Return Main Menu

Project Lift Core at New Liquid Line-3
Item: 04 (A08W) RCC work (1:1.5:3) with 3% pudlu
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
13.750
cft
13.00
178.75
Cement
22.000
bag
343.00
7546.00
Sand - Sylhet
27.500
cft
24.00
660.00
Stone-chips
82.500
cft
80.00
6600.00
Pudloo
33.000
kg
70.00
2310.00
Sub-Total(A1)
17294.75
6107.64
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
100.000
cft
2.00
200.00
Sub-Total(E1)
200.00
70.63
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
RCC Work
100.000
cft
6.00
600.00
Sub-Total(L1)
600.00
211.89
Total(1)
6390.16
Add over head on Total(1)
2.5 %
159.75
Total(2)
6549.91
Add Profit on Total(2)
8.0 %
523.99
Total(3)
7073.91
Add VAT on Unit Price
4.5 %
347.90
Add Income Tax on Unit Price
4.0 %
309.24
Unit Price
7731.05
Say
7731
per M3
Item: 03 (A10A) Re-bar Grade 60
Basis:1000 kg.
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
GI Wire
10.000
kg
90.00
900.00
Re-bar G60
1050.000
kg
40.20
42210.00
Sub-Total(A1)
43110.00
211.89
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Re-bar Work
1000.000
kg
1.65
1650.00
Local carrying Rod
0.000
kg
0.25
0.00
Sub-Total(L0)
1650.00
211.89
Total(1)
423.78
Add over head on Total(1)
2.5 %
10.59
Total(2)
434.37
Add Profit on Total(2)
8.0 %
34.75
Total(3)
469.12
Add VAT on Unit Price
4.5 %
23.07
Add Income Tax on Unit Price
4.0 %
20.51
Unit Price
512.70
Say
513
per TON
Item: 07 (A11M1) Push Bar
Basis:1 no.
C2.MS/SS Work i/c matr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Push Bar1
1.000
no.
10000.00
10000.00
Sub-Total(C2)
10000.00
10000.00
Total(1)
10000.00
Add over head on Total(1)
2.5 %
250.00
Total(2)
10250.00
Add Profit on Total(2)
8.0 %
820.00
Total(3)
11070.00
Add VAT on Unit Price
4.5 %
544.43
Add Income Tax on Unit Price
4.0 %
483.93
Unit Price
12098.36
Say
12098
per NO.
Item: 06 (A11R) MS Door
Basis:23 sft
C2.MS/SS Work i/c matr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Hollow Metal Door
22.600
sft
350.00
7910.00
Mortise Door Lock
1.000
no.
380.00
380.00
Sub-Total(C2)
8290.00
3948.39
Total(1)
3948.39
Add over head on Total(1)
2.5 %
98.71
Total(2)
4047.10
Add Profit on Total(2)
8.0 %
323.77
Total(3)
4370.87
Add VAT on Unit Price
4.5 %
214.96
Add Income Tax on Unit Price
4.0 %
191.08
Unit Price
4776.90
Say
4777
per M2
Item: 05 (C16) M.S I-Beam (203x102)
Basis:1 no.
C1.Steel Structures
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS angle
267.880
kg
38.00
10179.44
M.S plate
15.860
kg
45.00
713.70
200x100 MS I-beam
144.690
rft
300.00
43407.00
100x50 MS I-beam
10.330
rft
180.00
1859.40
6mm MS plate
263.620
kg
45.00
11862.90
Nut-bolt-wasr+galvanized
24.000
no
70.00
1680.00
Sub-Total(C1)
69702.44
69702.44
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carrying L.s
1.000
L.s
1500.00
1500.00
Sub-Total(E1)
1500.00
1500.00
L5.Labour-MS Work
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS angle fixing for slab
521.300
kg
10.00
5213.00
I-Beam Fixing
147.645
rft
50.00
7382.25
Welding for Lift
1.000
L.s
3500.00
3500.00
Sub-Total(L5)
16095.25
16095.25
Total(1)
87297.69
Add over head on Total(1)
2.5 %
2182.44
Total(2)
89480.13
Add Profit on Total(2)
8.0 %
7158.41
Total(3)
96638.54
Add VAT on Unit Price
4.5 %
4752.72
Add Income Tax on Unit Price
4.0 %
4224.64
Unit Price
105615.89
Say
105616
per L.S.
Item: 01 (C18A) SS Lift Door Frame (335mm)
Basis:1 rft
C2.MS/SS Work i/c matr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
1750x1760x2 SS Lift Dr.Co
1.000
rft
645.00
645.00
Sub-Total(C2)
645.00
16095.25
Total(1)
16095.25
Add over head on Total(1)
2.5 %
402.38
Total(2)
16497.63
Add Profit on Total(2)
8.0 %
1319.81
Total(3)
17817.44
Add VAT on Unit Price
4.5 %
876.27
Add Income Tax on Unit Price
4.0 %
778.90
Unit Price
19472.61
Say
19473
per RM
Item: 02 (C18B) SS Plate(110mm) for Lift Door
Basis:4 rft
C2.MS/SS Work i/c matr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
SS Cover 425x350x2
1.000
no.
1410.00
1410.00
Sub-Total(C2)
1410.00
16095.25
Total(1)
16095.25
Add over head on Total(1)
2.5 %
402.38
Total(2)
16497.63
Add Profit on Total(2)
8.0 %
1319.81
Total(3)
17817.44
Add VAT on Unit Price
4.5 %
876.27
Add Income Tax on Unit Price
4.0 %
778.90
Unit Price
19472.61
Say
19473
per RM
Item: 08 (C18C) SS Stair Nosing (25x40mm)
Basis:1 rft
C2.MS/SS Work i/c matr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
SS Cover 425x350x2
0.138
no.
1410.00
194.58
Sub-Total(C2)
194.58
16095.25
Total(1)
16095.25
Add over head on Total(1)
2.5 %
402.38
Total(2)
16497.63
Add Profit on Total(2)
8.0 %
1319.81
Total(3)
17817.44
Add VAT on Unit Price
4.5 %
876.27
Add Income Tax on Unit Price
4.0 %
778.90
Unit Price
19472.61
Say
19473
per RM
Item: 09 (C18D) SS Flat Bar 30mm
Basis:1 rft
C2.MS/SS Work i/c matr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
SS Cover 425x350x2
0.064
no.
1410.00
90.24
Sub-Total(C2)
90.24
16095.25
Total(1)
16095.25
Add over head on Total(1)
2.5 %
402.38
Total(2)
16497.63
Add Profit on Total(2)
8.0 %
1319.81
Total(3)
17817.44
Add VAT on Unit Price
4.5 %
876.27
Add Income Tax on Unit Price
4.0 %
778.90
Unit Price
19472.61
Say
19473
per RM
Item: 10 (C18E) SS Cover 425x350x2mm
Basis:1 no.
C2.MS/SS Work i/c matr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
SS Cover 425x350x2
1.000
no.
1410.00
1410.00
Sub-Total(C2)
1410.00
1410.00
Total(1)
1410.00
Add over head on Total(1)
2.5 %
35.25
Total(2)
1445.25
Add Profit on Total(2)
8.0 %
115.62
Total(3)
1560.87
Add VAT on Unit Price
4.5 %
76.76
Add Income Tax on Unit Price
4.0 %
68.23
Unit Price
1705.87
Say
1706
per NO.
Item: 11 (C18F) SS Angle -75x75x3mm L=1200mm
Basis:1 no.
C2.MS/SS Work i/c matr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
SS Angle 75x75x3
4.134
rft
250.00
1033.50
Sub-Total(C2)
1033.50
1033.50
Total(1)
1033.50
Add over head on Total(1)
2.5 %
25.84
Total(2)
1059.34
Add Profit on Total(2)
8.0 %
84.75
Total(3)
1144.08
Add VAT on Unit Price
4.5 %
56.27
Add Income Tax on Unit Price
4.0 %
50.01
Unit Price
1250.37
Say
1250
per NO.
Item: 12 (C19) MS Bump Rail
Basis:1 sft
C2.MS/SS Work i/c matr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS Bump Rail
1.000
sft
120.00
120.00
Sub-Total(C2)
120.00
1291.68
Total(1)
1291.68
Add over head on Total(1)
2.5 %
32.29
Total(2)
1323.97
Add Profit on Total(2)
8.0 %
105.92
Total(3)
1429.89
Add VAT on Unit Price
4.5 %
70.32
Add Income Tax on Unit Price
4.0 %
62.51
Unit Price
1562.72
Say
1563
per M2