.00
200.00
Sub-Total(E1)
400.00
141.26
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Form work Foot-col-Str
440.960
sft
6.00
2645.76
RCC Casting.
100.000
cft
8.00
800.00
Sub-Total(L0)
3445.76
1216.87
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Forms
440.960
sft
5.00
2204.80
Sub-Total(M1)
2204.80
778.63
Total(1)
7153.78
Add over head on Total(1)
3.0 %
214.61
Total(2)
7368.39
Add Profit on Total(2)
8.0 %
589.47
Total(3)
7957.87
Add VAT on Unit Price
4.5 %
374.98
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
8332.84
Say
8333
per M3
Item: 04 (A10A) Re-bar Grade 60
Basis:1000 kg.
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
GI Wire
10.000
kg
90.00
900.00
Re-bar G60
1050.000
kg
40.20
42210.00
Sub-Total(A1)
43110.00
778.63
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Re-bar Work
1000.000
kg
1.65
1650.00
Local carrying Rod
0.000
kg
0.25
0.00
Sub-Total(L0)
1650.00
778.63
Total(1)
1557.25
Add over head on Total(1)
3.0 %
46.72
Total(2)
1603.97
Add Profit on Total(2)
8.0 %
128.32
Total(3)
1732.29
Add VAT on Unit Price
4.5 %
81.63
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
1813.91
Say
1814
per TON
Item: 03 (A12H1) Both side flush pionting(1:2)
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
1.250
cft
13.00
16.25
Cement
0.500
bag
343.00
171.50
Sub-Total(A1)
187.75
20.21
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Flush pointing (1:2)
100.000
sft
3.00
300.00
Sub-Total(L0)
300.00
32.29
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Scaffolding
0.500
set
100.00
50.00
Sub-Total(M1)
50.00
5.38
Total(1)
57.88
Add over head on Total(1)
3.0 %
1.74
Total(2)
59.62
Add Profit on Total(2)
8.0 %
4.77
Total(3)
64.39
Add VAT on Unit Price
4.5 %
3.03
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
67.42
Say
67
per M2
Item: 07 (A13F) Weather coat paint
Basis:100 sft
A3.Material-Paint
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Plastron Sealer
0.500
Ltr
160.00
80.00
Enamel paint
0.250
Ltr
170.00
42.50
Snowcel
2.500
kg
7.60
19.00
Thinner-T6/T7
0.500
Ltr
46.00
23.00
Weather Coat (ColorBank)
1.420
Ltr
227.85
323.55
Sub-Total(A3)
488.05
52.53
L6.Labour Paints
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Weather coat painting
100.000
sft
4.00
400.00
Sub-Total(L6)
400.00
43.06
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Scaffolding
1.000
set
100.00
100.00
Sub-Total(M1)
100.00
10.76
Total(1)
106.35
Add over head on Total(1)
3.0 %
3.19
Total(2)
109.54
Add Profit on Total(2)
8.0 %
8.76
Total(3)
118.31
Add VAT on Unit Price
4.5 %
5.57
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
123.88
Say
124
per M2
Item: 05 (A20A) Hollow steel box boundary
Basis:130 sft
A3.Material-Paint
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ind. Enamel paint
5.000
Ltr
210.00
1050.00
Plastron Sealer
1.300
Ltr
160.00
208.00
Snowcel
6.500
kg
7.60
49.40
Thinner-T6/T7
1.300
Ltr
46.00
59.80
Industrial Primer(Enamel)
3.000
Ltr
210.00
630.00
Sub-Total(A3)
1997.20
165.39
C1.Steel Structures
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Hollow box (75x75x4.5mm)
14.470
rft
322.00
4659.34
Hollow box (50x50x3mm)
39.620
rft
147.00
5824.14
Hollow Met (25x25x2.3mm)
390.668
rft
70.00
27346.76
Metal Cap
2.000
no
50.00
100.00
Sub-Total(C1)
37930.24
3141.11
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Enamel paint-Boundary
259.960
sft
5.00
1299.80
Sub-Total(L0)
1299.80
107.64
S2.Alum,SS/MS,FalseCeil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Hollow Metal Fenc mak/fix
129.980
sft
50.00
6499.00
Sub-Total(S2)
6499.00
538.20
Total(1)
3952.34
Add over head on Total(1)
3.0 %
118.57
Total(2)
4070.91
Add Profit on Total(2)
8.0 %
325.67
Total(3)
4396.58
Add VAT on Unit Price
4.5 %
207.17
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
4603.75
Say
4604
per M2
Item: 06 (A20C) 75x75x5mm MS plate
Basis:1 no.
C1.Steel Structures
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
75x75x5mm MS Plate
1.000
no
110.00
110.00
75x75x5mm plate fitting
1.000
no
20.00
20.00
Sub-Total(C1)
130.00
130.00
Total(1)
130.00
Add over head on Total(1)
3.0 %
3.90
Total(2)
133.90
Add Profit on Total(2)
8.0 %
10.71
Total(3)
144.61
Add VAT on Unit Price
4.5 %
6.81
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
151.43
Say
151
per NO