Project Pile and GB for boundary wall at Te-Park |
Item: 01 (A01B) Earth cutting |
|
Basis:1
no. |
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
E/Cutting |
3000.000 |
cft |
2.00 |
6000.00 |
|
|
Sub-Total(L0) |
6000.00
|
6000.00
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Shoring for Excavation |
4000.000 |
sft |
2.15 |
8600.00 |
|
|
Sub-Total(M1) |
8600.00
|
8600.00
|
|
|
|
Total(1) |
|
14600.00 |
|
Add over head on Total(1)
|
3.0 % |
438.00 |
|
|
|
Total(2) |
|
15038.00 |
|
Add Profit on Total(2) |
8.0 % |
1203.04
|
|
|
|
Total(3) |
|
16241.04 |
|
Add VAT on Unit Price |
4.5 % |
765.28 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
17006.32
|
|
|
|
Say |
|
Item: 03 (A05) Sand Filling |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Filling Sand |
130.000 |
cft |
8.50 |
1105.00 |
|
|
Sub-Total(A1) |
1105.00
|
390.23
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mini Roller Compaction |
100.000 |
cft |
1.00 |
100.00 |
|
Mini Dumper |
130.000 |
cft |
2.00 |
260.00 |
|
Payloader |
0.000 |
day |
8000.00 |
0.00 |
|
Dump Truck |
0.000 |
day |
8300.00 |
0.00 |
|
|
Sub-Total(E1) |
360.00
|
127.13
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Ordinary Labour Supply |
0.800 |
nos. |
100.00 |
80.00 |
|
|
Sub-Total(L0) |
80.00
|
28.25
|
|
|
|
Total(1) |
|
545.62 |
|
Add over head on Total(1)
|
3.0 % |
16.37 |
|
|
|
Total(2) |
|
561.99 |
|
Add Profit on Total(2) |
8.0 % |
44.96
|
|
|
|
Total(3) |
|
606.94 |
|
Add VAT on Unit Price |
4.5 % |
28.60 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
635.54
|
|
|
|
Say |
|
Item: 02 (A05G) Earth Filling (Loose Volume) |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Filling Earth |
100.000 |
cft |
6.60 |
660.00 |
|
|
Sub-Total(A1) |
660.00
|
233.08
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Ordinary Labour Supply |
0.800 |
nos. |
100.00 |
80.00 |
|
|
Sub-Total(L0) |
80.00
|
28.25
|
|
|
|
Total(1) |
|
261.33 |
|
Add over head on Total(1)
|
3.0 % |
7.84 |
|
|
|
Total(2) |
|
269.17 |
|
Add Profit on Total(2) |
8.0 % |
21.53
|
|
|
|
Total(3) |
|
290.70 |
|
Add VAT on Unit Price |
4.5 % |
13.70 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
304.40
|
|
|
|
Say |
|
Item: 04B (A08A0) RCC (1:1.5:3) in Pile (400x400) |
|
Basis:103
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Cement |
23.000 |
bag |
343.00 |
7889.00 |
|
Sand - Sylhet |
43.000 |
cft |
24.00 |
1032.00 |
|
Stone-chips |
86.000 |
cft |
80.00 |
6880.00 |
|
|
Sub-Total(A1) |
15801.00
|
5433.42
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Batching Plant , Vibrator |
102.713 |
cft |
8.00 |
821.70 |
|
|
Sub-Total(E1) |
821.70
|
282.56
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Formwork upto 10ft from P |
238.240 |
sft |
8.00 |
1905.92 |
|
Sand Screening |
43.000 |
cft |
1.00 |
43.00 |
|
RCC Casting. |
102.713 |
cft |
8.00 |
821.70 |
|
|
Sub-Total(L0) |
2770.62
|
952.72
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Pile Shutter (steel) |
238.240 |
sft |
12.00 |
2858.88 |
|
Cost of Pre-casr yard |
59.642 |
rft |
8.00 |
477.14 |
|
|
Sub-Total(M1) |
3336.02
|
1147.14
|
|
|
|
Total(1) |
|
7815.84 |
|
Add over head on Total(1)
|
3.0 % |
234.48 |
|
|
|
Total(2) |
|
8050.32 |
|
Add Profit on Total(2) |
8.0 % |
644.03
|
|
|
|
Total(3) |
|
8694.34 |
|
Add VAT on Unit Price |
4.5 % |
409.68 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
9104.02
|
|
|
|
Say |
|
Item: 04A (A08A1) RCC(1:1.5:3) in Pile (250x250) |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
20.500 |
cft |
13.00 |
266.50 |
|
Cement |
22.000 |
bag |
343.00 |
7546.00 |
|
Sand - Sylhet |
20.500 |
cft |
24.00 |
492.00 |
|
Stone-chips |
82.000 |
cft |
80.00 |
6560.00 |
|
|
Sub-Total(A1) |
14864.50
|
5249.40
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mini Dumper |
100.000 |
cft |
2.00 |
200.00 |
|
Batching Plant , Vibrator |
100.000 |
cft |
8.00 |
800.00 |
|
|
Sub-Total(E1) |
1000.00
|
353.15
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Formwork upto 10ft from P |
362.900 |
sft |
8.00 |
2903.20 |
|
Sand Screening |
41.000 |
cft |
1.00 |
41.00 |
|
RCC Casting. |
100.000 |
cft |
8.00 |
800.00 |
|
|
Sub-Total(L0) |
3744.20
|
1322.26
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Pile Shutter (steel) |
362.900 |
sft |
12.00 |
4354.80 |
|
Cost of Pre-casr yard |
150.000 |
rft |
8.00 |
1200.00 |
|
|
Sub-Total(M1) |
5554.80
|
1961.68
|
|
|
|
Total(1) |
|
8886.49 |
|
Add over head on Total(1)
|
3.0 % |
266.59 |
|
|
|
Total(2) |
|
9153.08 |
|
Add Profit on Total(2) |
8.0 % |
732.25
|
|
|
|
Total(3) |
|
9885.33 |
|
Add VAT on Unit Price |
4.5 % |
465.80 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
10351.13
|
|
|
|
Say |
|
Item: 07 (A08C1) RCC (1:2:4) in S-column |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
22.500 |
cft |
13.00 |
292.50 |
|
Cement |
18.000 |
bag |
343.00 |
6174.00 |
|
Sand - Sylhet |
22.500 |
cft |
24.00 |
540.00 |
|
Stone-chips |
90.000 |
cft |
80.00 |
7200.00 |
|
|
Sub-Total(A1) |
14206.50
|
5017.03
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mixer m/c and vibrator |
100.000 |
cft |
2.00 |
200.00 |
|
Mini Dumper |
100.000 |
cft |
2.00 |
200.00 |
|
|
Sub-Total(E1) |
400.00
|
141.26
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Form work Foot-col-Str |
476.267 |
sft |
6.00 |
2857.60 |
|
RCC Casting. |
100.000 |
cft |
8.00 |
800.00 |
|
|
Sub-Total(L0) |
3657.60
|
1291.68
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Forms |
476.267 |
sft |
5.00 |
2381.34 |
|
|
Sub-Total(M1) |
2381.34
|
840.97
|
|
|
|
Total(1) |
|
7290.94 |
|
Add over head on Total(1)
|
3.0 % |
218.73 |
|
|
|
Total(2) |
|
7509.66 |
|
Add Profit on Total(2) |
8.0 % |
600.77
|
|
|
|
Total(3) |
|
8110.44 |
|
Add VAT on Unit Price |
4.5 % |
382.17 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
8492.60
|
|
|
|
Say |
|
Item: 08 (A08D1) RCC (1:2:4) in GB-Boundary |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
22.500 |
cft |
13.00 |
292.50 |
|
Cement |
18.000 |
bag |
343.00 |
6174.00 |
|
Sand - Sylhet |
22.500 |
cft |
24.00 |
540.00 |
|
Stone-chips |
90.000 |
cft |
80.00 |
7200.00 |
|
|
Sub-Total(A1) |
14206.50
|
5017.03
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mixer m/c and vibrator |
100.000 |
cft |
2.00 |
200.00 |
|
Mini Dumper |
100.000 |
cft |
2.00 |
200.00 |
|
|
Sub-Total(E1) |
400.00
|
141.26
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Form work Foot-col-Str |
340.960 |
sft |
6.00 |
2045.76 |
|
|
Sub-Total(L0) |
2045.76
|
722.46
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Forms |
340.960 |
sft |
5.00 |
1704.80 |
|
|
Sub-Total(M1) |
1704.80
|
602.05
|
|
|
|
Total(1) |
|
6482.80 |
|
Add over head on Total(1)
|
3.0 % |
194.48 |
|
|
|
Total(2) |
|
6677.28 |
|
Add Profit on Total(2) |
8.0 % |
534.18
|
|
|
|
Total(3) |
|
7211.46 |
|
Add VAT on Unit Price |
4.5 % |
339.81 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
7551.27
|
|
|
|
Say |
|
Item: 09A (A10A) Re-bar Grade 60 |
|
Basis:1000
kg. |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
GI Wire |
10.000 |
kg |
90.00 |
900.00 |
|
Re-bar G60 |
1050.000 |
kg |
40.20 |
42210.00 |
|
|
Sub-Total(A1) |
43110.00
|
602.05
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Re-bar Work |
1000.000 |
kg |
1.65 |
1650.00 |
|
Local carrying Rod |
0.000 |
kg |
0.25 |
0.00 |
|
|
Sub-Total(L0) |
1650.00
|
602.05
|
|
|
|
Total(1) |
|
1204.10 |
|
Add over head on Total(1)
|
3.0 % |
36.12 |
|
|
|
Total(2) |
|
1240.22 |
|
Add Profit on Total(2) |
8.0 % |
99.22
|
|
|
|
Total(3) |
|
1339.44 |
|
Add VAT on Unit Price |
4.5 % |
63.12 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
1402.56
|
|
|
|
Say |
|
Item: 09B (A10B) Re-bar (G60)-Precast Pile 400x400 |
|
Basis:1000
kg. |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
GI Wire |
8.500 |
kg |
90.00 |
765.00 |
|
Re-bar G60 |
1050.000 |
kg |
40.20 |
42210.00 |
|
|
Sub-Total(A1) |
42975.00
|
602.05
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Re-bar Work |
1000.000 |
kg |
1.65 |
1650.00 |
|
Rebar Carrying |
1000.000 |
kg |
0.35 |
350.00 |
|
|
Sub-Total(L0) |
2000.00
|
602.05
|
|
|
|
Total(1) |
|
1204.10 |
|
Add over head on Total(1)
|
3.0 % |
36.12 |
|
|
|
Total(2) |
|
1240.22 |
|
Add Profit on Total(2) |
8.0 % |
99.22
|
|
|
|
Total(3) |
|
1339.44 |
|
Add VAT on Unit Price |
4.5 % |
63.12 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
1402.56
|
|
|
|
Say |
|
Item: 04E (A15) Pre-cast Pile Driving (400x400) |
|
Basis:60
rft |
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Pile driving equipment |
1.000 |
set |
2000.00 |
2000.00 |
|
Fuel (diesel for piling) |
19.500 |
Ltr |
33.00 |
643.50 |
|
Lubricant |
3.900 |
Ltr |
115.00 |
448.50 |
|
Crane |
59.642 |
rft |
31.00 |
1848.90 |
|
Trailer |
59.642 |
rft |
21.00 |
1252.48 |
|
|
Sub-Total(E1) |
6193.38
|
602.05
|
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Pile shifting, driving |
59.642 |
rft |
143.00 |
8528.81 |
|
|
Sub-Total(L1) |
8528.81
|
602.05
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Hardware materials |
1.000 |
LS |
140.00 |
140.00 |
|
|
Sub-Total(M1) |
140.00
|
602.05
|
|
|
|
Total(1) |
|
1806.15 |
|
Add over head on Total(1)
|
3.0 % |
54.18 |
|
|
|
Total(2) |
|
1860.33 |
|
Add Profit on Total(2) |
8.0 % |
148.83
|
|
|
|
Total(3) |
|
2009.16 |
|
Add VAT on Unit Price |
4.5 % |
94.67 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
2103.83
|
|
|
|
Say |
|
Item: 04C (A15B) Pre-cast Pile Driving (250x250) |
|
Basis:18
rft |
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Fuel (diesel for piling) |
8.000 |
Ltr |
33.00 |
264.00 |
|
Lubricant |
1.000 |
Ltr |
115.00 |
115.00 |
|
Diesel |
3.360 |
Ltr |
26.00 |
87.36 |
|
Mobil |
0.240 |
Ltr |
70.00 |
16.80 |
|
Hydraulic Oil |
0.240 |
Ltr |
80.00 |
19.20 |
|
Payloader |
0.030 |
day |
8000.00 |
240.00 |
|
Pile Driving Equipment(M) |
0.330 |
day |
1000.00 |
330.00 |
|
|
Sub-Total(E1) |
1072.36
|
602.05
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Pile driving (250x250mm) |
18.300 |
rft |
50.00 |
915.00 |
|
|
Sub-Total(L0) |
915.00
|
602.05
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Hardware materials |
0.160 |
LS |
140.00 |
22.40 |
|
|
Sub-Total(M1) |
22.40
|
602.05
|
|
|
|
Total(1) |
|
1806.15 |
|
Add over head on Total(1)
|
3.0 % |
54.18 |
|
|
|
Total(2) |
|
1860.33 |
|
Add Profit on Total(2) |
8.0 % |
148.83
|
|
|
|
Total(3) |
|
2009.16 |
|
Add VAT on Unit Price |
4.5 % |
94.67 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
2103.83
|
|
|
|
Say |
|
Item: 04D (A15B1) Precast Pile Driving250x250,bedPr |
|
Basis:26
rft |
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Fuel (diesel for piling) |
8.000 |
Ltr |
33.00 |
264.00 |
|
Lubricant |
1.000 |
Ltr |
115.00 |
115.00 |
|
Diesel |
35.000 |
Ltr |
26.00 |
910.00 |
|
Mobil |
2.500 |
Ltr |
70.00 |
175.00 |
|
Hydraulic Oil |
2.500 |
Ltr |
80.00 |
200.00 |
|
Payloader |
0.313 |
day |
8000.00 |
2504.00 |
|
Pile Driving Equipment(M) |
0.330 |
day |
1000.00 |
330.00 |
|
Mini Roller |
0.125 |
day |
500.00 |
62.50 |
|
|
Sub-Total(E1) |
4560.50
|
602.05
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Pile driving (250x250mm) |
26.200 |
rft |
50.00 |
1310.00 |
|
|
Sub-Total(L0) |
1310.00
|
602.05
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Hardware materials |
0.160 |
LS |
140.00 |
22.40 |
|
|
Sub-Total(M1) |
22.40
|
602.05
|
|
|
|
Total(1) |
|
1806.15 |
|
Add over head on Total(1)
|
3.0 % |
54.18 |
|
|
|
Total(2) |
|
1860.33 |
|
Add Profit on Total(2) |
8.0 % |
148.83
|
|
|
|
Total(3) |
|
2009.16 |
|
Add VAT on Unit Price |
4.5 % |
94.67 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
2103.83
|
|
|
|
Say |
|
Item: 05B (A18L0) Pile Head Breaking (400x400) |
|
Basis:1
no. |
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Ordinary Labour Supply |
4.000 |
nos. |
100.00 |
400.00 |
|
Head Mason Supply |
0.250 |
nos. |
200.00 |
50.00 |
|
|
Sub-Total(L0) |
450.00
|
450.00
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Stone Cutting Disc - 175 |
0.250 |
no |
70.00 |
17.50 |
|
Diamond Cuting Disc- 175 |
0.050 |
no |
2200.00 |
110.00 |
|
Cheisel - Hammer |
3.000 |
no |
55.00 |
165.00 |
|
|
Sub-Total(M1) |
292.50
|
292.50
|
|
|
|
Total(1) |
|
742.50 |
|
Add over head on Total(1)
|
3.0 % |
22.28 |
|
|
|
Total(2) |
|
764.78 |
|
Add Profit on Total(2) |
8.0 % |
61.18
|
|
|
|
Total(3) |
|
825.96 |
|
Add VAT on Unit Price |
4.5 % |
38.92 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
864.88
|
|
|
|
Say |
|
Item: 05A (A18L2) Precast Pilehead breaking |
|
Basis:1
no. |
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Ordinary Labour Supply |
0.330 |
nos. |
100.00 |
33.00 |
|
|
Sub-Total(L0) |
33.00
|
33.00
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Stone Cutting Disc - 175 |
0.250 |
no |
70.00 |
17.50 |
|
Cheisel - Hammer |
1.000 |
no |
55.00 |
55.00 |
|
|
Sub-Total(M1) |
72.50
|
72.50
|
|
|
|
Total(1) |
|
105.50 |
|
Add over head on Total(1)
|
3.0 % |
3.17 |
|
|
|
Total(2) |
|
108.67 |
|
Add Profit on Total(2) |
8.0 % |
8.69
|
|
|
|
Total(3) |
|
117.36 |
|
Add VAT on Unit Price |
4.5 % |
5.53 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
122.89
|
|
|
|
Say |
|
Item: 06A (A18L3) Welding between column-Boundary |
|
Basis:1
no. |
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Carpenter Helper |
0.167 |
nos. |
150.00 |
25.05 |
|
Welding surface cleaning |
1.000 |
no |
10.00 |
10.00 |
|
|
Sub-Total(L0) |
35.05
|
35.05
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Welding Electrode VM 8-no |
0.200 |
pack |
520.00 |
104.00 |
|
|
Sub-Total(M1) |
104.00
|
104.00
|
|
|
|
Total(1) |
|
139.05 |
|
Add over head on Total(1)
|
3.0 % |
4.17 |
|
|
|
Total(2) |
|
143.22 |
|
Add Profit on Total(2) |
8.0 % |
11.46
|
|
|
|
Total(3) |
|
154.68 |
|
Add VAT on Unit Price |
4.5 % |
7.29 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
161.97
|
|
|
|
Say |
|
Item: 06B (A18L4) Welding betn Column-Boundary-Gate |
|
Basis:1
no. |
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Carpenter Helper |
0.167 |
nos. |
150.00 |
25.05 |
|
Welding surface cleaning |
1.000 |
no |
10.00 |
10.00 |
|
|
Sub-Total(L0) |
35.05
|
35.05
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Welding Electrode VM 8-no |
0.250 |
pack |
520.00 |
130.00 |
|
|
Sub-Total(M1) |
130.00
|
130.00
|
|
|
|
Total(1) |
|
165.05 |
|
Add over head on Total(1)
|
3.0 % |
4.95 |
|
|
|
Total(2) |
|
170.00 |
|
Add Profit on Total(2) |
8.0 % |
13.60
|
|
|
|
Total(3) |
|
183.60 |
|
Add VAT on Unit Price |
4.5 % |
8.65 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
192.25
|
|
|
|
Say |
|