Project New PM+RM Ware House (Superstructure) |
Item: 02 (A06C) 250mm thick B-wall (1:5) - Supers |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Brick |
1200.000 |
no. |
3.80 |
4560.00 |
|
Sand - Local - Mymensingh |
40.000 |
cft |
13.00 |
520.00 |
|
Cement |
6.000 |
bag |
343.00 |
2058.00 |
|
|
Sub-Total(A1) |
7138.00
|
2520.78
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
B/w:15.5-27ft Scffld(Part |
100.000 |
cft |
6.00 |
600.00 |
|
|
Sub-Total(L0) |
600.00
|
211.89
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Scaffolding |
1.000 |
set |
100.00 |
100.00 |
|
|
Sub-Total(M1) |
100.00
|
35.32
|
|
|
|
Total(1) |
|
2767.99 |
|
Add over head on Total(1)
|
3.0 % |
83.04 |
|
|
|
Total(2) |
|
2851.03 |
|
Add Profit on Total(2) |
8.0 % |
228.08
|
|
|
|
Total(3) |
|
3079.11 |
|
Add VAT on Unit Price |
4.5 % |
145.09 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
3224.20
|
|
|
|
Say |
|
Item: 01 (A06F) 125 B/Wall (1:4) |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Brick |
500.000 |
no. |
3.80 |
1900.00 |
|
Sand - Local - Mymensingh |
17.000 |
cft |
13.00 |
221.00 |
|
Cement |
3.000 |
bag |
343.00 |
1029.00 |
|
|
Sub-Total(A1) |
3150.00
|
339.07
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
125mm thick Brick Work |
100.000 |
sft |
6.00 |
600.00 |
|
|
Sub-Total(L0) |
600.00
|
64.58
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Scaffolding |
0.000 |
set |
100.00 |
0.00 |
|
|
Sub-Total(M1) |
0.00
|
0.00
|
|
|
|
Total(1) |
|
403.65 |
|
Add over head on Total(1)
|
3.0 % |
12.11 |
|
|
|
Total(2) |
|
415.76 |
|
Add Profit on Total(2) |
8.0 % |
33.26
|
|
|
|
Total(3) |
|
449.02 |
|
Add VAT on Unit Price |
4.5 % |
21.16 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
470.18
|
|
|
|
Say |
|
Item: 15 (A07A) Glazed Wall Tiles |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
7.030 |
cft |
13.00 |
91.39 |
|
Cement |
1.870 |
bag |
343.00 |
641.41 |
|
White-Cement |
3.600 |
kg |
16.25 |
58.50 |
|
|
Sub-Total(A1) |
791.30
|
85.18
|
A2.Material-Mosaic/Tile |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Glazed Wall Tiles-RAK |
105.000 |
sft |
36.00 |
3780.00 |
|
|
Sub-Total(A2) |
3780.00
|
406.88
|
L2.Labour-Tile/Sanitary |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Floor/ Wall Tiles fitting |
100.000 |
sft |
20.00 |
2000.00 |
|
|
Sub-Total(L2) |
2000.00
|
215.28
|
|
|
|
Total(1) |
|
707.33 |
|
Add over head on Total(1)
|
3.0 % |
21.22 |
|
|
|
Total(2) |
|
728.55 |
|
Add Profit on Total(2) |
8.0 % |
58.28
|
|
|
|
Total(3) |
|
786.84 |
|
Add VAT on Unit Price |
4.5 % |
37.08 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
823.92
|
|
|
|
Say |
|
Item: 13 (A07C) Homogenous Floor Tiles |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
6.250 |
cft |
13.00 |
81.25 |
|
Cement |
2.500 |
bag |
343.00 |
857.50 |
|
White-Cement |
3.600 |
kg |
16.25 |
58.50 |
|
|
Sub-Total(A1) |
997.25
|
107.34
|
A2.Material-Mosaic/Tile |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Homogenious Tiles |
110.000 |
sft |
46.00 |
5060.00 |
|
|
Sub-Total(A2) |
5060.00
|
544.66
|
L2.Labour-Tile/Sanitary |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Floor/ Wall Tiles fitting |
100.000 |
sft |
20.00 |
2000.00 |
|
|
Sub-Total(L2) |
2000.00
|
215.28
|
|
|
|
Total(1) |
|
867.28 |
|
Add over head on Total(1)
|
3.0 % |
26.02 |
|
|
|
Total(2) |
|
893.30 |
|
Add Profit on Total(2) |
8.0 % |
71.46
|
|
|
|
Total(3) |
|
964.76 |
|
Add VAT on Unit Price |
4.5 % |
45.46 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
1010.23
|
|
|
|
Say |
|
Item: 14 (A07E) Homogenious Stiar Step Tiles |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
6.250 |
cft |
13.00 |
81.25 |
|
Cement |
2.500 |
bag |
343.00 |
857.50 |
|
White-Cement |
3.500 |
kg |
16.25 |
56.88 |
|
|
Sub-Total(A1) |
995.63
|
107.17
|
A2.Material-Mosaic/Tile |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Homogeneous Stair Tiles |
130.000 |
sft |
53.00 |
6890.00 |
|
|
Sub-Total(A2) |
6890.00
|
741.64
|
L2.Labour-Tile/Sanitary |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Stair Tiles fitting |
100.000 |
sft |
15.00 |
1500.00 |
|
|
Sub-Total(L2) |
1500.00
|
161.46
|
|
|
|
Total(1) |
|
1010.27 |
|
Add over head on Total(1)
|
3.0 % |
30.31 |
|
|
|
Total(2) |
|
1040.58 |
|
Add Profit on Total(2) |
8.0 % |
83.25
|
|
|
|
Total(3) |
|
1123.82 |
|
Add VAT on Unit Price |
4.5 % |
52.96 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
1176.78
|
|
|
|
Say |
|
Item: 30 (A07F) Ceramic Roof Tiles |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
6.250 |
cft |
13.00 |
81.25 |
|
Cement |
2.500 |
bag |
343.00 |
857.50 |
|
White-Cement |
3.500 |
kg |
16.25 |
56.88 |
|
|
Sub-Total(A1) |
995.63
|
107.17
|
A2.Material-Mosaic/Tile |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Ceramic Roof tiles |
105.000 |
sft |
72.00 |
7560.00 |
|
|
Sub-Total(A2) |
7560.00
|
813.76
|
L2.Labour-Tile/Sanitary |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
C-roof tiles |
100.000 |
sft |
15.00 |
1500.00 |
|
|
Sub-Total(L2) |
1500.00
|
161.46
|
|
|
|
Total(1) |
|
1082.39 |
|
Add over head on Total(1)
|
3.0 % |
32.47 |
|
|
|
Total(2) |
|
1114.86 |
|
Add Profit on Total(2) |
8.0 % |
89.19
|
|
|
|
Total(3) |
|
1204.05 |
|
Add VAT on Unit Price |
4.5 % |
56.74 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
1260.78
|
|
|
|
Say |
|
Item: 31 (A07G1) 300x300 C-tiles with lime morter |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
2.000 |
cft |
13.00 |
26.00 |
|
Cement |
1.500 |
bag |
343.00 |
514.50 |
|
Stone-chips |
2.000 |
cft |
80.00 |
160.00 |
|
Surki |
18.320 |
cft |
35.00 |
641.20 |
|
Stone Lime |
4.160 |
kg |
6.50 |
27.04 |
|
|
Sub-Total(A1) |
1368.74
|
147.33
|
L2.Labour-Tile/Sanitary |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Make Paving Tiles i/c M/c |
100.000 |
nos. |
10.00 |
1000.00 |
|
Tiles Fix with Lime Mortr |
100.000 |
sft |
25.00 |
2500.00 |
|
|
Sub-Total(L2) |
3500.00
|
376.74
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Form work with angle/flat |
26.000 |
sft |
10.00 |
260.00 |
|
|
Sub-Total(M1) |
260.00
|
27.99
|
|
|
|
Total(1) |
|
552.06 |
|
Add over head on Total(1)
|
3.0 % |
16.56 |
|
|
|
Total(2) |
|
568.62 |
|
Add Profit on Total(2) |
8.0 % |
45.49
|
|
|
|
Total(3) |
|
614.11 |
|
Add VAT on Unit Price |
4.5 % |
28.94 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
643.05
|
|
|
|
Say |
|
Item: 05A (A08C) RCC (1:1.5:3) in Column |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Cement |
22.000 |
bag |
343.00 |
7546.00 |
|
Sand - Sylhet |
46.000 |
cft |
24.00 |
1104.00 |
|
Stone-chips |
91.000 |
cft |
80.00 |
7280.00 |
|
|
Sub-Total(A1) |
15930.00
|
5625.68
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mini Dumper |
100.000 |
cft |
2.00 |
200.00 |
|
M/C-Vibrator,S-structure |
100.000 |
cft |
5.00 |
500.00 |
|
|
Sub-Total(E1) |
700.00
|
247.21
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Ordinary Labour Supply |
1.000 |
nos. |
100.00 |
100.00 |
|
RCC Casting-Superstructur |
100.000 |
sft |
10.00 |
1000.00 |
|
FormWork:24-33ft from PL |
305.000 |
sft |
10.00 |
3050.00 |
|
|
Sub-Total(L0) |
4150.00
|
1465.57
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Forms |
305.000 |
sft |
5.00 |
1525.00 |
|
Hessain cloth |
323.000 |
sft |
1.00 |
323.00 |
|
|
Sub-Total(M1) |
1848.00
|
652.62
|
|
|
|
Total(1) |
|
7991.08 |
|
Add over head on Total(1)
|
3.0 % |
239.73 |
|
|
|
Total(2) |
|
8230.81 |
|
Add Profit on Total(2) |
8.0 % |
658.46
|
|
|
|
Total(3) |
|
8889.28 |
|
Add VAT on Unit Price |
4.5 % |
418.87 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
9308.14
|
|
|
|
Say |
|
Item: 05B (A08Y) Beam, Lintel (1:1.5:3) |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Cement |
22.000 |
bag |
343.00 |
7546.00 |
|
Sand - Sylhet |
46.000 |
cft |
24.00 |
1104.00 |
|
Stone-chips |
91.000 |
cft |
80.00 |
7280.00 |
|
|
Sub-Total(A1) |
15930.00
|
5625.68
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mixer m/c and vibrator |
100.000 |
cft |
2.00 |
200.00 |
|
Mini Dumper |
100.000 |
cft |
2.00 |
200.00 |
|
|
Sub-Total(E1) |
400.00
|
141.26
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Ordinary Labour Supply |
1.000 |
nos. |
100.00 |
100.00 |
|
RCC Casting-Superstructur |
100.000 |
sft |
10.00 |
1000.00 |
|
FormWork:24-33ft from PL |
357.000 |
sft |
10.00 |
3570.00 |
|
|
Sub-Total(L0) |
4670.00
|
1649.21
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Forms |
357.000 |
sft |
5.00 |
1785.00 |
|
Steel pipe with B-plate |
15.000 |
no |
11.00 |
165.00 |
|
Wood shutter-3time |
2.000 |
cft |
350.00 |
700.00 |
|
Steel beam,S-structure |
8.000 |
no |
40.00 |
320.00 |
|
|
Sub-Total(M1) |
2970.00
|
1048.86
|
|
|
|
Total(1) |
|
8465.01 |
|
Add over head on Total(1)
|
3.0 % |
253.95 |
|
|
|
Total(2) |
|
8718.96 |
|
Add Profit on Total(2) |
8.0 % |
697.52
|
|
|
|
Total(3) |
|
9416.47 |
|
Add VAT on Unit Price |
4.5 % |
443.71 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
9860.18
|
|
|
|
Say |
|
Item: 05C (A08Z) Parapet wall (1:1.5:3) |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
14.333 |
cft |
13.00 |
186.33 |
|
Cement |
22.000 |
bag |
343.00 |
7546.00 |
|
Sand - Sylhet |
28.667 |
cft |
24.00 |
688.01 |
|
Stone-chips |
86.000 |
cft |
80.00 |
6880.00 |
|
|
Sub-Total(A1) |
15300.34
|
5403.31
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mixer m/c and vibrator |
100.000 |
cft |
2.00 |
200.00 |
|
|
Sub-Total(E1) |
200.00
|
70.63
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
RCC Casting-Superstructur |
100.000 |
sft |
10.00 |
1000.00 |
|
FormWork:24-33ft from PL |
564.000 |
sft |
10.00 |
5640.00 |
|
|
Sub-Total(L0) |
6640.00
|
2344.92
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Forms |
564.000 |
sft |
5.00 |
2820.00 |
|
|
Sub-Total(M1) |
2820.00
|
995.88
|
|
|
|
Total(1) |
|
8814.74 |
|
Add over head on Total(1)
|
3.0 % |
264.44 |
|
|
|
Total(2) |
|
9079.19 |
|
Add Profit on Total(2) |
8.0 % |
726.33
|
|
|
|
Total(3) |
|
9805.52 |
|
Add VAT on Unit Price |
4.5 % |
462.04 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
10267.56
|
|
|
|
Say |
|
Item: 33E (A09F1) Dismantling 250mm brick wall |
|
Basis:1
cft |
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Dismantle B/W 250mm thk |
1.000 |
cft |
5.00 |
5.00 |
|
|
Sub-Total(L1) |
5.00
|
176.58
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Scaffolding |
0.000 |
set |
100.00 |
0.00 |
|
|
Sub-Total(M1) |
0.00
|
0.00
|
|
|
|
Total(1) |
|
176.58 |
|
Add over head on Total(1)
|
3.0 % |
5.30 |
|
|
|
Total(2) |
|
181.87 |
|
Add Profit on Total(2) |
8.0 % |
14.55
|
|
|
|
Total(3) |
|
196.42 |
|
Add VAT on Unit Price |
4.5 % |
9.26 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
205.68
|
|
|
|
Say |
|
Item: 33F (A09H) Dismantling of 125mm b/wall |
|
Basis:1
sft |
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Ordinary Labour Supply |
0.060 |
nos. |
100.00 |
6.00 |
|
|
Sub-Total(L0) |
6.00
|
64.58
|
|
|
|
Total(1) |
|
64.58 |
|
Add over head on Total(1)
|
3.0 % |
1.94 |
|
|
|
Total(2) |
|
66.52 |
|
Add Profit on Total(2) |
8.0 % |
5.32
|
|
|
|
Total(3) |
|
71.84 |
|
Add VAT on Unit Price |
4.5 % |
3.39 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
75.23
|
|
|
|
Say |
|
Item: 05D (A09L) Rcc Darin-Gutter (1:1.5:3) |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
14.333 |
cft |
13.00 |
186.33 |
|
Cement |
22.000 |
bag |
343.00 |
7546.00 |
|
Sand - Sylhet |
28.667 |
cft |
24.00 |
688.01 |
|
Stone-chips |
86.000 |
cft |
80.00 |
6880.00 |
|
|
Sub-Total(A1) |
15300.34
|
5403.31
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mixer m/c and vibrator |
100.000 |
cft |
2.00 |
200.00 |
|
|
Sub-Total(E1) |
200.00
|
70.63
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
RCC Casting-Superstructur |
100.000 |
sft |
10.00 |
1000.00 |
|
|
Sub-Total(L0) |
1000.00
|
353.15
|
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Form work S-structure |
606.060 |
sft |
8.00 |
4848.48 |
|
|
Sub-Total(L1) |
4848.48
|
1712.24
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Scaffolding |
8.000 |
set |
100.00 |
800.00 |
|
Steel pipe with B-plate |
40.000 |
no |
11.00 |
440.00 |
|
Steel form,S-structure |
606.060 |
sft |
10.00 |
6060.60 |
|
|
Sub-Total(M1) |
7300.60
|
2578.21
|
|
|
|
Total(1) |
|
10117.54 |
|
Add over head on Total(1)
|
3.0 % |
303.53 |
|
|
|
Total(2) |
|
10421.07 |
|
Add Profit on Total(2) |
8.0 % |
833.69
|
|
|
|
Total(3) |
|
11254.75 |
|
Add VAT on Unit Price |
4.5 % |
530.33 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
11785.08
|
|
|
|
Say |
|
Item: 05E (A09M) Stair Landing (1:1.5:3) |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
14.333 |
cft |
13.00 |
186.33 |
|
Cement |
22.000 |
bag |
343.00 |
7546.00 |
|
Sand - Sylhet |
28.667 |
cft |
24.00 |
688.01 |
|
Stone-chips |
86.000 |
cft |
80.00 |
6880.00 |
|
|
Sub-Total(A1) |
15300.34
|
5403.31
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mixer m/c and vibrator |
100.000 |
cft |
2.00 |
200.00 |
|
|
Sub-Total(E1) |
200.00
|
70.63
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Formwork upto 10ft from P |
390.000 |
sft |
8.00 |
3120.00 |
|
RCC Casting-Superstructur |
100.000 |
sft |
10.00 |
1000.00 |
|
|
Sub-Total(L0) |
4120.00
|
1454.98
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel pipe with B-plate |
20.000 |
no |
11.00 |
220.00 |
|
Wood shutter-3time |
10.800 |
cft |
350.00 |
3780.00 |
|
|
Sub-Total(M1) |
4000.00
|
1412.60
|
|
|
|
Total(1) |
|
8341.52 |
|
Add over head on Total(1)
|
3.0 % |
250.25 |
|
|
|
Total(2) |
|
8591.77 |
|
Add Profit on Total(2) |
8.0 % |
687.34
|
|
|
|
Total(3) |
|
9279.11 |
|
Add VAT on Unit Price |
4.5 % |
437.24 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
9716.34
|
|
|
|
Say |
|
Item: 05F (A09N) Slab, false slab (1:1.5:3) |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
14.333 |
cft |
13.00 |
186.33 |
|
Cement |
22.000 |
bag |
343.00 |
7546.00 |
|
Sand - Sylhet |
28.667 |
cft |
24.00 |
688.01 |
|
Stone-chips |
86.000 |
cft |
80.00 |
6880.00 |
|
|
Sub-Total(A1) |
15300.34
|
5403.31
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mixer m/c and vibrator |
100.000 |
cft |
2.00 |
200.00 |
|
|
Sub-Total(E1) |
200.00
|
70.63
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
RCC Casting-Superstructur |
100.000 |
sft |
10.00 |
1000.00 |
|
FormWork:24-33ft from PL |
242.000 |
sft |
10.00 |
2420.00 |
|
|
Sub-Total(L0) |
3420.00
|
1207.77
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Forms |
242.000 |
sft |
5.00 |
1210.00 |
|
Steel Scaffolding |
4.000 |
set |
100.00 |
400.00 |
|
B-plate with pipe |
20.000 |
no |
16.00 |
320.00 |
|
Steel beam,S-structure |
12.000 |
no |
40.00 |
480.00 |
|
|
Sub-Total(M1) |
2410.00
|
851.09
|
|
|
|
Total(1) |
|
7532.81 |
|
Add over head on Total(1)
|
3.0 % |
225.98 |
|
|
|
Total(2) |
|
7758.79 |
|
Add Profit on Total(2) |
8.0 % |
620.70
|
|
|
|
Total(3) |
|
8379.50 |
|
Add VAT on Unit Price |
4.5 % |
394.85 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
8774.34
|
|
|
|
Say |
|
Item: 33D (A09N2) Supply of Plstocrete Plus |
|
Basis:1
no. |
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Plastocerte Plus |
1.000 |
kg |
160.00 |
160.00 |
|
|
Sub-Total(M1) |
160.00
|
160.00
|
|
|
|
Total(1) |
|
160.00 |
|
Add over head on Total(1)
|
3.0 % |
4.80 |
|
|
|
Total(2) |
|
164.80 |
|
Add Profit on Total(2) |
8.0 % |
13.18
|
|
|
|
Total(3) |
|
177.98 |
|
Add VAT on Unit Price |
4.5 % |
8.39 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
186.37
|
|
|
|
Say |
|
Item: 06 (A10A) Re-bar Grade 60 |
|
Basis:1000
kg. |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
GI Wire |
10.000 |
kg |
90.00 |
900.00 |
|
Re-bar G60 |
1050.000 |
kg |
40.20 |
42210.00 |
|
|
Sub-Total(A1) |
43110.00
|
160.00
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Re-bar Work |
1000.000 |
kg |
1.65 |
1650.00 |
|
Local carrying Rod |
0.000 |
kg |
0.25 |
0.00 |
|
|
Sub-Total(L0) |
1650.00
|
160.00
|
|
|
|
Total(1) |
|
320.00 |
|
Add over head on Total(1)
|
3.0 % |
9.60 |
|
|
|
Total(2) |
|
329.60 |
|
Add Profit on Total(2) |
8.0 % |
26.37
|
|
|
|
Total(3) |
|
355.97 |
|
Add VAT on Unit Price |
4.5 % |
16.77 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
372.74
|
|
|
|
Say |
|
Item: 19 (A11C) Alum (PC) Sliding/fixed window |
|
Basis:1
sft |
S2.Alum,SS/MS,FalseCeil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Alum.Fixed Window-PowdrCt |
1.000 |
sft |
175.00 |
175.00 |
|
|
Sub-Total(S2) |
175.00
|
1883.70
|
|
|
|
Total(1) |
|
1883.70 |
|
Add over head on Total(1)
|
3.0 % |
56.51 |
|
|
|
Total(2) |
|
1940.21 |
|
Add Profit on Total(2) |
8.0 % |
155.22
|
|
|
|
Total(3) |
|
2095.43 |
|
Add VAT on Unit Price |
4.5 % |
98.74 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
2194.17
|
|
|
|
Say |
|
Item: 20A (A11G) Alum(PC) swing door Plastic-Glass |
|
Basis:1
sft |
S2.Alum,SS/MS,FalseCeil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Alum.Swing doorGlass-Plas |
1.000 |
sft |
470.00 |
470.00 |
|
|
Sub-Total(S2) |
470.00
|
5059.08
|
|
|
|
Total(1) |
|
5059.08 |
|
Add over head on Total(1)
|
3.0 % |
151.77 |
|
|
|
Total(2) |
|
5210.85 |
|
Add Profit on Total(2) |
8.0 % |
416.87
|
|
|
|
Total(3) |
|
5627.72 |
|
Add VAT on Unit Price |
4.5 % |
265.18 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
5892.90
|
|
|
|
Say |
|
Item: 20B (A11I) Alum(PC)-Swing door Louvr-glass |
|
Basis:1
sft |
S2.Alum,SS/MS,FalseCeil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
AlPC) SwingDoorLouvr-Glas |
1.000 |
sft |
439.00 |
439.00 |
|
|
Sub-Total(S2) |
439.00
|
4725.40
|
|
|
|
Total(1) |
|
4725.40 |
|
Add over head on Total(1)
|
3.0 % |
141.76 |
|
|
|
Total(2) |
|
4867.16 |
|
Add Profit on Total(2) |
8.0 % |
389.37
|
|
|
|
Total(3) |
|
5256.53 |
|
Add VAT on Unit Price |
4.5 % |
247.69 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
5504.22
|
|
|
|
Say |
|
Item: 20C (A11J) Alum(PC)-Swing door Pastc-Frst gl |
|
Basis:1
sft |
S2.Alum,SS/MS,FalseCeil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Al(PC) SwDoorPlst-frstGls |
1.000 |
sft |
431.00 |
431.00 |
|
|
Sub-Total(S2) |
431.00
|
4639.28
|
|
|
|
Total(1) |
|
4639.28 |
|
Add over head on Total(1)
|
3.0 % |
139.18 |
|
|
|
Total(2) |
|
4778.46 |
|
Add Profit on Total(2) |
8.0 % |
382.28
|
|
|
|
Total(3) |
|
5160.74 |
|
Add VAT on Unit Price |
4.5 % |
243.18 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
5403.92
|
|
|
|
Say |
|
Item: 20D (A11K) Alum(PC)-Swing-door Lvr-Frst gls |
|
Basis:1
sft |
S2.Alum,SS/MS,FalseCeil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Al(PC) SwDoor Lvr-FrsGls |
1.000 |
sft |
447.00 |
447.00 |
|
|
Sub-Total(S2) |
447.00
|
4811.51
|
|
|
|
Total(1) |
|
4811.51 |
|
Add over head on Total(1)
|
3.0 % |
144.35 |
|
|
|
Total(2) |
|
4955.85 |
|
Add Profit on Total(2) |
8.0 % |
396.47
|
|
|
|
Total(3) |
|
5352.32 |
|
Add VAT on Unit Price |
4.5 % |
252.20 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
5604.53
|
|
|
|
Say |
|
Item: 21 (A11L) Anodzed Aluminium-Cove |
|
Basis:1
rft |
S2.Alum,SS/MS,FalseCeil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Alum Cove - Andz |
1.050 |
rft |
44.00 |
46.20 |
|
Alum Cove - PC |
1.050 |
rft |
46.00 |
48.30 |
|
Al.Cove fix,Sealant,Gaskt |
1.000 |
rft |
10.00 |
10.00 |
|
|
Sub-Total(S2) |
104.50
|
4811.51
|
|
|
|
Total(1) |
|
4811.51 |
|
Add over head on Total(1)
|
3.0 % |
144.35 |
|
|
|
Total(2) |
|
4955.85 |
|
Add Profit on Total(2) |
8.0 % |
396.47
|
|
|
|
Total(3) |
|
5352.32 |
|
Add VAT on Unit Price |
4.5 % |
252.20 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
5604.53
|
|
|
|
Say |
|
Item: 24 (A11M) MS Emergency Exit door |
|
Basis:1
no. |
C2.MS/SS Work i/c matr |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Hollow Metal Door |
26.000 |
sft |
350.00 |
9100.00 |
|
Push Bar1 |
1.000 |
no. |
10000.00 |
10000.00 |
|
|
Sub-Total(C2) |
19100.00
|
19100.00
|
|
|
|
Total(1) |
|
19100.00 |
|
Add over head on Total(1)
|
3.0 % |
573.00 |
|
|
|
Total(2) |
|
19673.00 |
|
Add Profit on Total(2) |
8.0 % |
1573.84
|
|
|
|
Total(3) |
|
21246.84 |
|
Add VAT on Unit Price |
4.5 % |
1001.16 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
22248.00
|
|
|
|
Say |
|
Item: 25 (A11N) Alum-Window Louver |
|
Basis:1
sft |
S2.Alum,SS/MS,FalseCeil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Aluminium Louver |
1.000 |
sft |
310.00 |
310.00 |
|
|
Sub-Total(S2) |
310.00
|
3336.84
|
|
|
|
Total(1) |
|
3336.84 |
|
Add over head on Total(1)
|
3.0 % |
100.11 |
|
|
|
Total(2) |
|
3436.95 |
|
Add Profit on Total(2) |
8.0 % |
274.96
|
|
|
|
Total(3) |
|
3711.90 |
|
Add VAT on Unit Price |
4.5 % |
174.91 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
3886.81
|
|
|
|
Say |
|
Item: 26 (A11O) SS stair railing |
|
Basis:1
sft |
C2.MS/SS Work i/c matr |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
SS Stair Railing1 |
1.000 |
sft |
479.00 |
479.00 |
|
|
Sub-Total(C2) |
479.00
|
5155.96
|
|
|
|
Total(1) |
|
5155.96 |
|
Add over head on Total(1)
|
3.0 % |
154.68 |
|
|
|
Total(2) |
|
5310.63 |
|
Add Profit on Total(2) |
8.0 % |
424.85
|
|
|
|
Total(3) |
|
5735.49 |
|
Add VAT on Unit Price |
4.5 % |
270.26 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
6005.74
|
|
|
|
Say |
|
Item: 33 (A11O2) MS Stair Rail with Doco Paint |
|
Basis:490
sft |
A3.Material-Paint |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Docu Paint |
10.000 |
Ltr |
650.00 |
6500.00 |
|
Docu Base Coat |
8.000 |
Ltr |
220.00 |
1760.00 |
|
NC Thinner-Docu |
48.000 |
Ltr |
80.00 |
3840.00 |
|
|
Sub-Total(A3) |
12100.00
|
265.80
|
C2.MS/SS Work i/c matr |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
MS Stair Railing |
500.000 |
sft |
110.00 |
55000.00 |
|
|
Sub-Total(C2) |
55000.00
|
1208.20
|
L6.Labour Paints |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Duco Paint Complete |
700.000 |
sft |
45.00 |
31500.00 |
|
|
Sub-Total(L6) |
31500.00
|
691.97
|
|
|
|
Total(1) |
|
2165.98 |
|
Add over head on Total(1)
|
3.0 % |
64.98 |
|
|
|
Total(2) |
|
2230.96 |
|
Add Profit on Total(2) |
8.0 % |
178.48
|
|
|
|
Total(3) |
|
2409.44 |
|
Add VAT on Unit Price |
4.5 % |
113.53 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
2522.97
|
|
|
|
Say |
|
Item: 27 (A11P) SS Verandah railing |
|
Basis:1
sft |
C2.MS/SS Work i/c matr |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
SS Verandah Railing |
1.000 |
sft |
291.00 |
291.00 |
|
|
Sub-Total(C2) |
291.00
|
3132.32
|
|
|
|
Total(1) |
|
3132.32 |
|
Add over head on Total(1)
|
3.0 % |
93.97 |
|
|
|
Total(2) |
|
3226.29 |
|
Add Profit on Total(2) |
8.0 % |
258.10
|
|
|
|
Total(3) |
|
3484.40 |
|
Add VAT on Unit Price |
4.5 % |
164.19 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
3648.58
|
|
|
|
Say |
|
Item: 28 (A11Q) SS Bump rail |
|
Basis:1
rft |
C2.MS/SS Work i/c matr |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
SS Bump Rail - 50mm dia |
1.050 |
rft |
250.00 |
262.50 |
|
|
Sub-Total(C2) |
262.50
|
3132.32
|
|
|
|
Total(1) |
|
3132.32 |
|
Add over head on Total(1)
|
3.0 % |
93.97 |
|
|
|
Total(2) |
|
3226.29 |
|
Add Profit on Total(2) |
8.0 % |
258.10
|
|
|
|
Total(3) |
|
3484.40 |
|
Add VAT on Unit Price |
4.5 % |
164.19 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
3648.58
|
|
|
|
Say |
|
Item: 23 (A11R) MS Door |
|
Basis:23
sft |
C2.MS/SS Work i/c matr |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Hollow Metal Door |
22.600 |
sft |
350.00 |
7910.00 |
|
Mortise Door Lock |
1.000 |
no. |
380.00 |
380.00 |
|
|
Sub-Total(C2) |
8290.00
|
3948.39
|
|
|
|
Total(1) |
|
3948.39 |
|
Add over head on Total(1)
|
3.0 % |
118.45 |
|
|
|
Total(2) |
|
4066.84 |
|
Add Profit on Total(2) |
8.0 % |
325.35
|
|
|
|
Total(3) |
|
4392.19 |
|
Add VAT on Unit Price |
4.5 % |
206.96 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
4599.15
|
|
|
|
Say |
|
Item: 22 (A11S) PVC Door i/c Lock(750) |
|
Basis:1
no. |
S2.Alum,SS/MS,FalseCeil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
PVC Door |
1.000 |
no. |
3000.00 |
3000.00 |
|
|
Sub-Total(S2) |
3000.00
|
3000.00
|
|
|
|
Total(1) |
|
3000.00 |
|
Add over head on Total(1)
|
3.0 % |
90.00 |
|
|
|
Total(2) |
|
3090.00 |
|
Add Profit on Total(2) |
8.0 % |
247.20
|
|
|
|
Total(3) |
|
3337.20 |
|
Add VAT on Unit Price |
4.5 % |
157.25 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
3494.45
|
|
|
|
Say |
|
Item: 18 (A11T) Alum-Cartain wall |
|
Basis:1
sft |
S2.Alum,SS/MS,FalseCeil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Curtain Wall |
1.000 |
sft |
383.00 |
383.00 |
|
|
Sub-Total(S2) |
383.00
|
4122.61
|
|
|
|
Total(1) |
|
4122.61 |
|
Add over head on Total(1)
|
3.0 % |
123.68 |
|
|
|
Total(2) |
|
4246.29 |
|
Add Profit on Total(2) |
8.0 % |
339.70
|
|
|
|
Total(3) |
|
4585.99 |
|
Add VAT on Unit Price |
4.5 % |
216.09 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
4802.09
|
|
|
|
Say |
|
Item: 03 (A12A) Plaster(1:5) 20mm thick |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
8.250 |
cft |
13.00 |
107.25 |
|
Cement |
1.100 |
bag |
343.00 |
377.30 |
|
|
Sub-Total(A1) |
484.55
|
52.16
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
OutPlaster 30.5ft |
100.000 |
sft |
4.50 |
450.00 |
|
|
Sub-Total(L0) |
450.00
|
48.44
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Scaffolding |
1.500 |
set |
100.00 |
150.00 |
|
|
Sub-Total(M1) |
150.00
|
16.15
|
|
|
|
Total(1) |
|
116.74 |
|
Add over head on Total(1)
|
3.0 % |
3.50 |
|
|
|
Total(2) |
|
120.24 |
|
Add Profit on Total(2) |
8.0 % |
9.62
|
|
|
|
Total(3) |
|
129.86 |
|
Add VAT on Unit Price |
4.5 % |
6.12 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
135.98
|
|
|
|
Say |
|
Item: 04 (A12E) 8mm thick plaster(1:4) |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
5.000 |
cft |
13.00 |
65.00 |
|
Cement |
1.000 |
bag |
343.00 |
343.00 |
|
|
Sub-Total(A1) |
408.00
|
43.92
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
InPlaster 44.5ft |
100.000 |
sft |
4.00 |
400.00 |
|
|
Sub-Total(L0) |
400.00
|
43.06
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Scaffolding |
0.600 |
set |
100.00 |
60.00 |
|
|
Sub-Total(M1) |
60.00
|
6.46
|
|
|
|
Total(1) |
|
93.43 |
|
Add over head on Total(1)
|
3.0 % |
2.80 |
|
|
|
Total(2) |
|
96.23 |
|
Add Profit on Total(2) |
8.0 % |
7.70
|
|
|
|
Total(3) |
|
103.93 |
|
Add VAT on Unit Price |
4.5 % |
4.90 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
108.83
|
|
|
|
Say |
|
Item: 10 (A13B) Epoxy paint to floor |
|
Basis:100
sft |
A3.Material-Paint |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Epoxy Primer |
2.000 |
Ltr |
170.00 |
340.00 |
|
Epoxy Enamel |
3.080 |
Ltr |
387.00 |
1191.96 |
|
Thinner-T6/T7 |
1.600 |
Ltr |
46.00 |
73.60 |
|
Chalk powder |
1.330 |
kg |
18.00 |
23.94 |
|
Mosaic stone |
0.200 |
no |
110.00 |
22.00 |
|
Scrap |
1.000 |
L.s |
30.00 |
30.00 |
|
|
Sub-Total(A3) |
1681.50
|
181.00
|
L6.Labour Paints |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Epoxy Paint-Floor |
100.000 |
sft |
7.00 |
700.00 |
|
|
Sub-Total(L6) |
700.00
|
75.35
|
|
|
|
Total(1) |
|
256.34 |
|
Add over head on Total(1)
|
3.0 % |
7.69 |
|
|
|
Total(2) |
|
264.03 |
|
Add Profit on Total(2) |
8.0 % |
21.12
|
|
|
|
Total(3) |
|
285.16 |
|
Add VAT on Unit Price |
4.5 % |
13.44 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
298.59
|
|
|
|
Say |
|
Item: 11 (A13D) Epoxy paint to Ceiling |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
White-Cement |
1.000 |
kg |
16.25 |
16.25 |
|
|
Sub-Total(A1) |
16.25
|
1.75
|
A3.Material-Paint |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Epoxy Primer |
2.000 |
Ltr |
170.00 |
340.00 |
|
Epoxy Enamel |
3.080 |
Ltr |
387.00 |
1191.96 |
|
Thinner-T6/T7 |
1.600 |
Ltr |
46.00 |
73.60 |
|
Chalk powder |
1.330 |
kg |
18.00 |
23.94 |
|
Mosaic stone |
0.200 |
no |
110.00 |
22.00 |
|
Scrap |
1.000 |
L.s |
30.00 |
30.00 |
|
Bakram |
1.000 |
yds |
25.00 |
25.00 |
|
Aica |
0.500 |
kg |
120.00 |
60.00 |
|
|
Sub-Total(A3) |
1766.50
|
190.15
|
L6.Labour Paints |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
EpoxyPaint-P.boardCeiling |
100.000 |
sft |
12.00 |
1200.00 |
|
|
Sub-Total(L6) |
1200.00
|
129.17
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Scaffolding |
1.000 |
set |
100.00 |
100.00 |
|
|
Sub-Total(M1) |
100.00
|
10.76
|
|
|
|
Total(1) |
|
331.83 |
|
Add over head on Total(1)
|
3.0 % |
9.95 |
|
|
|
Total(2) |
|
341.78 |
|
Add Profit on Total(2) |
8.0 % |
27.34
|
|
|
|
Total(3) |
|
369.12 |
|
Add VAT on Unit Price |
4.5 % |
17.39 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
386.52
|
|
|
|
Say |
|
Item: 07 (A13E) Plastic paint |
|
Basis:100
sft |
A3.Material-Paint |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Plastron Sealer |
0.800 |
Ltr |
160.00 |
128.00 |
|
Plastic Emulsion |
1.330 |
Ltr |
170.00 |
226.10 |
|
Enamel paint |
0.610 |
Ltr |
170.00 |
103.70 |
|
Snowcel |
2.500 |
kg |
7.60 |
19.00 |
|
Thinner-T6/T7 |
0.800 |
Ltr |
46.00 |
36.80 |
|
Water Paper |
0.500 |
nos |
40.00 |
20.00 |
|
Chalk powder |
2.500 |
kg |
18.00 |
45.00 |
|
Mosaic stone |
0.100 |
no |
110.00 |
11.00 |
|
|
Sub-Total(A3) |
589.60
|
63.46
|
L6.Labour Paints |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Plastic Painting |
100.000 |
sft |
2.50 |
250.00 |
|
|
Sub-Total(L6) |
250.00
|
26.91
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Scaffolding |
1.000 |
set |
100.00 |
100.00 |
|
|
Sub-Total(M1) |
100.00
|
10.76
|
|
|
|
Total(1) |
|
101.14 |
|
Add over head on Total(1)
|
3.0 % |
3.03 |
|
|
|
Total(2) |
|
104.17 |
|
Add Profit on Total(2) |
8.0 % |
8.33
|
|
|
|
Total(3) |
|
112.51 |
|
Add VAT on Unit Price |
4.5 % |
5.30 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
117.81
|
|
|
|
Say |
|
Item: 08 (A13F) Weather coat paint |
|
Basis:100
sft |
A3.Material-Paint |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Plastron Sealer |
0.500 |
Ltr |
160.00 |
80.00 |
|
Enamel paint |
0.250 |
Ltr |
170.00 |
42.50 |
|
Snowcel |
2.500 |
kg |
7.60 |
19.00 |
|
Thinner-T6/T7 |
0.500 |
Ltr |
46.00 |
23.00 |
|
Weather Coat (ColorBank) |
1.420 |
Ltr |
227.85 |
323.55 |
|
|
Sub-Total(A3) |
488.05
|
52.53
|
L6.Labour Paints |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Weather coat painting |
100.000 |
sft |
4.00 |
400.00 |
|
|
Sub-Total(L6) |
400.00
|
43.06
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Scaffolding |
1.000 |
set |
100.00 |
100.00 |
|
|
Sub-Total(M1) |
100.00
|
10.76
|
|
|
|
Total(1) |
|
106.35 |
|
Add over head on Total(1)
|
3.0 % |
3.19 |
|
|
|
Total(2) |
|
109.54 |
|
Add Profit on Total(2) |
8.0 % |
8.76
|
|
|
|
Total(3) |
|
118.31 |
|
Add VAT on Unit Price |
4.5 % |
5.57 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
123.88
|
|
|
|
Say |
|
Item: 09 (A13G) Epoxy paint to wall (New) |
|
Basis:100
sft |
A3.Material-Paint |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Epoxy Primer |
2.000 |
Ltr |
170.00 |
340.00 |
|
Epoxy Enamel |
3.080 |
Ltr |
387.00 |
1191.96 |
|
Thinner-T6/T7 |
1.600 |
Ltr |
46.00 |
73.60 |
|
Chalk powder |
1.330 |
kg |
18.00 |
23.94 |
|
Mosaic stone |
0.200 |
no |
110.00 |
22.00 |
|
Scrap |
1.000 |
L.s |
30.00 |
30.00 |
|
|
Sub-Total(A3) |
1681.50
|
181.00
|
L6.Labour Paints |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Epoxy Paint to wall |
100.000 |
sft |
10.00 |
1000.00 |
|
|
Sub-Total(L6) |
1000.00
|
107.64
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Scaffolding |
1.000 |
set |
100.00 |
100.00 |
|
|
Sub-Total(M1) |
100.00
|
10.76
|
|
|
|
Total(1) |
|
299.40 |
|
Add over head on Total(1)
|
3.0 % |
8.98 |
|
|
|
Total(2) |
|
308.38 |
|
Add Profit on Total(2) |
8.0 % |
24.67
|
|
|
|
Total(3) |
|
333.05 |
|
Add VAT on Unit Price |
4.5 % |
15.69 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
348.75
|
|
|
|
Say |
|
Item: 12 (A13I) Anti-dust sealent paint |
|
Basis:100
sft |
A3.Material-Paint |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Epoxy Clear Laquer |
3.000 |
Ltr |
385.00 |
1155.00 |
|
|
Sub-Total(A3) |
1155.00
|
124.32
|
L6.Labour Paints |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Anti-dust Selant |
100.000 |
sft |
1.50 |
150.00 |
|
|
Sub-Total(L6) |
150.00
|
16.15
|
|
|
|
Total(1) |
|
140.47 |
|
Add over head on Total(1)
|
3.0 % |
4.21 |
|
|
|
Total(2) |
|
144.68 |
|
Add Profit on Total(2) |
8.0 % |
11.57
|
|
|
|
Total(3) |
|
156.26 |
|
Add VAT on Unit Price |
4.5 % |
7.36 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
163.62
|
|
|
|
Say |
|
Item: 16 (A14A) Laminated Gypsum Board Ceiling |
|
Basis:100
sft |
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Scaffolding |
1.000 |
set |
100.00 |
100.00 |
|
|
Sub-Total(M1) |
100.00
|
10.76
|
S2.Alum,SS/MS,FalseCeil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Lamint GypsumBoardCeiling |
100.000 |
sft |
42.00 |
4200.00 |
|
|
Sub-Total(S2) |
4200.00
|
452.09
|
|
|
|
Total(1) |
|
462.85 |
|
Add over head on Total(1)
|
3.0 % |
13.89 |
|
|
|
Total(2) |
|
476.74 |
|
Add Profit on Total(2) |
8.0 % |
38.14
|
|
|
|
Total(3) |
|
514.88 |
|
Add VAT on Unit Price |
4.5 % |
24.26 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
539.14
|
|
|
|
Say |
|
Item: 17 (A14C) Plaster board ceiling |
|
Basis:100
sft |
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Scaffolding |
1.000 |
set |
100.00 |
100.00 |
|
|
Sub-Total(M1) |
100.00
|
10.76
|
S2.Alum,SS/MS,FalseCeil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Plaster Board Ceiling |
100.000 |
sft |
125.00 |
12500.00 |
|
|
Sub-Total(S2) |
12500.00
|
1345.50
|
|
|
|
Total(1) |
|
1356.26 |
|
Add over head on Total(1)
|
3.0 % |
40.69 |
|
|
|
Total(2) |
|
1396.95 |
|
Add Profit on Total(2) |
8.0 % |
111.76
|
|
|
|
Total(3) |
|
1508.71 |
|
Add VAT on Unit Price |
4.5 % |
71.09 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
1579.80
|
|
|
|
Say |
|
Item: 29 (B01A) uPVC Pipe - 150mm dia |
|
Basis:319
rft |
B1.Plumbing/Sanitr Pipe |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
uPVC Pipe 150 dia |
328.280 |
rft |
115.00 |
37752.20 |
|
uPVC Bend 150mm dia |
3.000 |
no. |
560.00 |
1680.00 |
|
uPVC Tee - 150mm dia |
21.000 |
no |
950.00 |
19950.00 |
|
uPVC End Cap -150 dia |
2.000 |
no |
920.00 |
1840.00 |
|
Clamp |
73.000 |
no |
35.00 |
2555.00 |
|
Standing Urinal |
1.000 |
no |
150.00 |
150.00 |
|
Hole making (150 dia) |
21.000 |
no |
350.00 |
7350.00 |
|
S-cement tube |
5.000 |
no |
190.00 |
950.00 |
|
Solvent cement -500 ml |
2.000 |
pot |
490.00 |
980.00 |
|
|
Sub-Total(B1) |
73207.20
|
1345.50
|
L4.Labour-Sanitary |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
uPVC Pipe Fitting -150mm |
318.720 |
rft |
20.00 |
6374.40 |
|
|
Sub-Total(L4) |
6374.40
|
1345.50
|
|
|
|
Total(1) |
|
2691.00 |
|
Add over head on Total(1)
|
3.0 % |
80.73 |
|
|
|
Total(2) |
|
2771.73 |
|
Add Profit on Total(2) |
8.0 % |
221.74
|
|
|
|
Total(3) |
|
2993.47 |
|
Add VAT on Unit Price |
4.5 % |
141.05 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
3134.52
|
|
|
|
Say |
|
Item: 33A (D07A) Rolling Shutter Side Dismantle/Fi |
|
Basis:1
sft |
|
|
|
Total(1) |
|
0.00 |
|
Add over head on Total(1)
|
3.0 % |
80.73 |
|
|
|
Total(2) |
|
2771.73 |
|
Add Profit on Total(2) |
8.0 % |
221.74
|
|
|
|
Total(3) |
|
2993.47 |
|
Add VAT on Unit Price |
4.5 % |
141.05 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
3134.52
|
|
|
|
Say |
|
Item: 33B (D07B) MS Swing Door Remove/Refiting |
|
Basis:1
no. |
|
|
|
Total(1) |
|
0.00 |
|
Add over head on Total(1)
|
3.0 % |
80.73 |
|
|
|
Total(2) |
|
2771.73 |
|
Add Profit on Total(2) |
8.0 % |
221.74
|
|
|
|
Total(3) |
|
2993.47 |
|
Add VAT on Unit Price |
4.5 % |
141.05 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
3134.52
|
|
|
|
Say |
|
Item: 33C (D07C) Wall Top Plaster Dismante/Replast |
|
Basis:1
sft |
|
|
|
Total(1) |
|
0.00 |
|
Add over head on Total(1)
|
3.0 % |
80.73 |
|
|
|
Total(2) |
|
2771.73 |
|
Add Profit on Total(2) |
8.0 % |
221.74
|
|
|
|
Total(3) |
|
2993.47 |
|
Add VAT on Unit Price |
4.5 % |
141.05 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
3134.52
|
|
|
|
Say |
|
Item: 32 (F010) 100 dia SS grating |
|
Basis:1
no. |
B3.Sanitary Fixtures |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
100 dia SS grating |
1.000 |
no |
250.00 |
250.00 |
|
|
Sub-Total(B3) |
250.00
|
250.00
|
|
|
|
Total(1) |
|
250.00 |
|
Add over head on Total(1)
|
3.0 % |
7.50 |
|
|
|
Total(2) |
|
257.50 |
|
Add Profit on Total(2) |
8.0 % |
20.60
|
|
|
|
Total(3) |
|
278.10 |
|
Add VAT on Unit Price |
4.5 % |
13.10 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
291.20
|
|
|
|
Say |
|