Project Extn of Documentn Mod.O/A Solid Track-II
Item: 01 (A09D1) Aluminium Partition Remove
Basis:1 sft
S2.Alum,SS/MS,FalseCeil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Aluminium Partition Remov
1.000
sft
3.50
3.50
Sub-Total(S2)
3.50
37.67
Total(1)
37.67
Add over head on Total(1)
3.0 %
1.13
Total(2)
38.80
Add Profit on Total(2)
10.0 %
3.88
Total(3)
42.68
Add VAT on Unit Price
4.5 %
2.10
Add Income Tax on Unit Price
4.0 %
1.87
Unit Price
46.65
Say
47
per M2
Item: 02 (A11U) Al.PC) Partition Frost Glass-2400
Basis:1 sft
S2.Alum,SS/MS,FalseCeil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Al.(PC)Partition,FrstGls
1.000
sft
220.00
220.00
Sub-Total(S2)
220.00
2368.08
Total(1)
2368.08
Add over head on Total(1)
3.0 %
71.04
Total(2)
2439.12
Add Profit on Total(2)
10.0 %
243.91
Total(3)
2683.03
Add VAT on Unit Price
4.5 %
131.95
Add Income Tax on Unit Price
4.0 %
117.29
Unit Price
2932.28
Say
2932
per M2
Item: 03 (A11A) Alum(PC)-Swing Door Frosted Glass
Basis:1 sft
S2.Alum,SS/MS,FalseCeil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Al.(PC) Swing Door,FrsGls
1.000
sft
400.00
400.00
Sub-Total(S2)
400.00
4305.60
Total(1)
4305.60
Add over head on Total(1)
3.0 %
129.17
Total(2)
4434.77
Add Profit on Total(2)
10.0 %
443.48
Total(3)
4878.24
Add VAT on Unit Price
4.5 %
239.91
Add Income Tax on Unit Price
4.0 %
213.26
Unit Price
5331.42
Say
5331
per M2
Item: 04 (A13K) Apply Baralastic Paint - Labour
Basis:1 sft
L6.Labour Paints
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
ApplyBaralastic Paint-Wal
1.000
sft
4.50
4.50
Sub-Total(L6)
4.50
48.44
Total(1)
48.44
Add over head on Total(1)
3.0 %
1.45
Total(2)
49.89
Add Profit on Total(2)
10.0 %
4.99
Total(3)
54.88
Add VAT on Unit Price
4.5 %
2.70
Add Income Tax on Unit Price
4.0 %
2.40
Unit Price
59.98
Say
60
per M2