Return Main Menu

Project 3no.Adl Pile-Solid Track-II Utility Bldg
Item: 01 (A09A1) Dismatle Pipe Rack Base
Basis:1 no.
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mini Dumper
100.000
cft
2.00
200.00
Sub-Total(E1)
200.00
200.00
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
100.000
nos.
100.00
10000.00
Sub-Total(L0)
10000.00
10000.00
Total(1)
10200.00
Add over head on Total(1)
3.0 %
306.00
Total(2)
10506.00
Add Profit on Total(2)
8.0 %
840.48
Total(3)
11346.48
Add VAT on Unit Price
4.5 %
558.02
Add Income Tax on Unit Price
4.0 %
496.02
Unit Price
12400.52
Say
12401
per LS
Item: 02 (A08M) RCC(1:1.5:3) -500mm Bored Pile
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement
26.400
bag
343.00
9055.20
Sand - Sylhet
51.600
cft
24.00
1238.40
Stone-chips
103.200
cft
80.00
8256.00
Sub-Total(A1)
18549.60
6550.79
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Rig,Mixer M/c
120.000
cft
10.00
1200.00
Sub-Total(E1)
1200.00
423.78
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
RCC Casting.
120.000
cft
8.00
960.00
Sub-Total(L0)
960.00
339.02
Total(1)
7313.60
Add over head on Total(1)
3.0 %
219.41
Total(2)
7533.00
Add Profit on Total(2)
8.0 %
602.64
Total(3)
8135.64
Add VAT on Unit Price
4.5 %
400.11
Add Income Tax on Unit Price
4.0 %
355.66
Unit Price
8891.41
Say
8891
per M3
Item: 03 (A10D) Re-bar (G60) - Bored Pile
Basis:1000 kg.
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
GI Wire
8.000
kg
90.00
720.00
Re-bar G60
1050.000
kg
40.20
42210.00
Sub-Total(A1)
42930.00
339.02
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Welding M/c
1000.000
kg
0.50
500.00
Sub-Total(E1)
500.00
339.02
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Re-bar Work
1000.000
kg
1.65
1650.00
Sub-Total(L0)
1650.00
339.02
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Welding Electrode VM 8-no
3.000
pack
520.00
1560.00
Sub-Total(M1)
1560.00
339.02
Total(1)
1356.10
Add over head on Total(1)
3.0 %
40.68
Total(2)
1396.78
Add Profit on Total(2)
8.0 %
111.74
Total(3)
1508.52
Add VAT on Unit Price
4.5 %
74.19
Add Income Tax on Unit Price
4.0 %
65.95
Unit Price
1648.66
Say
1649
per TON
Item: 04 (A15A) Insitu Pile Boring -400mm dia
Basis:1 rft
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Bored Piling Equipment
1.000
rft
30.00
30.00
Sub-Total(E1)
30.00
339.02
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Pile Boring - 500mm dia
1.000
rft
90.00
90.00
Sub-Total(L1)
90.00
339.02
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Bentonite
1.000
kg
20.00
20.00
Sub-Total(M1)
20.00
339.02
Total(1)
1017.07
Add over head on Total(1)
3.0 %
30.51
Total(2)
1047.58
Add Profit on Total(2)
8.0 %
83.81
Total(3)
1131.39
Add VAT on Unit Price
4.5 %
55.64
Add Income Tax on Unit Price
4.0 %
49.46
Unit Price
1236.49
Say
1236
per RM