Return Main Menu

Project BEL Store At Technology Park
Item: 01 (A01) Earth work in Excavation
Basis:1000 cft
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Earth Work in Excavation
1000.000
cft
1.80
1800.00
Sub-Total(L1)
1800.00
63.57
Total(1)
63.57
Add over head on Total(1)
0.0 %
0.00
Total(2)
63.57
Add Profit on Total(2)
0.0 %
0.00
Total(3)
63.57
Add VAT on Unit Price
4.5 %
3.13
Add Income Tax on Unit Price
4.0 %
2.78
Unit Price
69.47
Say
69
per M3
Item: 02 (A05D) Back filling-(Excluding Sand Supp
Basis:100 cft
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mini Roller Compaction
25.000
cft
1.00
25.00
Mini Dumper-Sand carrying
50.000
cft
1.00
50.00
Sub-Total(E1)
75.00
26.49
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Filling
100.000
cft
1.00
100.00
Sub-Total(L1)
100.00
35.32
Total(1)
61.80
Add over head on Total(1)
0.0 %
0.00
Total(2)
61.80
Add Profit on Total(2)
0.0 %
0.00
Total(3)
61.80
Add VAT on Unit Price
4.5 %
3.04
Add Income Tax on Unit Price
4.0 %
2.70
Unit Price
67.54
Say
68
per M3
Item: 03 (A02B) Brick Flat Soling
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Filling Sand
5.000
cft
8.50
42.50
Brick
300.000
no.
3.80
1140.00
Sub-Total(A1)
1182.50
127.28
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
0.100
nos.
100.00
10.00
Head Mason Supply
0.250
nos.
200.00
50.00
Sub-Total(L0)
60.00
6.46
Total(1)
133.74
Add over head on Total(1)
0.0 %
0.00
Total(2)
133.74
Add Profit on Total(2)
0.0 %
0.00
Total(3)
133.74
Add VAT on Unit Price
4.5 %
6.58
Add Income Tax on Unit Price
4.0 %
5.85
Unit Price
146.17
Say
146
per M2
Item: 04 (A02F) Single layer polythene
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Polythene
1.500
kg
77.00
115.50
Sub-Total(A1)
115.50
12.43
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
0.020
nos.
100.00
2.00
Sub-Total(L0)
2.00
0.22
Total(1)
12.65
Add over head on Total(1)
0.0 %
0.00
Total(2)
12.65
Add Profit on Total(2)
0.0 %
0.00
Total(3)
12.65
Add VAT on Unit Price
4.5 %
0.62
Add Income Tax on Unit Price
4.0 %
0.55
Unit Price
13.82
Say
14
per M2
Item: 05 (A03E) 75 mm thick CC with NCF
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
3.750
cft
13.00
48.75
Cement
5.000
bag
343.00
1715.00
Sand - Sylhet
7.500
cft
24.00
180.00
Brick-chips
22.500
cft
40.00
900.00
Sub-Total(A1)
2843.75
306.10
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
25.000
cft
2.00
50.00
Sub-Total(E1)
50.00
5.38
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
CC Work
25.000
cft
5.00
125.00
Sub-Total(L1)
125.00
13.46
Total(1)
324.94
Add over head on Total(1)
0.0 %
0.00
Total(2)
324.94
Add Profit on Total(2)
0.0 %
0.00
Total(3)
324.94
Add VAT on Unit Price
4.5 %
15.98
Add Income Tax on Unit Price
4.0 %
14.20
Unit Price
355.12
Say
355
per M2
Item: 06 (A06B) Brick Work 250mm in Foundation
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
1200.000
no.
3.80
4560.00
Sand - Local - Mymensingh
40.000
cft
13.00
520.00
Cement
5.000
bag
343.00
1715.00
Sub-Total(A1)
6795.00
2399.65
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
250mm Brickwork upto 7 ft
100.000
cft
4.25
425.00
Sub-Total(L0)
425.00
150.09
Total(1)
2549.74
Add over head on Total(1)
0.0 %
0.00
Total(2)
2549.74
Add Profit on Total(2)
0.0 %
0.00
Total(3)
2549.74
Add VAT on Unit Price
4.5 %
125.40
Add Income Tax on Unit Price
4.0 %
111.46
Unit Price
2786.60
Say
2787
per M3
Item: 07 (A03G) 50mm DPC (1:1.5:3)
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
7.500
cft
13.00
97.50
Cement
4.000
bag
343.00
1372.00
Stone-chips
15.000
cft
80.00
1200.00
Plastocrete super-Sika
1.000
kg
155.00
155.00
Sub-Total(A1)
2824.50
304.03
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
16.700
cft
2.00
33.40
Sub-Total(E1)
33.40
3.60
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
D.P.C.
100.000
sft
3.00
300.00
Sub-Total(L0)
300.00
32.29
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Wood shutter-3time
1.110
cft
350.00
388.50
Sub-Total(M1)
388.50
41.82
Total(1)
381.73
Add over head on Total(1)
0.0 %
0.00
Total(2)
381.73
Add Profit on Total(2)
0.0 %
0.00
Total(3)
381.73
Add VAT on Unit Price
4.5 %
18.77
Add Income Tax on Unit Price
4.0 %
16.69
Unit Price
417.20
Say
417
per M2
Item: 08 (A06A) 125mm thick brick work (1:5)
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
500.000
no.
3.80
1900.00
Sand - Local - Mymensingh
17.000
cft
13.00
221.00
Cement
2.600
bag
343.00
891.80
Sub-Total(A1)
3012.80
324.30
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
125mm thick Brick Work
100.000
sft
6.00
600.00
Sub-Total(L0)
600.00
64.58
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Scaffolding
1.000
set
100.00
100.00
Sub-Total(M1)
100.00
10.76
Total(1)
399.65
Add over head on Total(1)
0.0 %
0.00
Total(2)
399.65
Add Profit on Total(2)
0.0 %
0.00
Total(3)
399.65
Add VAT on Unit Price
4.5 %
19.65
Add Income Tax on Unit Price
4.0 %
17.47
Unit Price
436.77
Say
437
per M2
Item: 09 (A08K) RCC Lintel (1:2:4) with 1% rod
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
15.000
cft
13.00
195.00
Cement
18.000
bag
343.00
6174.00
Sand - Sylhet
30.000
cft
24.00
720.00
Stone-chips
90.000
cft
80.00
7200.00
Re-bar G60
222.730
kg
40.20
8953.75
Wood - Mango
13.000
cft
250.00
3250.00
Sub-Total(A1)
26492.75
9355.91
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
RCC Work
100.000
cft
6.00
600.00
Form work
476.000
sft
8.00
3808.00
Sub-Total(L1)
4408.00
1556.69
Total(1)
10912.60
Add over head on Total(1)
0.0 %
0.00
Total(2)
10912.60
Add Profit on Total(2)
0.0 %
0.00
Total(3)
10912.60
Add VAT on Unit Price
4.5 %
536.69
Add Income Tax on Unit Price
4.0 %
477.05
Unit Price
11926.34
Say
11926
per M3
Item: 10 (C14) CI sheet roofing (excl.angle)
Basis:100 sft
C1.Steel Structures
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
J-Hook
65.000
no
2.50
162.50
CI Sheet 0.45mm
0.700
Bun
3000.00
2100.00
Sub-Total(C1)
2262.50
243.54
S2.Alum,SS/MS,FalseCeil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
CI Sheet roofing
100.000
sft
2.75
275.00
Sub-Total(S2)
275.00
29.60
Total(1)
273.14
Add over head on Total(1)
0.0 %
0.00
Total(2)
273.14
Add Profit on Total(2)
0.0 %
0.00
Total(3)
273.14
Add VAT on Unit Price
4.5 %
13.43
Add Income Tax on Unit Price
4.0 %
11.94
Unit Price
298.51
Say
299
per M2
Item: 11 (C01) MS Angle Purlin
Basis:1000 kg.
C1.Steel Structures
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS angle
1050.000
kg
38.00
39900.00
Sub-Total(C1)
39900.00
29.60
L5.Labour-MS Work
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Making Purlin,rafter, box
1000.000
kg
6.50
6500.00
Sub-Total(L5)
6500.00
29.60
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Welding Electrode VM 8-no
2.000
pack
520.00
1040.00
Sub-Total(M1)
1040.00
29.60
Total(1)
88.80
Add over head on Total(1)
0.0 %
0.00
Total(2)
88.80
Add Profit on Total(2)
0.0 %
0.00
Total(3)
88.80
Add VAT on Unit Price
4.5 %
4.37
Add Income Tax on Unit Price
4.0 %
3.88
Unit Price
97.05
Say
97
per TON
Item: 12 (C02) MS Door - Old
Basis:18 sft
C2.MS/SS Work i/c matr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS Door - Old
17.500
sft
80.00
1400.00
Sub-Total(C2)
1400.00
861.12
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
0.500
nos.
100.00
50.00
Head Mason Supply
0.500
nos.
200.00
100.00
Sub-Total(L0)
150.00
92.26
S1.Sub-contractor-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Painting to MS surface
35.000
sft
5.00
175.00
Sub-Total(S1)
175.00
107.64
Total(1)
1061.02
Add over head on Total(1)
0.0 %
0.00
Total(2)
1061.02
Add Profit on Total(2)
0.0 %
0.00
Total(3)
1061.02
Add VAT on Unit Price
4.5 %
52.18
Add Income Tax on Unit Price
4.0 %
46.38
Unit Price
1159.59
Say
1160
per M2
Item: 13 (C03) MS Window - Old
Basis:12 sft
C2.MS/SS Work i/c matr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS Window - Old
12.000
sft
70.00
840.00
Sub-Total(C2)
840.00
753.48
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
0.500
nos.
100.00
50.00
Head Mason Supply
0.500
nos.
200.00
100.00
Sub-Total(L0)
150.00
134.55
S1.Sub-contractor-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Painting to MS surface
24.000
sft
5.00
120.00
Sub-Total(S1)
120.00
107.64
Total(1)
995.67
Add over head on Total(1)
0.0 %
0.00
Total(2)
995.67
Add Profit on Total(2)
0.0 %
0.00
Total(3)
995.67
Add VAT on Unit Price
4.5 %
48.97
Add Income Tax on Unit Price
4.0 %
43.53
Unit Price
1088.16
Say
1088
per M2