Return Main Menu

Project Renovation I-pit-SepticTank-Nitrogen Pln
Item: 01 (A01G) Site cln-Minor E/Cutting
Basis:1 no.
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Earth Work in Excavation
1652.740
cft
1.80
2974.93
Site cleaning
3358.360
sft
2.00
6716.72
Sub-Total(L1)
9691.65
9691.65
Total(1)
9691.65
Add over head on Total(1)
2.5 %
242.29
Total(2)
9933.94
Add Profit on Total(2)
8.0 %
794.72
Total(3)
10728.66
Add VAT on Unit Price
4.5 %
527.64
Add Income Tax on Unit Price
4.0 %
469.01
Unit Price
11725.31
Say
11725
per L.S
Item: 02 (A18I) Dismantling CC, BFS, HBB
Basis:100 sft
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
1.500
nos.
100.00
150.00
Sub-Total(L0)
150.00
16.15
Total(1)
16.15
Add over head on Total(1)
2.5 %
0.40
Total(2)
16.55
Add Profit on Total(2)
8.0 %
1.32
Total(3)
17.87
Add VAT on Unit Price
4.5 %
0.88
Add Income Tax on Unit Price
4.0 %
0.78
Unit Price
19.53
Say
20
per M2
Item: 03 (A18M) Dist. of Ext. brick structure
Basis:1 no.
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ext. Structure remove
1.000
L.s
1750.00
1750.00
Sub-Total(L1)
1750.00
1750.00
Total(1)
1750.00
Add over head on Total(1)
2.5 %
43.75
Total(2)
1793.75
Add Profit on Total(2)
8.0 %
143.50
Total(3)
1937.25
Add VAT on Unit Price
4.5 %
95.27
Add Income Tax on Unit Price
4.0 %
84.69
Unit Price
2117.21
Say
2117
per L.S
Item: 04 (A02I) Renovation of Imsp.Pits
Basis:1 no.
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
424.000
no.
3.80
1611.20
Sand - Local - Mymensingh
37.500
cft
13.00
487.50
Cement
5.000
bag
343.00
1715.00
Stone-chips
7.500
cft
80.00
600.00
Re-bar - G40
12.500
kg
38.50
481.25
Sub-Total(A1)
4894.95
4894.95
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Earth Work in Excavation
35.315
cft
1.80
63.57
Plaster Work
30.140
sft
3.00
90.42
NCF
30.140
sft
1.00
30.14
RCC Work
3.540
cft
6.00
21.24
Form work
10.764
sft
8.00
86.11
250mm Brick work
24.720
cft
4.00
98.88
Sub-Total(L1)
390.36
390.36
Total(1)
5285.31
Add over head on Total(1)
2.5 %
132.13
Total(2)
5417.44
Add Profit on Total(2)
8.0 %
433.40
Total(3)
5850.84
Add VAT on Unit Price
4.5 %
287.75
Add Income Tax on Unit Price
4.0 %
255.77
Unit Price
6394.36
Say
6394
per NO
Item: 05 (A02J) Insp. pits with b-wall 250mm
Basis:1 no.
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
792.000
no.
3.80
3009.60
Sand - Local - Mymensingh
15.000
cft
13.00
195.00
Polythene
0.250
kg
77.00
19.25
Cement
8.000
bag
343.00
2744.00
Sand - Sylhet
22.500
cft
24.00
540.00
Stone-chips
15.000
cft
80.00
1200.00
Re-bar - G40
31.000
kg
38.50
1193.50
Sub-Total(A1)
8901.35
8901.35
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
CI Cover -450MM DIA
1.000
no.
2500.00
2500.00
Sub-Total(B1)
2500.00
2500.00
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Earth Work in Excavation
268.390
cft
1.80
483.10
Filling
171.760
cft
1.00
171.76
Brck flat soling
15.500
sft
0.60
9.30
Plaster Work
87.830
sft
3.00
263.49
Form work
10.764
sft
8.00
86.11
250mm Brick work
60.030
cft
4.00
240.12
Sub-Total(L1)
1253.88
1253.88
Total(1)
12655.23
Add over head on Total(1)
2.5 %
316.38
Total(2)
12971.61
Add Profit on Total(2)
8.0 %
1037.73
Total(3)
14009.34
Add VAT on Unit Price
4.5 %
688.98
Add Income Tax on Unit Price
4.0 %
612.43
Unit Price
15310.76
Say
15311
per NO
Item: 06 (A02K) Renovation of Ext.S-tank
Basis:1 no.
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
1500.000
no.
3.80
5700.00
Sand - Local - Mymensingh
100.000
cft
13.00
1300.00
Cement
23.000
bag
343.00
7889.00
Sand - Sylhet
17.000
cft
24.00
408.00
Stone-chips
52.000
cft
80.00
4160.00
Re-bar - G40
130.000
kg
38.50
5005.00
Wood - Mango
3.000
cft
250.00
750.00
Sub-Total(A1)
25212.00
25212.00
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Re-bar Work
130.000
kg
1.65
214.50
Sub-Total(L0)
214.50
214.50
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Earth Work in Excavation
247.200
cft
1.80
444.96
Plaster Work
333.110
sft
3.00
999.33
NCF
333.110
sft
1.00
333.11
RCC Work
49.440
cft
6.00
296.64
Form work
110.000
sft
8.00
880.00
250mm Brick work
137.720
cft
4.00
550.88
Sub-Total(L1)
3504.92
3504.92
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
CI grating fitting
3.000
no
300.00
900.00
Sub-Total(M1)
900.00
900.00
Total(1)
29831.42
Add over head on Total(1)
2.5 %
745.79
Total(2)
30577.21
Add Profit on Total(2)
8.0 %
2446.18
Total(3)
33023.38
Add VAT on Unit Price
4.5 %
1624.10
Add Income Tax on Unit Price
4.0 %
1443.65
Unit Price
36091.13
Say
36091
per LS
Item: 07 (A02L) Raising up to Pump pits
Basis:1 no.
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
425.000
no.
3.80
1615.00
Sand - Local - Mymensingh
39.500
cft
13.00
513.50
Cement
5.500
bag
343.00
1886.50
Stone-chips
8.500
cft
80.00
680.00
Re-bar - G40
15.000
kg
38.50
577.50
Sub-Total(A1)
5272.50
5272.50
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Earth Work in Excavation
63.570
cft
1.80
114.43
Plaster Work
30.140
sft
3.00
90.42
NCF
30.140
sft
1.00
30.14
RCC Work
3.540
cft
6.00
21.24
Form work
10.764
sft
8.00
86.11
250mm Brick work
24.720
cft
4.00
98.88
Sub-Total(L1)
441.22
441.22
Total(1)
5713.72
Add over head on Total(1)
2.5 %
142.84
Total(2)
5856.56
Add Profit on Total(2)
8.0 %
468.52
Total(3)
6325.09
Add VAT on Unit Price
4.5 %
311.07
Add Income Tax on Unit Price
4.0 %
276.51
Unit Price
6912.66
Say
6913
per LS
Item: 08 (B14) 225mm Re-arrange of R/W line
Basis:1 rft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
9.000
no.
3.80
34.20
Cement
0.200
bag
343.00
68.60
Sub-Total(A1)
102.80
441.22
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
RCC Pipe 9" dia
1.000
rft
108.00
108.00
Sub-Total(B1)
108.00
441.22
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Earth Work in Excavation
15.890
cft
1.80
28.60
Filling
15.890
cft
1.00
15.89
225mm dia RCC pipe
1.000
rft
25.00
25.00
Sub-Total(L1)
69.49
441.22
Total(1)
1323.65
Add over head on Total(1)
2.5 %
33.09
Total(2)
1356.75
Add Profit on Total(2)
8.0 %
108.54
Total(3)
1465.28
Add VAT on Unit Price
4.5 %
72.06
Add Income Tax on Unit Price
4.0 %
64.06
Unit Price
1601.40
Say
1601
per RM
Item: 09 (A23B) Ext. under ground W/Tank
Basis:1 no.
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
30.000
cft
13.00
390.00
Cement
24.000
bag
343.00
8232.00
Sand - Sylhet
30.000
cft
24.00
720.00
Stone-chips
120.000
cft
80.00
9600.00
Re-bar - G40
424.300
kg
38.50
16335.55
Sub-Total(A1)
35277.55
35277.55
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Re-bar Work
404.000
kg
1.65
666.60
Sub-Total(L0)
666.60
666.60
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Earth Work in Excavation
296.646
cft
1.80
533.96
RCC Work
120.950
cft
6.00
725.70
Form work
460.690
sft
8.00
3685.52
RCC Dismantling
90.400
sft
15.00
1356.00
Sub-Total(L1)
6301.18
6301.18
Total(1)
42245.33
Add over head on Total(1)
2.5 %
1056.13
Total(2)
43301.47
Add Profit on Total(2)
8.0 %
3464.12
Total(3)
46765.58
Add VAT on Unit Price
4.5 %
2299.95
Add Income Tax on Unit Price
4.0 %
2044.40
Unit Price
51109.93
Say
51110
per NO
Item: 10 (A09O) P-Protection with 50 p-cast slab
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
2.443
cft
13.00
31.76
Cement
3.740
bag
343.00
1282.82
Sand - Sylhet
4.886
cft
24.00
117.26
Stone-chips
14.620
cft
80.00
1169.60
Wire Mesh
105.000
sft
7.00
735.00
Sub-Total(A1)
3336.44
359.13
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Pre-cast block fitting
45.860
no
25.00
1146.50
Sub-Total(L1)
1146.50
123.41
Total(1)
482.54
Add over head on Total(1)
2.5 %
12.06
Total(2)
494.61
Add Profit on Total(2)
8.0 %
39.57
Total(3)
534.18
Add VAT on Unit Price
4.5 %
26.27
Add Income Tax on Unit Price
4.0 %
23.35
Unit Price
583.80
Say
584
per M2
Item: 11 (A06H) U-ground 125(1:5) b/wall
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
500.000
no.
3.80
1900.00
Sand - Local - Mymensingh
17.000
cft
13.00
221.00
Cement
2.600
bag
343.00
891.80
Sub-Total(A1)
3012.80
324.30
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick Work-125mm
100.000
sft
3.50
350.00
Sub-Total(L1)
350.00
37.67
Total(1)
361.97
Add over head on Total(1)
2.5 %
9.05
Total(2)
371.02
Add Profit on Total(2)
8.0 %
29.68
Total(3)
400.70
Add VAT on Unit Price
4.5 %
19.71
Add Income Tax on Unit Price
4.0 %
17.52
Unit Price
437.93
Say
438
per M2
Item: 12 (A03M) 75mm C.C (1:2:4) at F-base
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
3.750
cft
13.00
48.75
Polythene
1.430
kg
77.00
110.11
Cement
5.000
bag
343.00
1715.00
Sand - Sylhet
7.500
cft
24.00
180.00
Stone-chips
22.500
cft
80.00
1800.00
Sub-Total(A1)
3853.86
414.83
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
25.000
cft
2.00
50.00
Sub-Total(E1)
50.00
5.38
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
CC Work
25.000
cft
5.00
125.00
Sub-Total(L1)
125.00
13.46
Total(1)
433.67
Add over head on Total(1)
2.5 %
10.84
Total(2)
444.51
Add Profit on Total(2)
8.0 %
35.56
Total(3)
480.07
Add VAT on Unit Price
4.5 %
23.61
Add Income Tax on Unit Price
4.0 %
20.99
Unit Price
524.67
Say
525
per M2
Item: 13 (A12A) Plaster(1:5) 20mm thick
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
8.250
cft
13.00
107.25
Cement
1.100
bag
343.00
377.30
Sub-Total(A1)
484.55
52.16
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
OutPlaster 30.5ft
100.000
sft
4.50
450.00
Sub-Total(L0)
450.00
48.44
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Scaffolding
1.500
set
100.00
150.00
Sub-Total(M1)
150.00
16.15
Total(1)
116.74
Add over head on Total(1)
2.5 %
2.92
Total(2)
119.66
Add Profit on Total(2)
8.0 %
9.57
Total(3)
129.23
Add VAT on Unit Price
4.5 %
6.36
Add Income Tax on Unit Price
4.0 %
5.65
Unit Price
141.24
Say
141
per M2
Item: 14A (B01B) uPVC Pipe 100 dia
Basis:300 rft
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
uPVC Pipe 100mm dia
315.000
rft
58.00
18270.00
Solvent cement -500 ml
8.000
pot
490.00
3920.00
uPVC Plainn Tee-100mm Dia
16.000
no.
278.00
4448.00
uPVC Long Trap - 100mm Di
6.000
no.
370.00
2220.00
uPVC Door Bend - 100mm di
24.000
no.
290.00
6960.00
uPVC Bend 45D -100mm dia
6.000
no.
175.00
1050.00
Sub-Total(B1)
36868.00
16.15
L4.Labour-Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
uPVC Pipe fitting-100 mm
300.000
rft
15.00
4500.00
Sub-Total(L4)
4500.00
16.15
Total(1)
32.29
Add over head on Total(1)
2.5 %
0.81
Total(2)
33.10
Add Profit on Total(2)
8.0 %
2.65
Total(3)
35.75
Add VAT on Unit Price
4.5 %
1.76
Add Income Tax on Unit Price
4.0 %
1.56
Unit Price
39.07
Say
39
per RM