Project QC Lab Roof Admin Bldg. |
Item: 01 (A18H1) Dismantling of Lime Terracing |
|
Basis:1
sft |
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Ordinary Labour Supply |
0.160 |
nos. |
100.00 |
16.00 |
|
|
Sub-Total(L0) |
16.00
|
172.22
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Cheisel - Hammer |
0.100 |
no |
55.00 |
5.50 |
|
|
Sub-Total(M1) |
5.50
|
59.20
|
|
|
|
Total(1) |
|
231.43 |
|
Add over head on Total(1)
|
5.0 % |
11.57 |
|
|
|
Total(2) |
|
243.00 |
|
Add Profit on Total(2) |
8.0 % |
19.44
|
|
|
|
Total(3) |
|
262.44 |
|
Add VAT on Unit Price |
4.5 % |
12.37 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
274.80
|
|
|
|
Say |
|
Item: 02 (A18H2) Dismantling of Ext. clmn head |
|
Basis:1
no. |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Brick |
34.000 |
no. |
3.80 |
129.20 |
|
Sand - Local - Mymensingh |
3.750 |
cft |
13.00 |
48.75 |
|
Cement |
0.500 |
bag |
343.00 |
171.50 |
|
|
Sub-Total(A1) |
349.45
|
349.45
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Ordinary Labour Supply |
2.300 |
nos. |
100.00 |
230.00 |
|
Dismentling F/W/Mar tile |
19.380 |
sft |
10.00 |
193.80 |
|
125mm thick Brick Work |
6.460 |
sft |
6.00 |
38.76 |
|
|
Sub-Total(L0) |
462.56
|
462.56
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Scaffolding |
1.000 |
set |
100.00 |
100.00 |
|
Diamond Cuting Disc- 175 |
0.008 |
no |
2200.00 |
17.60 |
|
Cheisel - Hammer |
2.000 |
no |
55.00 |
110.00 |
|
|
Sub-Total(M1) |
227.60
|
227.60
|
|
|
|
Total(1) |
|
1039.61 |
|
Add over head on Total(1)
|
5.0 % |
51.98 |
|
|
|
Total(2) |
|
1091.59 |
|
Add Profit on Total(2) |
8.0 % |
87.33
|
|
|
|
Total(3) |
|
1178.92 |
|
Add VAT on Unit Price |
4.5 % |
55.55 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
1234.47
|
|
|
|
Say |
|
Item: 03 (A10A) Re-bar Grade 60 |
|
Basis:1000
kg. |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
GI Wire |
10.000 |
kg |
90.00 |
900.00 |
|
Re-bar G60 |
1050.000 |
kg |
40.20 |
42210.00 |
|
|
Sub-Total(A1) |
43110.00
|
227.60
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Re-bar Work |
1000.000 |
kg |
1.65 |
1650.00 |
|
Local carrying Rod |
0.000 |
kg |
0.25 |
0.00 |
|
|
Sub-Total(L0) |
1650.00
|
227.60
|
|
|
|
Total(1) |
|
455.20 |
|
Add over head on Total(1)
|
5.0 % |
22.76 |
|
|
|
Total(2) |
|
477.96 |
|
Add Profit on Total(2) |
8.0 % |
38.24
|
|
|
|
Total(3) |
|
516.20 |
|
Add VAT on Unit Price |
4.5 % |
24.32 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
540.52
|
|
|
|
Say |
|
Item: 04A (A10E1) Rod lapping A-Type Corner clmn |
|
Basis:1
no. |
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Welding M/c |
30.000 |
kg |
0.50 |
15.00 |
|
|
Sub-Total(E1) |
15.00
|
15.00
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Ordinary Labour Supply |
1.000 |
nos. |
100.00 |
100.00 |
|
Carpenter Helper |
0.375 |
nos. |
150.00 |
56.25 |
|
|
Sub-Total(L0) |
156.25
|
156.25
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Welding Electrode VM 8-no |
1.000 |
pack |
520.00 |
520.00 |
|
|
Sub-Total(M1) |
520.00
|
520.00
|
|
|
|
Total(1) |
|
691.25 |
|
Add over head on Total(1)
|
5.0 % |
34.56 |
|
|
|
Total(2) |
|
725.81 |
|
Add Profit on Total(2) |
8.0 % |
58.07
|
|
|
|
Total(3) |
|
783.88 |
|
Add VAT on Unit Price |
4.5 % |
36.94 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
820.81
|
|
|
|
Say |
|
Item: 04B (A10E2) Rod lapping B-Type Corner clmn |
|
Basis:1
no. |
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Welding M/c |
30.000 |
kg |
0.50 |
15.00 |
|
|
Sub-Total(E1) |
15.00
|
15.00
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Ordinary Labour Supply |
1.000 |
nos. |
100.00 |
100.00 |
|
Carpenter Helper |
0.500 |
nos. |
150.00 |
75.00 |
|
|
Sub-Total(L0) |
175.00
|
175.00
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Welding Electrode VM 8-no |
1.000 |
pack |
520.00 |
520.00 |
|
|
Sub-Total(M1) |
520.00
|
520.00
|
|
|
|
Total(1) |
|
710.00 |
|
Add over head on Total(1)
|
5.0 % |
35.50 |
|
|
|
Total(2) |
|
745.50 |
|
Add Profit on Total(2) |
8.0 % |
59.64
|
|
|
|
Total(3) |
|
805.14 |
|
Add VAT on Unit Price |
4.5 % |
37.94 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
843.08
|
|
|
|
Say |
|
Item: 05A (A08C) RCC (1:1.5:3) in Column |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Cement |
22.000 |
bag |
343.00 |
7546.00 |
|
Sand - Sylhet |
46.000 |
cft |
24.00 |
1104.00 |
|
Stone-chips |
91.000 |
cft |
80.00 |
7280.00 |
|
|
Sub-Total(A1) |
15930.00
|
5625.68
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mini Dumper |
100.000 |
cft |
2.00 |
200.00 |
|
M/C-Vibrator,S-structure |
100.000 |
cft |
5.00 |
500.00 |
|
|
Sub-Total(E1) |
700.00
|
247.21
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Ordinary Labour Supply |
1.000 |
nos. |
100.00 |
100.00 |
|
RCC Casting-Superstructur |
100.000 |
sft |
10.00 |
1000.00 |
|
FormWork:24-33ft from PL |
305.000 |
sft |
10.00 |
3050.00 |
|
|
Sub-Total(L0) |
4150.00
|
1465.57
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Forms |
305.000 |
sft |
5.00 |
1525.00 |
|
Hessain cloth |
323.000 |
sft |
1.00 |
323.00 |
|
|
Sub-Total(M1) |
1848.00
|
652.62
|
|
|
|
Total(1) |
|
7991.08 |
|
Add over head on Total(1)
|
5.0 % |
399.55 |
|
|
|
Total(2) |
|
8390.63 |
|
Add Profit on Total(2) |
8.0 % |
671.25
|
|
|
|
Total(3) |
|
9061.88 |
|
Add VAT on Unit Price |
4.5 % |
427.00 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
9488.88
|
|
|
|
Say |
|
Item: 05B (A09N1) Roof Slab (1:1.5:3) |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Cement |
22.000 |
bag |
343.00 |
7546.00 |
|
Sand - Sylhet |
46.000 |
cft |
24.00 |
1104.00 |
|
Stone-chips |
91.000 |
cft |
80.00 |
7280.00 |
|
Sika plastcrete plus |
2.200 |
kg |
0.00 |
0.00 |
|
|
Sub-Total(A1) |
15930.00
|
5625.68
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mixer m/c and vibrator |
100.000 |
cft |
2.00 |
200.00 |
|
Mini Dumper |
100.000 |
cft |
2.00 |
200.00 |
|
|
Sub-Total(E1) |
400.00
|
141.26
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Ordinary Labour Supply |
1.000 |
nos. |
100.00 |
100.00 |
|
Rcc S-Casting slop |
100.000 |
cft |
10.00 |
1000.00 |
|
Form work slop 24-33ft |
242.000 |
sft |
10.00 |
2420.00 |
|
|
Sub-Total(L0) |
3520.00
|
1243.09
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Forms |
242.000 |
sft |
5.00 |
1210.00 |
|
Steel Scaffolding |
4.000 |
set |
100.00 |
400.00 |
|
B-plate with pipe |
20.000 |
no |
16.00 |
320.00 |
|
Steel beam,S-structure |
12.000 |
no |
40.00 |
480.00 |
|
Hessain cloth |
480.000 |
sft |
1.00 |
480.00 |
|
|
Sub-Total(M1) |
2890.00
|
1020.60
|
|
|
|
Total(1) |
|
8030.63 |
|
Add over head on Total(1)
|
5.0 % |
401.53 |
|
|
|
Total(2) |
|
8432.16 |
|
Add Profit on Total(2) |
8.0 % |
674.57
|
|
|
|
Total(3) |
|
9106.74 |
|
Add VAT on Unit Price |
4.5 % |
429.11 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
9535.85
|
|
|
|
Say |
|
Item: 05B1 (D05) Extra for Sloping Roof Slab |
|
Basis:1
cft |
|
|
|
Total(1) |
|
0.00 |
|
Add over head on Total(1)
|
5.0 % |
401.53 |
|
|
|
Total(2) |
|
8432.16 |
|
Add Profit on Total(2) |
8.0 % |
674.57
|
|
|
|
Total(3) |
|
9106.74 |
|
Add VAT on Unit Price |
4.5 % |
429.11 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
9535.85
|
|
|
|
Say |
|
Item: 05C (A08Y) Beam, Lintel (1:1.5:3) |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Cement |
22.000 |
bag |
343.00 |
7546.00 |
|
Sand - Sylhet |
46.000 |
cft |
24.00 |
1104.00 |
|
Stone-chips |
91.000 |
cft |
80.00 |
7280.00 |
|
|
Sub-Total(A1) |
15930.00
|
5625.68
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mixer m/c and vibrator |
100.000 |
cft |
2.00 |
200.00 |
|
Mini Dumper |
100.000 |
cft |
2.00 |
200.00 |
|
|
Sub-Total(E1) |
400.00
|
141.26
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Ordinary Labour Supply |
1.000 |
nos. |
100.00 |
100.00 |
|
RCC Casting-Superstructur |
100.000 |
sft |
10.00 |
1000.00 |
|
FormWork:24-33ft from PL |
357.000 |
sft |
10.00 |
3570.00 |
|
|
Sub-Total(L0) |
4670.00
|
1649.21
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Forms |
357.000 |
sft |
5.00 |
1785.00 |
|
Steel pipe with B-plate |
15.000 |
no |
11.00 |
165.00 |
|
Wood shutter-3time |
2.000 |
cft |
350.00 |
700.00 |
|
Steel beam,S-structure |
8.000 |
no |
40.00 |
320.00 |
|
|
Sub-Total(M1) |
2970.00
|
1048.86
|
|
|
|
Total(1) |
|
8465.01 |
|
Add over head on Total(1)
|
5.0 % |
423.25 |
|
|
|
Total(2) |
|
8888.26 |
|
Add Profit on Total(2) |
8.0 % |
711.06
|
|
|
|
Total(3) |
|
9599.32 |
|
Add VAT on Unit Price |
4.5 % |
452.32 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
10051.64
|
|
|
|
Say |
|
Item: 05D (A08Z1) Parapet and Drop wall (1:1.5:3) |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
15.000 |
cft |
13.00 |
195.00 |
|
Cement |
22.000 |
bag |
343.00 |
7546.00 |
|
Sand - Sylhet |
30.000 |
cft |
24.00 |
720.00 |
|
Stone-chips |
91.000 |
cft |
80.00 |
7280.00 |
|
|
Sub-Total(A1) |
15741.00
|
5558.93
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mixer m/c and vibrator |
100.000 |
cft |
2.00 |
200.00 |
|
Mini Dumper |
100.000 |
cft |
2.00 |
200.00 |
|
|
Sub-Total(E1) |
400.00
|
141.26
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Ordinary Labour Supply |
1.000 |
nos. |
100.00 |
100.00 |
|
RCC Casting-Superstructur |
100.000 |
sft |
10.00 |
1000.00 |
|
FormWork:24-33ft from PL |
564.000 |
sft |
10.00 |
5640.00 |
|
|
Sub-Total(L0) |
6740.00
|
2380.23
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Forms |
564.000 |
sft |
5.00 |
2820.00 |
|
Steel Scaffolding |
8.000 |
set |
100.00 |
800.00 |
|
|
Sub-Total(M1) |
3620.00
|
1278.40
|
|
|
|
Total(1) |
|
9358.83 |
|
Add over head on Total(1)
|
5.0 % |
467.94 |
|
|
|
Total(2) |
|
9826.77 |
|
Add Profit on Total(2) |
8.0 % |
786.14
|
|
|
|
Total(3) |
|
10612.91 |
|
Add VAT on Unit Price |
4.5 % |
500.08 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
11113.00
|
|
|
|
Say |
|
Item: 06 (A09N2) Supply of Plstocrete Plus |
|
Basis:1
no. |
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Plastocerte Plus |
1.000 |
kg |
160.00 |
160.00 |
|
|
Sub-Total(M1) |
160.00
|
160.00
|
|
|
|
Total(1) |
|
160.00 |
|
Add over head on Total(1)
|
5.0 % |
8.00 |
|
|
|
Total(2) |
|
168.00 |
|
Add Profit on Total(2) |
8.0 % |
13.44
|
|
|
|
Total(3) |
|
181.44 |
|
Add VAT on Unit Price |
4.5 % |
8.55 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
189.99
|
|
|
|
Say |
|
Item: 07 (D04A) Addl.Shutter-QC Lab Roof-Admin.Bl |
|
Basis:1
no. |
|
|
|
Total(1) |
|
0.00 |
|
Add over head on Total(1)
|
5.0 % |
8.00 |
|
|
|
Total(2) |
|
168.00 |
|
Add Profit on Total(2) |
8.0 % |
13.44
|
|
|
|
Total(3) |
|
181.44 |
|
Add VAT on Unit Price |
4.5 % |
8.55 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
189.99
|
|
|
|
Say |
|