Return Main Menu

Project Temporary Project Office at O/A STrack-2
Item: 01 (A06A) 125mm thick brick work (1:5)
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
500.000
no.
3.80
1900.00
Sand - Local - Mymensingh
17.000
cft
13.00
221.00
Cement
2.600
bag
343.00
891.80
Sub-Total(A1)
3012.80
324.30
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
125mm thick Brick Work
100.000
sft
6.00
600.00
Sub-Total(L0)
600.00
64.58
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Scaffolding
1.000
set
100.00
100.00
Sub-Total(M1)
100.00
10.76
Total(1)
399.65
Add over head on Total(1)
2.5 %
9.99
Total(2)
409.64
Add Profit on Total(2)
8.0 %
32.77
Total(3)
442.41
Add VAT on Unit Price
4.5 %
21.76
Add Income Tax on Unit Price
4.0 %
19.34
Unit Price
483.51
Say
484
per M2
Item: 02 (A12A) Plaster(1:5) 20mm thick
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
8.250
cft
13.00
107.25
Cement
1.100
bag
343.00
377.30
Sub-Total(A1)
484.55
52.16
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
OutPlaster 30.5ft
100.000
sft
4.50
450.00
Sub-Total(L0)
450.00
48.44
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Scaffolding
1.500
set
100.00
150.00
Sub-Total(M1)
150.00
16.15
Total(1)
116.74
Add over head on Total(1)
2.5 %
2.92
Total(2)
119.66
Add Profit on Total(2)
8.0 %
9.57
Total(3)
129.23
Add VAT on Unit Price
4.5 %
6.36
Add Income Tax on Unit Price
4.0 %
5.65
Unit Price
141.24
Say
141
per M2
Item: 03 (A14C) Plaster board ceiling
Basis:100 sft
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Scaffolding
1.000
set
100.00
100.00
Sub-Total(M1)
100.00
10.76
S2.Alum,SS/MS,FalseCeil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Plaster Board Ceiling
100.000
sft
125.00
12500.00
Sub-Total(S2)
12500.00
1345.50
Total(1)
1356.26
Add over head on Total(1)
2.5 %
33.91
Total(2)
1390.17
Add Profit on Total(2)
8.0 %
111.21
Total(3)
1501.38
Add VAT on Unit Price
4.5 %
73.84
Add Income Tax on Unit Price
4.0 %
65.63
Unit Price
1640.86
Say
1641
per M2
Item: 04 (A14A) Laminated Gypsum Board Ceiling
Basis:100 sft
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Scaffolding
1.000
set
100.00
100.00
Sub-Total(M1)
100.00
10.76
S2.Alum,SS/MS,FalseCeil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Lamint GypsumBoardCeiling
100.000
sft
42.00
4200.00
Sub-Total(S2)
4200.00
452.09
Total(1)
462.85
Add over head on Total(1)
2.5 %
11.57
Total(2)
474.42
Add Profit on Total(2)
8.0 %
37.95
Total(3)
512.38
Add VAT on Unit Price
4.5 %
25.20
Add Income Tax on Unit Price
4.0 %
22.40
Unit Price
559.98
Say
560
per M2
Item: 05A (A11U) Al.PC) Partition Frost Glass-2400
Basis:1 sft
S2.Alum,SS/MS,FalseCeil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Al.(PC)Partition,FrstGls
1.000
sft
220.00
220.00
Sub-Total(S2)
220.00
2368.08
Total(1)
2368.08
Add over head on Total(1)
2.5 %
59.20
Total(2)
2427.28
Add Profit on Total(2)
8.0 %
194.18
Total(3)
2621.46
Add VAT on Unit Price
4.5 %
128.92
Add Income Tax on Unit Price
4.0 %
114.60
Unit Price
2864.99
Say
2865
per M2
Item: 05B (A11W) Al.PC) Partition Frost Glass-2100
Basis:1 sft
S2.Alum,SS/MS,FalseCeil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Al.(PC)Partition,FrstGls
1.000
sft
220.00
220.00
Sub-Total(S2)
220.00
2368.08
Total(1)
2368.08
Add over head on Total(1)
2.5 %
59.20
Total(2)
2427.28
Add Profit on Total(2)
8.0 %
194.18
Total(3)
2621.46
Add VAT on Unit Price
4.5 %
128.92
Add Income Tax on Unit Price
4.0 %
114.60
Unit Price
2864.99
Say
2865
per M2
Item: 05C (A11V) Al.(PC)Partition Clear Glass-2100
Basis:1 sft
S2.Alum,SS/MS,FalseCeil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Al.(PC)Partition,FrstGls
1.000
sft
220.00
220.00
Sub-Total(S2)
220.00
2368.08
Total(1)
2368.08
Add over head on Total(1)
2.5 %
59.20
Total(2)
2427.28
Add Profit on Total(2)
8.0 %
194.18
Total(3)
2621.46
Add VAT on Unit Price
4.5 %
128.92
Add Income Tax on Unit Price
4.0 %
114.60
Unit Price
2864.99
Say
2865
per M2
Item: 06 (A11X) Dry Pannel Wall
Basis:1 sft
S2.Alum,SS/MS,FalseCeil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Gypsum Board
1.050
sft
25.00
26.25
Dry Panel Wall(Ex Board)
1.000
sft
25.00
25.00
Sub-Total(S2)
51.25
551.66
Total(1)
551.66
Add over head on Total(1)
2.5 %
13.79
Total(2)
565.45
Add Profit on Total(2)
8.0 %
45.24
Total(3)
610.68
Add VAT on Unit Price
4.5 %
30.03
Add Income Tax on Unit Price
4.0 %
26.70
Unit Price
667.41
Say
667
per M2
Item: 07 (A11A) Alum(PC)-Swing Door Frosted Glass
Basis:1 sft
S2.Alum,SS/MS,FalseCeil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Al.(PC) Swing Door,FrsGls
1.000
sft
400.00
400.00
Sub-Total(S2)
400.00
4305.60
Total(1)
4305.60
Add over head on Total(1)
2.5 %
107.64
Total(2)
4413.24
Add Profit on Total(2)
8.0 %
353.06
Total(3)
4766.30
Add VAT on Unit Price
4.5 %
234.41
Add Income Tax on Unit Price
4.0 %
208.36
Unit Price
5209.07
Say
5209
per M2
Item: 08 (A11Y) Toilet cubicle Installation-Labor
Basis:1 sft
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Toilet Cubical fitting
1.000
sft
20.00
20.00
Sub-Total(L1)
20.00
215.28
Total(1)
215.28
Add over head on Total(1)
2.5 %
5.38
Total(2)
220.66
Add Profit on Total(2)
8.0 %
17.65
Total(3)
238.31
Add VAT on Unit Price
4.5 %
11.72
Add Income Tax on Unit Price
4.0 %
10.42
Unit Price
260.45
Say
260
per M2
Item: 09 (A13G) Epoxy paint to wall (New)
Basis:100 sft
A3.Material-Paint
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Epoxy Primer
2.000
Ltr
170.00
340.00
Epoxy Enamel
3.080
Ltr
387.00
1191.96
Thinner-T6/T7
1.600
Ltr
46.00
73.60
Chalk powder
1.330
kg
18.00
23.94
Mosaic stone
0.200
no
110.00
22.00
Scrap
1.000
L.s
30.00
30.00
Sub-Total(A3)
1681.50
181.00
L6.Labour Paints
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Epoxy Paint to wall
100.000
sft
10.00
1000.00
Sub-Total(L6)
1000.00
107.64
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Scaffolding
1.000
set
100.00
100.00
Sub-Total(M1)
100.00
10.76
Total(1)
299.40
Add over head on Total(1)
2.5 %
7.49
Total(2)
306.89
Add Profit on Total(2)
8.0 %
24.55
Total(3)
331.44
Add VAT on Unit Price
4.5 %
16.30
Add Income Tax on Unit Price
4.0 %
14.49
Unit Price
362.23
Say
362
per M2
Item: 10 (A13D) Epoxy paint to Ceiling
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
White-Cement
1.000
kg
16.25
16.25
Sub-Total(A1)
16.25
1.75
A3.Material-Paint
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Epoxy Primer
2.000
Ltr
170.00
340.00
Epoxy Enamel
3.080
Ltr
387.00
1191.96
Thinner-T6/T7
1.600
Ltr
46.00
73.60
Chalk powder
1.330
kg
18.00
23.94
Mosaic stone
0.200
no
110.00
22.00
Scrap
1.000
L.s
30.00
30.00
Bakram
1.000
yds
25.00
25.00
Aica
0.500
kg
120.00
60.00
Sub-Total(A3)
1766.50
190.15
L6.Labour Paints
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
EpoxyPaint-P.boardCeiling
100.000
sft
12.00
1200.00
Sub-Total(L6)
1200.00
129.17
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Scaffolding
1.000
set
100.00
100.00
Sub-Total(M1)
100.00
10.76
Total(1)
331.83
Add over head on Total(1)
2.5 %
8.30
Total(2)
340.12
Add Profit on Total(2)
8.0 %
27.21
Total(3)
367.33
Add VAT on Unit Price
4.5 %
18.07
Add Income Tax on Unit Price
4.0 %
16.06
Unit Price
401.46
Say
401
per M2
Item: 11 (A03K) Over head tank base
Basis:1 no.
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
480.000
no.
3.80
1824.00
Sand - Local - Mymensingh
41.250
cft
13.00
536.25
Cement
10.000
bag
343.00
3430.00
Sand - Sylhet
8.250
cft
24.00
198.00
Stone-chips
33.000
cft
80.00
2640.00
Re-bar G60
76.650
kg
40.20
3081.33
Sub-Total(A1)
11709.58
11709.58
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
RCC Casting-Superstructur
25.400
sft
10.00
254.00
FormWork:24-33ft from PL
99.370
sft
10.00
993.70
B/W:15.5-27ft Scaffold Ht
36.200
cft
12.00
434.40
OutPlaster 15.5-28ft
257.000
sft
5.00
1285.00
Sub-Total(L0)
2967.10
2967.10
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
LC Dismantling
22.060
sft
25.00
551.50
Sub-Total(L1)
551.50
551.50
S1.Sub-contractor-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Weather Coat paint
257.000
sft
11.00
2827.00
Sub-Total(S1)
2827.00
2827.00
Total(1)
18055.18
Add over head on Total(1)
2.5 %
451.38
Total(2)
18506.56
Add Profit on Total(2)
8.0 %
1480.52
Total(3)
19987.08
Add VAT on Unit Price
4.5 %
982.97
Add Income Tax on Unit Price
4.0 %
873.75
Unit Price
21843.81
Say
21844
per NO
Item: 12A (A11D) Alum. Door Plastic Board
Basis:1 sft
S2.Alum,SS/MS,FalseCeil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Alum.Door, Plastic Board
1.000
sft
220.00
220.00
Sub-Total(S2)
220.00
2368.08
Total(1)
2368.08
Add over head on Total(1)
2.5 %
59.20
Total(2)
2427.28
Add Profit on Total(2)
8.0 %
194.18
Total(3)
2621.46
Add VAT on Unit Price
4.5 %
128.92
Add Income Tax on Unit Price
4.0 %
114.60
Unit Price
2864.99
Say
2865
per M2
Item: 12B (B03) SS Sink-single
Basis:1 no.
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
SS Sink
1.000
no.
2000.00
2000.00
CP Bashin wast
1.000
No
95.00
95.00
Sub-Total(B1)
2095.00
2095.00
L4.Labour-Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sink fitting
1.000
no.
125.00
125.00
Sub-Total(L4)
125.00
125.00
Total(1)
2220.00
Add over head on Total(1)
2.5 %
55.50
Total(2)
2275.50
Add Profit on Total(2)
8.0 %
182.04
Total(3)
2457.54
Add VAT on Unit Price
4.5 %
120.86
Add Income Tax on Unit Price
4.0 %
107.43
Unit Price
2685.84
Say
2686
per NO.
Item: 12C (A07) Tiles Fitting excluding Tiles
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
6.250
cft
13.00
81.25
Cement
2.500
bag
343.00
857.50
White-Cement
3.500
kg
16.25
56.88
Sub-Total(A1)
995.63
107.17
L2.Labour-Tile/Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Floor/ Wall Tiles fitting
100.000
sft
20.00
2000.00
Sub-Total(L2)
2000.00
215.28
Total(1)
322.45
Add over head on Total(1)
2.5 %
8.06
Total(2)
330.51
Add Profit on Total(2)
8.0 %
26.44
Total(3)
356.95
Add VAT on Unit Price
4.5 %
17.55
Add Income Tax on Unit Price
4.0 %
15.60
Unit Price
390.11
Say
390
per M2
Item: 12D (A11E) Paintable Sealant
Basis:1 rft
A3.Material-Paint
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Acrylic Sealant
0.150
tube
180.00
27.00
Sub-Total(A3)
27.00
215.28
L6.Labour Paints
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Apllying Sealant
1.000
rft
2.00
2.00
Sub-Total(L6)
2.00
215.28
Total(1)
430.56
Add over head on Total(1)
2.5 %
10.76
Total(2)
441.32
Add Profit on Total(2)
8.0 %
35.31
Total(3)
476.63
Add VAT on Unit Price
4.5 %
23.44
Add Income Tax on Unit Price
4.0 %
20.84
Unit Price
520.91
Say
521
per RM
Item: 12E (A11F) Applying Sealant - Labour Charge
Basis:1 rft
L6.Labour Paints
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Apllying Sealant
1.000
rft
2.00
2.00
Sub-Total(L6)
2.00
215.28
Total(1)
215.28
Add over head on Total(1)
2.5 %
5.38
Total(2)
220.66
Add Profit on Total(2)
8.0 %
17.65
Total(3)
238.31
Add VAT on Unit Price
4.5 %
11.72
Add Income Tax on Unit Price
4.0 %
10.42
Unit Price
260.45
Say
260
per RM