Project Solid Track II Utility - Substructure |
Item: 01 (A18L1) Insitu Pile Head Breaking |
|
Basis:1
no. |
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Ordinary Labour Supply |
1.000 |
nos. |
100.00 |
100.00 |
|
|
Sub-Total(L0) |
100.00
|
100.00
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Stone Cutting Disc - 175 |
1.000 |
no |
70.00 |
70.00 |
|
Diamond Cuting Disc- 175 |
0.070 |
no |
2200.00 |
154.00 |
|
Cheisel - Hammer |
1.000 |
no |
55.00 |
55.00 |
|
|
Sub-Total(M1) |
279.00
|
279.00
|
|
|
|
Total(1) |
|
379.00 |
|
Add over head on Total(1)
|
3.0 % |
11.37 |
|
|
|
Total(2) |
|
390.37 |
|
Add Profit on Total(2) |
8.0 % |
31.23
|
|
|
|
Total(3) |
|
421.60 |
|
Add VAT on Unit Price |
4.5 % |
19.87 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
441.47
|
|
|
|
Say |
|
Item: 02 (A01D) E/Cuting with shoring,soil remove |
|
Basis:100
cft |
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Earth Work in Excavation |
100.000 |
cft |
1.80 |
180.00 |
|
|
Sub-Total(L1) |
180.00
|
63.57
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Shoring for Excavation |
38.440 |
sft |
2.15 |
82.65 |
|
|
Sub-Total(M1) |
82.65
|
29.19
|
|
|
|
Total(1) |
|
92.75 |
|
Add over head on Total(1)
|
3.0 % |
2.78 |
|
|
|
Total(2) |
|
95.54 |
|
Add Profit on Total(2) |
8.0 % |
7.64
|
|
|
|
Total(3) |
|
103.18 |
|
Add VAT on Unit Price |
4.5 % |
4.86 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
108.04
|
|
|
|
Say |
|
Item: 03 (A05F) Back Filling |
|
Basis:100
cft |
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mini Roller Compaction |
100.000 |
cft |
1.00 |
100.00 |
|
|
Sub-Total(E1) |
100.00
|
35.32
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Ordinary Labour Supply |
1.000 |
nos. |
100.00 |
100.00 |
|
|
Sub-Total(L0) |
100.00
|
35.32
|
|
|
|
Total(1) |
|
70.63 |
|
Add over head on Total(1)
|
3.0 % |
2.12 |
|
|
|
Total(2) |
|
72.75 |
|
Add Profit on Total(2) |
8.0 % |
5.82
|
|
|
|
Total(3) |
|
78.57 |
|
Add VAT on Unit Price |
4.5 % |
3.70 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
82.27
|
|
|
|
Say |
|
Item: 04 (A02B) Brick Flat Soling |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Filling Sand |
5.000 |
cft |
8.50 |
42.50 |
|
Brick |
300.000 |
no. |
3.80 |
1140.00 |
|
|
Sub-Total(A1) |
1182.50
|
127.28
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Ordinary Labour Supply |
0.100 |
nos. |
100.00 |
10.00 |
|
Head Mason Supply |
0.250 |
nos. |
200.00 |
50.00 |
|
|
Sub-Total(L0) |
60.00
|
6.46
|
|
|
|
Total(1) |
|
133.74 |
|
Add over head on Total(1)
|
3.0 % |
4.01 |
|
|
|
Total(2) |
|
137.75 |
|
Add Profit on Total(2) |
8.0 % |
11.02
|
|
|
|
Total(3) |
|
148.78 |
|
Add VAT on Unit Price |
4.5 % |
7.01 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
155.79
|
|
|
|
Say |
|
Item: 05 (A02F) Single layer polythene |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Polythene |
1.500 |
kg |
77.00 |
115.50 |
|
|
Sub-Total(A1) |
115.50
|
12.43
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Ordinary Labour Supply |
0.020 |
nos. |
100.00 |
2.00 |
|
|
Sub-Total(L0) |
2.00
|
0.22
|
|
|
|
Total(1) |
|
12.65 |
|
Add over head on Total(1)
|
3.0 % |
0.38 |
|
|
|
Total(2) |
|
13.03 |
|
Add Profit on Total(2) |
8.0 % |
1.04
|
|
|
|
Total(3) |
|
14.07 |
|
Add VAT on Unit Price |
4.5 % |
0.66 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
14.73
|
|
|
|
Say |
|
Item: 06 (A06B) Brick Work 250mm in Foundation |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Brick |
1200.000 |
no. |
3.80 |
4560.00 |
|
Sand - Local - Mymensingh |
40.000 |
cft |
13.00 |
520.00 |
|
Cement |
5.000 |
bag |
343.00 |
1715.00 |
|
|
Sub-Total(A1) |
6795.00
|
2399.65
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
250mm Brickwork upto 7 ft |
100.000 |
cft |
4.25 |
425.00 |
|
|
Sub-Total(L0) |
425.00
|
150.09
|
|
|
|
Total(1) |
|
2549.74 |
|
Add over head on Total(1)
|
3.0 % |
76.49 |
|
|
|
Total(2) |
|
2626.24 |
|
Add Profit on Total(2) |
8.0 % |
210.10
|
|
|
|
Total(3) |
|
2836.33 |
|
Add VAT on Unit Price |
4.5 % |
133.65 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
2969.98
|
|
|
|
Say |
|
Item: 07 (A10A) Re-bar Grade 60 |
|
Basis:1000
kg. |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
GI Wire |
10.000 |
kg |
90.00 |
900.00 |
|
Re-bar G60 |
1050.000 |
kg |
40.20 |
42210.00 |
|
|
Sub-Total(A1) |
43110.00
|
150.09
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Re-bar Work |
1000.000 |
kg |
1.65 |
1650.00 |
|
Local carrying Rod |
0.000 |
kg |
0.25 |
0.00 |
|
|
Sub-Total(L0) |
1650.00
|
150.09
|
|
|
|
Total(1) |
|
300.18 |
|
Add over head on Total(1)
|
3.0 % |
9.01 |
|
|
|
Total(2) |
|
309.18 |
|
Add Profit on Total(2) |
8.0 % |
24.73
|
|
|
|
Total(3) |
|
333.92 |
|
Add VAT on Unit Price |
4.5 % |
15.73 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
349.65
|
|
|
|
Say |
|
Item: 08A (A08B1) RCC(1:1.5:3) in Pile Cap |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
14.330 |
cft |
13.00 |
186.29 |
|
Cement |
22.000 |
bag |
343.00 |
7546.00 |
|
Sand - Sylhet |
28.670 |
cft |
24.00 |
688.08 |
|
Stone-chips |
86.000 |
cft |
80.00 |
6880.00 |
|
|
Sub-Total(A1) |
15300.37
|
5403.33
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mini Dumper |
100.000 |
cft |
2.00 |
200.00 |
|
Batching Plant , Vibrator |
100.000 |
cft |
8.00 |
800.00 |
|
|
Sub-Total(E1) |
1000.00
|
353.15
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Formwork upto 10ft from P |
89.310 |
sft |
8.00 |
714.48 |
|
Sand Screening |
43.000 |
cft |
1.00 |
43.00 |
|
RCC Casting. |
100.000 |
cft |
8.00 |
800.00 |
|
|
Sub-Total(L0) |
1557.48
|
550.02
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Forms |
61.820 |
sft |
5.00 |
309.10 |
|
|
Sub-Total(M1) |
309.10
|
109.16
|
|
|
|
Total(1) |
|
6415.66 |
|
Add over head on Total(1)
|
3.0 % |
192.47 |
|
|
|
Total(2) |
|
6608.13 |
|
Add Profit on Total(2) |
8.0 % |
528.65
|
|
|
|
Total(3) |
|
7136.78 |
|
Add VAT on Unit Price |
4.5 % |
336.29 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
7473.07
|
|
|
|
Say |
|
Item: 08B (A08D) RCC (1:1.5:3) in GB/TB |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Cement |
22.000 |
bag |
343.00 |
7546.00 |
|
Sand - Sylhet |
43.000 |
cft |
24.00 |
1032.00 |
|
Stone-chips |
86.000 |
cft |
80.00 |
6880.00 |
|
|
Sub-Total(A1) |
15458.00
|
5458.99
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mixer m/c and vibrator |
100.000 |
cft |
2.00 |
200.00 |
|
Mini Dumper |
100.000 |
cft |
2.00 |
200.00 |
|
|
Sub-Total(E1) |
400.00
|
141.26
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Formwork upto 10ft from P |
242.000 |
sft |
8.00 |
1936.00 |
|
RCC Casting. |
100.000 |
cft |
8.00 |
800.00 |
|
|
Sub-Total(L0) |
2736.00
|
966.22
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel pipe with B-plate |
0.000 |
no |
11.00 |
0.00 |
|
wood use 5-time-Garjan |
0.100 |
cft |
850.00 |
85.00 |
|
Steel form,S-structure |
242.000 |
sft |
10.00 |
2420.00 |
|
Wood use-6time mango |
0.200 |
cft |
350.00 |
70.00 |
|
|
Sub-Total(M1) |
2575.00
|
909.36
|
|
|
|
Total(1) |
|
7475.83 |
|
Add over head on Total(1)
|
3.0 % |
224.27 |
|
|
|
Total(2) |
|
7700.11 |
|
Add Profit on Total(2) |
8.0 % |
616.01
|
|
|
|
Total(3) |
|
8316.12 |
|
Add VAT on Unit Price |
4.5 % |
391.86 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
8707.97
|
|
|
|
Say |
|
Item: 08C (A09L1) RCC(1:1.5:3) in Lift Base/Wall |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
14.333 |
cft |
13.00 |
186.33 |
|
Cement |
22.000 |
bag |
343.00 |
7546.00 |
|
Sand - Sylhet |
28.667 |
cft |
24.00 |
688.01 |
|
Stone-chips |
86.000 |
cft |
80.00 |
6880.00 |
|
Plastocrete super-Sika |
3.440 |
kg |
155.00 |
533.20 |
|
|
Sub-Total(A1) |
15833.54
|
5591.61
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mini Dumper |
100.000 |
cft |
2.00 |
200.00 |
|
Batching Plant , Vibrator |
100.000 |
cft |
8.00 |
800.00 |
|
|
Sub-Total(E1) |
1000.00
|
353.15
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Formwork upto 10ft from P |
303.000 |
sft |
8.00 |
2424.00 |
|
Sand Screening |
43.000 |
cft |
1.00 |
43.00 |
|
RCC Casting. |
100.000 |
cft |
8.00 |
800.00 |
|
|
Sub-Total(L0) |
3267.00
|
1153.74
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Forms |
303.000 |
sft |
5.00 |
1515.00 |
|
|
Sub-Total(M1) |
1515.00
|
535.02
|
|
|
|
Total(1) |
|
7633.53 |
|
Add over head on Total(1)
|
3.0 % |
229.01 |
|
|
|
Total(2) |
|
7862.53 |
|
Add Profit on Total(2) |
8.0 % |
629.00
|
|
|
|
Total(3) |
|
8491.54 |
|
Add VAT on Unit Price |
4.5 % |
400.12 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
8891.66
|
|
|
|
Say |
|
Item: 08D (A08R) RCC Clmn (1:1.5:3) padestal |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Cement |
22.000 |
bag |
343.00 |
7546.00 |
|
Sand - Sylhet |
43.000 |
cft |
24.00 |
1032.00 |
|
Stone-chips |
86.000 |
cft |
80.00 |
6880.00 |
|
|
Sub-Total(A1) |
15458.00
|
5458.99
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mini Dumper |
100.000 |
cft |
2.00 |
200.00 |
|
Batching Plant , Vibrator |
100.000 |
cft |
8.00 |
800.00 |
|
|
Sub-Total(E1) |
1000.00
|
353.15
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Formwork upto 10ft from P |
305.000 |
sft |
8.00 |
2440.00 |
|
Sand Screening |
43.000 |
cft |
1.00 |
43.00 |
|
RCC Casting. |
100.000 |
cft |
8.00 |
800.00 |
|
|
Sub-Total(L0) |
3283.00
|
1159.39
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Forms |
305.000 |
sft |
5.00 |
1525.00 |
|
|
Sub-Total(M1) |
1525.00
|
538.55
|
|
|
|
Total(1) |
|
7510.09 |
|
Add over head on Total(1)
|
3.0 % |
225.30 |
|
|
|
Total(2) |
|
7735.39 |
|
Add Profit on Total(2) |
8.0 % |
618.83
|
|
|
|
Total(3) |
|
8354.22 |
|
Add VAT on Unit Price |
4.5 % |
393.65 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
8747.88
|
|
|
|
Say |
|
Item: 08E (A08E) RCC (1:1.5:3) in Suspended slab |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Cement |
22.000 |
bag |
343.00 |
7546.00 |
|
Sand - Sylhet |
43.000 |
cft |
24.00 |
1032.00 |
|
Stone-chips |
86.000 |
cft |
80.00 |
6880.00 |
|
|
Sub-Total(A1) |
15458.00
|
5458.99
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mixer m/c and vibrator |
100.000 |
cft |
2.00 |
200.00 |
|
Mini Dumper |
0.000 |
cft |
2.00 |
0.00 |
|
|
Sub-Total(E1) |
200.00
|
70.63
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Formwork upto 10ft from P |
240.000 |
sft |
8.00 |
1920.00 |
|
RCC Casting. |
100.000 |
cft |
8.00 |
800.00 |
|
|
Sub-Total(L0) |
2720.00
|
960.57
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
wood use 5-time-Garjan |
0.500 |
cft |
850.00 |
425.00 |
|
B-plate with pipe |
0.000 |
no |
16.00 |
0.00 |
|
Steel form,S-structure |
240.000 |
sft |
10.00 |
2400.00 |
|
Steel beam,S-structure |
0.000 |
no |
40.00 |
0.00 |
|
Wood use-6time mango |
1.200 |
cft |
350.00 |
420.00 |
|
|
Sub-Total(M1) |
3245.00
|
1145.97
|
|
|
|
Total(1) |
|
7636.16 |
|
Add over head on Total(1)
|
3.0 % |
229.08 |
|
|
|
Total(2) |
|
7865.25 |
|
Add Profit on Total(2) |
8.0 % |
629.22
|
|
|
|
Total(3) |
|
8494.47 |
|
Add VAT on Unit Price |
4.5 % |
400.26 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
8894.73
|
|
|
|
Say |
|
Item: 09 (A11H) Aluminium Louver |
|
Basis:1
sft |
S2.Alum,SS/MS,FalseCeil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Aluminium Louver |
1.000 |
sft |
310.00 |
310.00 |
|
|
Sub-Total(S2) |
310.00
|
3336.84
|
|
|
|
Total(1) |
|
3336.84 |
|
Add over head on Total(1)
|
3.0 % |
100.11 |
|
|
|
Total(2) |
|
3436.95 |
|
Add Profit on Total(2) |
8.0 % |
274.96
|
|
|
|
Total(3) |
|
3711.90 |
|
Add VAT on Unit Price |
4.5 % |
174.91 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
3886.81
|
|
|
|
Say |
|
Item: 10 (A03B) Pre-cast CC (1:1.5:3) Block-50mm |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
2.443 |
cft |
13.00 |
31.76 |
|
Cement |
3.740 |
bag |
343.00 |
1282.82 |
|
Sand - Sylhet |
4.886 |
cft |
24.00 |
117.26 |
|
Stone-chips |
14.620 |
cft |
80.00 |
1169.60 |
|
Wire Mesh |
105.000 |
sft |
7.00 |
735.00 |
|
|
Sub-Total(A1) |
3336.44
|
359.13
|
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Pre-cast block fitting |
45.860 |
no |
25.00 |
1146.50 |
|
|
Sub-Total(L1) |
1146.50
|
123.41
|
|
|
|
Total(1) |
|
482.54 |
|
Add over head on Total(1)
|
3.0 % |
14.48 |
|
|
|
Total(2) |
|
497.02 |
|
Add Profit on Total(2) |
8.0 % |
39.76
|
|
|
|
Total(3) |
|
536.78 |
|
Add VAT on Unit Price |
4.5 % |
25.29 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
562.08
|
|
|
|
Say |
|
Item: 11A (A22A) Ins. pit A type 500x500-in-in |
|
Basis:1
no. |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Brick |
21.000 |
no. |
3.80 |
79.80 |
|
Sand - Local - Mymensingh |
2.520 |
cft |
13.00 |
32.76 |
|
Polythene |
0.120 |
kg |
77.00 |
9.24 |
|
Cement |
3.160 |
bag |
343.00 |
1083.88 |
|
Sand - Sylhet |
4.000 |
cft |
24.00 |
96.00 |
|
Stone-chips |
11.930 |
cft |
80.00 |
954.40 |
|
Re-bar - G40 |
31.940 |
kg |
38.50 |
1229.69 |
|
GI Wire |
0.220 |
kg |
90.00 |
19.80 |
|
|
Sub-Total(A1) |
3505.57
|
3505.57
|
B1.Plumbing/Sanitr Pipe |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
CI Cover 300 mm dia |
1.000 |
no. |
750.00 |
750.00 |
|
|
Sub-Total(B1) |
750.00
|
750.00
|
C1.Steel Structures |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Galvanized Angle 38x38 |
1.720 |
rft |
125.00 |
215.00 |
|
MS Grating 200x75 |
1.000 |
no. |
100.00 |
100.00 |
|
|
Sub-Total(C1) |
315.00
|
315.00
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Re-bar Work |
30.420 |
kg |
1.65 |
50.19 |
|
Formwork upto 10ft from P |
35.830 |
sft |
8.00 |
286.64 |
|
Dismentling F/W/Mar tile |
10.760 |
sft |
10.00 |
107.60 |
|
Neat Cement Finishing |
10.760 |
sft |
1.00 |
10.76 |
|
RCC Casting. |
13.660 |
cft |
8.00 |
109.28 |
|
|
Sub-Total(L0) |
564.47
|
564.47
|
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Earth Work in Excavation |
55.440 |
cft |
1.80 |
99.79 |
|
Filling |
28.300 |
cft |
1.00 |
28.30 |
|
Brck flat soling |
6.880 |
sft |
0.60 |
4.13 |
|
Patent stone with NCF |
2.690 |
sft |
3.00 |
8.07 |
|
|
Sub-Total(L1) |
140.29
|
140.29
|
L4.Labour-Sanitary |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Manhole Cover fixing |
1.000 |
no. |
300.00 |
300.00 |
|
|
Sub-Total(L4) |
300.00
|
300.00
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Forms |
35.830 |
sft |
5.00 |
179.15 |
|
|
Sub-Total(M1) |
179.15
|
179.15
|
|
|
|
Total(1) |
|
5754.48 |
|
Add over head on Total(1)
|
3.0 % |
172.63 |
|
|
|
Total(2) |
|
5927.12 |
|
Add Profit on Total(2) |
8.0 % |
474.17
|
|
|
|
Total(3) |
|
6401.29 |
|
Add VAT on Unit Price |
4.5 % |
301.63 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
6702.92
|
|
|
|
Say |
|
Item: 11B (A22B) Ins. pit B type 750x750-in-in |
|
Basis:1
no. |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Brick |
32.000 |
no. |
3.80 |
121.60 |
|
Sand - Local - Mymensingh |
3.780 |
cft |
13.00 |
49.14 |
|
Polythene |
0.180 |
kg |
77.00 |
13.86 |
|
Cement |
4.740 |
bag |
343.00 |
1625.82 |
|
Sand - Sylhet |
6.000 |
cft |
24.00 |
144.00 |
|
Stone-chips |
17.900 |
cft |
80.00 |
1432.00 |
|
Re-bar - G40 |
48.300 |
kg |
38.50 |
1859.55 |
|
GI Wire |
0.330 |
kg |
90.00 |
29.70 |
|
|
Sub-Total(A1) |
5275.67
|
5275.67
|
B1.Plumbing/Sanitr Pipe |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
CI Cover 300 mm dia |
1.000 |
no. |
750.00 |
750.00 |
|
|
Sub-Total(B1) |
750.00
|
750.00
|
C1.Steel Structures |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Galvanized Angle 38x38 |
2.580 |
rft |
125.00 |
322.50 |
|
MS Grating 200x75 |
1.000 |
no. |
100.00 |
100.00 |
|
|
Sub-Total(C1) |
422.50
|
422.50
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mixer m/c and vibrator |
20.490 |
cft |
2.00 |
40.98 |
|
|
Sub-Total(E1) |
40.98
|
40.98
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Re-bar Work |
46.000 |
kg |
1.65 |
75.90 |
|
Formwork upto 10ft from P |
53.740 |
sft |
8.00 |
429.92 |
|
Dismentling F/W/Mar tile |
16.140 |
sft |
10.00 |
161.40 |
|
Neat Cement Finishing |
16.140 |
sft |
1.00 |
16.14 |
|
RCC Casting. |
20.490 |
cft |
8.00 |
163.92 |
|
|
Sub-Total(L0) |
847.28
|
847.28
|
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Earth Work in Excavation |
83.160 |
cft |
1.80 |
149.69 |
|
Filling |
42.450 |
cft |
1.00 |
42.45 |
|
Brck flat soling |
11.860 |
sft |
0.60 |
7.12 |
|
Patent stone with NCF |
4.035 |
sft |
3.00 |
12.11 |
|
|
Sub-Total(L1) |
211.36
|
211.36
|
L4.Labour-Sanitary |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Manhole Cover fixing |
1.000 |
no. |
300.00 |
300.00 |
|
|
Sub-Total(L4) |
300.00
|
300.00
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Forms |
53.740 |
sft |
5.00 |
268.70 |
|
|
Sub-Total(M1) |
268.70
|
268.70
|
|
|
|
Total(1) |
|
8116.49 |
|
Add over head on Total(1)
|
3.0 % |
243.49 |
|
|
|
Total(2) |
|
8359.98 |
|
Add Profit on Total(2) |
8.0 % |
668.80
|
|
|
|
Total(3) |
|
9028.78 |
|
Add VAT on Unit Price |
4.5 % |
425.44 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
9454.22
|
|
|
|
Say |
|
Item: 12 (B01B1) uPVC Pipe pipe fitting -100mm |
|
Basis:1
rft |
L4.Labour-Sanitary |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
uPVC Pipe fitting-100 mm |
1.000 |
rft |
15.00 |
15.00 |
|
|
Sub-Total(L4) |
15.00
|
268.70
|
|
|
|
Total(1) |
|
268.70 |
|
Add over head on Total(1)
|
3.0 % |
8.06 |
|
|
|
Total(2) |
|
276.76 |
|
Add Profit on Total(2) |
8.0 % |
22.14
|
|
|
|
Total(3) |
|
298.90 |
|
Add VAT on Unit Price |
4.5 % |
14.08 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
312.99
|
|
|
|
Say |
|
Item: 13 (B14A) Re-arrangement of Sewer Pipe-150 |
|
Basis:56
rft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Brick |
24.000 |
no. |
3.80 |
91.20 |
|
|
Sub-Total(A1) |
91.20
|
268.70
|
B1.Plumbing/Sanitr Pipe |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
uPVC Pipe 150 dia |
60.000 |
rft |
115.00 |
6900.00 |
|
uPVC Bend 150mm dia |
2.000 |
no. |
560.00 |
1120.00 |
|
Solution |
1.000 |
Tube |
185.00 |
185.00 |
|
|
Sub-Total(B1) |
8205.00
|
268.70
|
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Earth Work in Excavation |
360.000 |
cft |
1.80 |
648.00 |
|
|
Sub-Total(L1) |
648.00
|
268.70
|
|
|
|
Total(1) |
|
806.10 |
|
Add over head on Total(1)
|
3.0 % |
24.18 |
|
|
|
Total(2) |
|
830.28 |
|
Add Profit on Total(2) |
8.0 % |
66.42
|
|
|
|
Total(3) |
|
896.71 |
|
Add VAT on Unit Price |
4.5 % |
42.25 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
938.96
|
|
|
|
Say |
|
Item: 14 (A12H) 12mm Plaster (1:6) |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
11.250 |
cft |
13.00 |
146.25 |
|
Cement |
1.000 |
bag |
343.00 |
343.00 |
|
|
Sub-Total(A1) |
489.25
|
52.66
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Dismentling F/W/Mar tile |
100.000 |
sft |
10.00 |
1000.00 |
|
|
Sub-Total(L0) |
1000.00
|
107.64
|
|
|
|
Total(1) |
|
160.30 |
|
Add over head on Total(1)
|
3.0 % |
4.81 |
|
|
|
Total(2) |
|
165.11 |
|
Add Profit on Total(2) |
8.0 % |
13.21
|
|
|
|
Total(3) |
|
178.32 |
|
Add VAT on Unit Price |
4.5 % |
8.40 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
186.72
|
|
|
|
Say |
|
Item: 15 (A12E) 8mm thick plaster(1:4) |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
5.000 |
cft |
13.00 |
65.00 |
|
Cement |
1.000 |
bag |
343.00 |
343.00 |
|
|
Sub-Total(A1) |
408.00
|
43.92
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
InPlaster 44.5ft |
100.000 |
sft |
4.00 |
400.00 |
|
|
Sub-Total(L0) |
400.00
|
43.06
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Scaffolding |
0.600 |
set |
100.00 |
60.00 |
|
|
Sub-Total(M1) |
60.00
|
6.46
|
|
|
|
Total(1) |
|
93.43 |
|
Add over head on Total(1)
|
3.0 % |
2.80 |
|
|
|
Total(2) |
|
96.23 |
|
Add Profit on Total(2) |
8.0 % |
7.70
|
|
|
|
Total(3) |
|
103.93 |
|
Add VAT on Unit Price |
4.5 % |
4.90 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
108.83
|
|
|
|
Say |
|
Item: 16 (A03L) Hardonite Floor Finsh(Exc Labour) |
|
Basis:100
sft |
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Ordinary Labour Supply |
2.000 |
nos. |
100.00 |
200.00 |
|
Head Mason Supply |
1.000 |
nos. |
200.00 |
200.00 |
|
|
Sub-Total(L0) |
400.00
|
43.06
|
|
|
|
Total(1) |
|
43.06 |
|
Add over head on Total(1)
|
3.0 % |
1.29 |
|
|
|
Total(2) |
|
44.35 |
|
Add Profit on Total(2) |
8.0 % |
3.55
|
|
|
|
Total(3) |
|
47.90 |
|
Add VAT on Unit Price |
4.5 % |
2.26 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
50.15
|
|
|
|
Say |
|