Return Main Menu

Project Pile and GB for boundary wall at Te-Park
Item: 01 (A01B) Earth cutting
Basis:1 no.
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
E/Cutting
3000.000
cft
2.00
6000.00
Sub-Total(L0)
6000.00
6000.00
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Shoring for Excavation
4000.000
sft
2.15
8600.00
Sub-Total(M1)
8600.00
8600.00
Total(1)
14600.00
Add over head on Total(1)
3.0 %
438.00
Total(2)
15038.00
Add Profit on Total(2)
8.0 %
1203.04
Total(3)
16241.04
Add VAT on Unit Price
4.5 %
765.28
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
17006.32
Say
17006
per L.S
Item: 03 (A05) Sand Filling
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Filling Sand
130.000
cft
8.50
1105.00
Sub-Total(A1)
1105.00
390.23
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mini Roller Compaction
100.000
cft
1.00
100.00
Mini Dumper
130.000
cft
2.00
260.00
Payloader
0.000
day
8000.00
0.00
Dump Truck
0.000
day
8300.00
0.00
Sub-Total(E1)
360.00
127.13
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
0.800
nos.
100.00
80.00
Sub-Total(L0)
80.00
28.25
Total(1)
545.62
Add over head on Total(1)
3.0 %
16.37
Total(2)
561.99
Add Profit on Total(2)
8.0 %
44.96
Total(3)
606.94
Add VAT on Unit Price
4.5 %
28.60
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
635.54
Say
636
per M3
Item: 02 (A05G) Earth Filling (Loose Volume)
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Filling Earth
100.000
cft
6.60
660.00
Sub-Total(A1)
660.00
233.08
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
0.800
nos.
100.00
80.00
Sub-Total(L0)
80.00
28.25
Total(1)
261.33
Add over head on Total(1)
3.0 %
7.84
Total(2)
269.17
Add Profit on Total(2)
8.0 %
21.53
Total(3)
290.70
Add VAT on Unit Price
4.5 %
13.70
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
304.40
Say
304
per M3
Item: 04B (A08A0) RCC (1:1.5:3) in Pile (400x400)
Basis:103 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement
23.000
bag
343.00
7889.00
Sand - Sylhet
43.000
cft
24.00
1032.00
Stone-chips
86.000
cft
80.00
6880.00
Sub-Total(A1)
15801.00
5433.42
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Batching Plant , Vibrator
102.713
cft
8.00
821.70
Sub-Total(E1)
821.70
282.56
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Formwork upto 10ft from P
238.240
sft
8.00
1905.92
Sand Screening
43.000
cft
1.00
43.00
RCC Casting.
102.713
cft
8.00
821.70
Sub-Total(L0)
2770.62
952.72
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Pile Shutter (steel)
238.240
sft
12.00
2858.88
Cost of Pre-casr yard
59.642
rft
8.00
477.14
Sub-Total(M1)
3336.02
1147.14
Total(1)
7815.84
Add over head on Total(1)
3.0 %
234.48
Total(2)
8050.32
Add Profit on Total(2)
8.0 %
644.03
Total(3)
8694.34
Add VAT on Unit Price
4.5 %
409.68
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
9104.02
Say
9104
per M3
Item: 04A (A08A1) RCC(1:1.5:3) in Pile (250x250)
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
20.500
cft
13.00
266.50
Cement
22.000
bag
343.00
7546.00
Sand - Sylhet
20.500
cft
24.00
492.00
Stone-chips
82.000
cft
80.00
6560.00
Sub-Total(A1)
14864.50
5249.40
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mini Dumper
100.000
cft
2.00
200.00
Batching Plant , Vibrator
100.000
cft
8.00
800.00
Sub-Total(E1)
1000.00
353.15
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Formwork upto 10ft from P
362.900
sft
8.00
2903.20
Sand Screening
41.000
cft
1.00
41.00
RCC Casting.
100.000
cft
8.00
800.00
Sub-Total(L0)
3744.20
1322.26
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Pile Shutter (steel)
362.900
sft
12.00
4354.80
Cost of Pre-casr yard
150.000
rft
8.00
1200.00
Sub-Total(M1)
5554.80
1961.68
Total(1)
8886.49
Add over head on Total(1)
3.0 %
266.59
Total(2)
9153.08
Add Profit on Total(2)
8.0 %
732.25
Total(3)
9885.33
Add VAT on Unit Price
4.5 %
465.80
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
10351.13
Say
10351
per M3
Item: 07 (A08C1) RCC (1:2:4) in S-column
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
22.500
cft
13.00
292.50
Cement
18.000
bag
343.00
6174.00
Sand - Sylhet
22.500
cft
24.00
540.00
Stone-chips
90.000
cft
80.00
7200.00
Sub-Total(A1)
14206.50
5017.03
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
100.000
cft
2.00
200.00
Mini Dumper
100.000
cft
2.00
200.00
Sub-Total(E1)
400.00
141.26
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Form work Foot-col-Str
476.267
sft
6.00
2857.60
RCC Casting.
100.000
cft
8.00
800.00
Sub-Total(L0)
3657.60
1291.68
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Forms
476.267
sft
5.00
2381.34
Sub-Total(M1)
2381.34
840.97
Total(1)
7290.94
Add over head on Total(1)
3.0 %
218.73
Total(2)
7509.66
Add Profit on Total(2)
8.0 %
600.77
Total(3)
8110.44
Add VAT on Unit Price
4.5 %
382.17
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
8492.60
Say
8493
per M3
Item: 08 (A08D1) RCC (1:2:4) in GB-Boundary
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
22.500
cft
13.00
292.50
Cement
18.000
bag
343.00
6174.00
Sand - Sylhet
22.500
cft
24.00
540.00
Stone-chips
90.000
cft
80.00
7200.00
Sub-Total(A1)
14206.50
5017.03
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
100.000
cft
2.00
200.00
Mini Dumper
100.000
cft
2.00
200.00
Sub-Total(E1)
400.00
141.26
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Form work Foot-col-Str
340.960
sft
6.00
2045.76
Sub-Total(L0)
2045.76
722.46
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Forms
340.960
sft
5.00
1704.80
Sub-Total(M1)
1704.80
602.05
Total(1)
6482.80
Add over head on Total(1)
3.0 %
194.48
Total(2)
6677.28
Add Profit on Total(2)
8.0 %
534.18
Total(3)
7211.46
Add VAT on Unit Price
4.5 %
339.81
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
7551.27
Say
7551
per M3
Item: 09A (A10A) Re-bar Grade 60
Basis:1000 kg.
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
GI Wire
10.000
kg
90.00
900.00
Re-bar G60
1050.000
kg
40.20
42210.00
Sub-Total(A1)
43110.00
602.05
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Re-bar Work
1000.000
kg
1.65
1650.00
Local carrying Rod
0.000
kg
0.25
0.00
Sub-Total(L0)
1650.00
602.05
Total(1)
1204.10
Add over head on Total(1)
3.0 %
36.12
Total(2)
1240.22
Add Profit on Total(2)
8.0 %
99.22
Total(3)
1339.44
Add VAT on Unit Price
4.5 %
63.12
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
1402.56
Say
1403
per TON
Item: 09B (A10B) Re-bar (G60)-Precast Pile 400x400
Basis:1000 kg.
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
GI Wire
8.500
kg
90.00
765.00
Re-bar G60
1050.000
kg
40.20
42210.00
Sub-Total(A1)
42975.00
602.05
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Re-bar Work
1000.000
kg
1.65
1650.00
Rebar Carrying
1000.000
kg
0.35
350.00
Sub-Total(L0)
2000.00
602.05
Total(1)
1204.10
Add over head on Total(1)
3.0 %
36.12
Total(2)
1240.22
Add Profit on Total(2)
8.0 %
99.22
Total(3)
1339.44
Add VAT on Unit Price
4.5 %
63.12
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
1402.56
Say
1403
per TON
Item: 04E (A15) Pre-cast Pile Driving (400x400)
Basis:60 rft
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Pile driving equipment
1.000
set
2000.00
2000.00
Fuel (diesel for piling)
19.500
Ltr
33.00
643.50
Lubricant
3.900
Ltr
115.00
448.50
Crane
59.642
rft
31.00
1848.90
Trailer
59.642
rft
21.00
1252.48
Sub-Total(E1)
6193.38
602.05
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Pile shifting, driving
59.642
rft
143.00
8528.81
Sub-Total(L1)
8528.81
602.05
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Hardware materials
1.000
LS
140.00
140.00
Sub-Total(M1)
140.00
602.05
Total(1)
1806.15
Add over head on Total(1)
3.0 %
54.18
Total(2)
1860.33
Add Profit on Total(2)
8.0 %
148.83
Total(3)
2009.16
Add VAT on Unit Price
4.5 %
94.67
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
2103.83
Say
2104
per RM
Item: 04C (A15B) Pre-cast Pile Driving (250x250)
Basis:18 rft
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Fuel (diesel for piling)
8.000
Ltr
33.00
264.00
Lubricant
1.000
Ltr
115.00
115.00
Diesel
3.360
Ltr
26.00
87.36
Mobil
0.240
Ltr
70.00
16.80
Hydraulic Oil
0.240
Ltr
80.00
19.20
Payloader
0.030
day
8000.00
240.00
Pile Driving Equipment(M)
0.330
day
1000.00
330.00
Sub-Total(E1)
1072.36
602.05
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Pile driving (250x250mm)
18.300
rft
50.00
915.00
Sub-Total(L0)
915.00
602.05
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Hardware materials
0.160
LS
140.00
22.40
Sub-Total(M1)
22.40
602.05
Total(1)
1806.15
Add over head on Total(1)
3.0 %
54.18
Total(2)
1860.33
Add Profit on Total(2)
8.0 %
148.83
Total(3)
2009.16
Add VAT on Unit Price
4.5 %
94.67
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
2103.83
Say
2104
per RM
Item: 04D (A15B1) Precast Pile Driving250x250,bedPr
Basis:26 rft
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Fuel (diesel for piling)
8.000
Ltr
33.00
264.00
Lubricant
1.000
Ltr
115.00
115.00
Diesel
35.000
Ltr
26.00
910.00
Mobil
2.500
Ltr
70.00
175.00
Hydraulic Oil
2.500
Ltr
80.00
200.00
Payloader
0.313
day
8000.00
2504.00
Pile Driving Equipment(M)
0.330
day
1000.00
330.00
Mini Roller
0.125
day
500.00
62.50
Sub-Total(E1)
4560.50
602.05
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Pile driving (250x250mm)
26.200
rft
50.00
1310.00
Sub-Total(L0)
1310.00
602.05
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Hardware materials
0.160
LS
140.00
22.40
Sub-Total(M1)
22.40
602.05
Total(1)
1806.15
Add over head on Total(1)
3.0 %
54.18
Total(2)
1860.33
Add Profit on Total(2)
8.0 %
148.83
Total(3)
2009.16
Add VAT on Unit Price
4.5 %
94.67
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
2103.83
Say
2104
per RM
Item: 05B (A18L0) Pile Head Breaking (400x400)
Basis:1 no.
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
4.000
nos.
100.00
400.00
Head Mason Supply
0.250
nos.
200.00
50.00
Sub-Total(L0)
450.00
450.00
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Stone Cutting Disc - 175
0.250
no
70.00
17.50
Diamond Cuting Disc- 175
0.050
no
2200.00
110.00
Cheisel - Hammer
3.000
no
55.00
165.00
Sub-Total(M1)
292.50
292.50
Total(1)
742.50
Add over head on Total(1)
3.0 %
22.28
Total(2)
764.78
Add Profit on Total(2)
8.0 %
61.18
Total(3)
825.96
Add VAT on Unit Price
4.5 %
38.92
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
864.88
Say
865
per NOS
Item: 05A (A18L2) Precast Pilehead breaking
Basis:1 no.
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
0.330
nos.
100.00
33.00
Sub-Total(L0)
33.00
33.00
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Stone Cutting Disc - 175
0.250
no
70.00
17.50
Cheisel - Hammer
1.000
no
55.00
55.00
Sub-Total(M1)
72.50
72.50
Total(1)
105.50
Add over head on Total(1)
3.0 %
3.17
Total(2)
108.67
Add Profit on Total(2)
8.0 %
8.69
Total(3)
117.36
Add VAT on Unit Price
4.5 %
5.53
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
122.89
Say
123
per NOS
Item: 06A (A18L3) Welding between column-Boundary
Basis:1 no.
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Carpenter Helper
0.167
nos.
150.00
25.05
Welding surface cleaning
1.000
no
10.00
10.00
Sub-Total(L0)
35.05
35.05
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Welding Electrode VM 8-no
0.200
pack
520.00
104.00
Sub-Total(M1)
104.00
104.00
Total(1)
139.05
Add over head on Total(1)
3.0 %
4.17
Total(2)
143.22
Add Profit on Total(2)
8.0 %
11.46
Total(3)
154.68
Add VAT on Unit Price
4.5 %
7.29
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
161.97
Say
162
per NO
Item: 06B (A18L4) Welding betn Column-Boundary-Gate
Basis:1 no.
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Carpenter Helper
0.167
nos.
150.00
25.05
Welding surface cleaning
1.000
no
10.00
10.00
Sub-Total(L0)
35.05
35.05
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Welding Electrode VM 8-no
0.250
pack
520.00
130.00
Sub-Total(M1)
130.00
130.00
Total(1)
165.05
Add over head on Total(1)
3.0 %
4.95
Total(2)
170.00
Add Profit on Total(2)
8.0 %
13.60
Total(3)
183.60
Add VAT on Unit Price
4.5 %
8.65
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
192.25
Say
192
per NO.