Project RCC Road for Rm+Pm and Fg ware house |
Item: 02D (A01E) E/Cutting with Excavator |
|
Basis:100
cft |
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Excavator |
0.005 |
day |
8000.00 |
40.00 |
|
Wheel Loader-Road |
0.002 |
day |
10000.00 |
20.00 |
|
Dump Truck |
0.007 |
day |
8300.00 |
58.10 |
|
|
Sub-Total(E1) |
118.10
|
41.71
|
|
|
|
Total(1) |
|
41.71 |
|
Add over head on Total(1)
|
3.0 % |
1.25 |
|
|
|
Total(2) |
|
42.96 |
|
Add Profit on Total(2) |
8.0 % |
3.44
|
|
|
|
Total(3) |
|
46.39 |
|
Add VAT on Unit Price |
4.5 % |
2.19 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
48.58
|
|
|
|
Say |
|
Item: 04A (A02A) Brick Flat Soling- Road |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Filling Sand |
5.000 |
cft |
8.50 |
42.50 |
|
Brick |
300.000 |
no. |
3.80 |
1140.00 |
|
|
Sub-Total(A1) |
1182.50
|
127.28
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Ordinary Labour Supply |
0.100 |
nos. |
100.00 |
10.00 |
|
Head Mason Supply |
0.250 |
nos. |
200.00 |
50.00 |
|
|
Sub-Total(L0) |
60.00
|
6.46
|
|
|
|
Total(1) |
|
133.74 |
|
Add over head on Total(1)
|
3.0 % |
4.01 |
|
|
|
Total(2) |
|
137.75 |
|
Add Profit on Total(2) |
8.0 % |
11.02
|
|
|
|
Total(3) |
|
148.78 |
|
Add VAT on Unit Price |
4.5 % |
7.01 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
155.79
|
|
|
|
Say |
|
Item: 05 (A02F) Single layer polythene |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Polythene |
1.500 |
kg |
77.00 |
115.50 |
|
|
Sub-Total(A1) |
115.50
|
12.43
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Ordinary Labour Supply |
0.020 |
nos. |
100.00 |
2.00 |
|
|
Sub-Total(L0) |
2.00
|
0.22
|
|
|
|
Total(1) |
|
12.65 |
|
Add over head on Total(1)
|
3.0 % |
0.38 |
|
|
|
Total(2) |
|
13.03 |
|
Add Profit on Total(2) |
8.0 % |
1.04
|
|
|
|
Total(3) |
|
14.07 |
|
Add VAT on Unit Price |
4.5 % |
0.66 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
14.73
|
|
|
|
Say |
|
Item: 04B (A02G) BFS with existing brick |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Filling Sand |
5.000 |
cft |
8.50 |
42.50 |
|
|
Sub-Total(A1) |
42.50
|
4.57
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Ordinary Labour Supply |
0.400 |
nos. |
100.00 |
40.00 |
|
Head Mason Supply |
0.250 |
nos. |
200.00 |
50.00 |
|
|
Sub-Total(L0) |
90.00
|
9.69
|
|
|
|
Total(1) |
|
14.26 |
|
Add over head on Total(1)
|
3.0 % |
0.43 |
|
|
|
Total(2) |
|
14.69 |
|
Add Profit on Total(2) |
8.0 % |
1.18
|
|
|
|
Total(3) |
|
15.87 |
|
Add VAT on Unit Price |
4.5 % |
0.75 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
16.61
|
|
|
|
Say |
|
Item: 08 (A03J) 50mm thick C.C (1:2:4) with-4% Ad |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
2.500 |
cft |
13.00 |
32.50 |
|
Cement |
3.000 |
bag |
343.00 |
1029.00 |
|
Sand - Sylhet |
5.000 |
cft |
24.00 |
120.00 |
|
Stone-chips |
15.000 |
cft |
80.00 |
1200.00 |
|
Pudloo |
6.000 |
kg |
70.00 |
420.00 |
|
|
Sub-Total(A1) |
2801.50
|
301.55
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mixer m/c and vibrator |
16.700 |
cft |
2.00 |
33.40 |
|
|
Sub-Total(E1) |
33.40
|
3.60
|
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
CC Work |
16.700 |
cft |
5.00 |
83.50 |
|
|
Sub-Total(L1) |
83.50
|
8.99
|
|
|
|
Total(1) |
|
314.14 |
|
Add over head on Total(1)
|
3.0 % |
9.42 |
|
|
|
Total(2) |
|
323.56 |
|
Add Profit on Total(2) |
8.0 % |
25.88
|
|
|
|
Total(3) |
|
349.45 |
|
Add VAT on Unit Price |
4.5 % |
16.47 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
365.91
|
|
|
|
Say |
|
Item: 02A (A05A) Sand filling bott of road-95%comp |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Filling Sand |
130.000 |
cft |
8.50 |
1105.00 |
|
|
Sub-Total(A1) |
1105.00
|
390.23
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Roller hire ch. i/c fuel |
0.050 |
day |
6500.00 |
325.00 |
|
Wheel Loader-Road |
0.010 |
day |
10000.00 |
100.00 |
|
Gradder-Road |
0.001 |
day |
10000.00 |
10.00 |
|
|
Sub-Total(E1) |
435.00
|
153.62
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Ordinary Labour Supply |
1.000 |
nos. |
100.00 |
100.00 |
|
|
Sub-Total(L0) |
100.00
|
35.32
|
|
|
|
Total(1) |
|
579.17 |
|
Add over head on Total(1)
|
3.0 % |
17.37 |
|
|
|
Total(2) |
|
596.54 |
|
Add Profit on Total(2) |
8.0 % |
47.72
|
|
|
|
Total(3) |
|
644.26 |
|
Add VAT on Unit Price |
4.5 % |
30.36 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
674.62
|
|
|
|
Say |
|
Item: 02B (A05B) Sand filling foot path and other |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Filling Sand |
130.000 |
cft |
8.50 |
1105.00 |
|
|
Sub-Total(A1) |
1105.00
|
390.23
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Wheel Loader-Road |
0.015 |
day |
10000.00 |
150.00 |
|
|
Sub-Total(E1) |
150.00
|
52.97
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Ordinary Labour Supply |
1.250 |
nos. |
100.00 |
125.00 |
|
|
Sub-Total(L0) |
125.00
|
44.14
|
|
|
|
Total(1) |
|
487.35 |
|
Add over head on Total(1)
|
3.0 % |
14.62 |
|
|
|
Total(2) |
|
501.97 |
|
Add Profit on Total(2) |
8.0 % |
40.16
|
|
|
|
Total(3) |
|
542.12 |
|
Add VAT on Unit Price |
4.5 % |
25.55 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
567.67
|
|
|
|
Say |
|
Item: 03 (A05C) 400mm thick Sub-base (40:60) |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Filling Sand |
52.000 |
cft |
8.50 |
442.00 |
|
Brick |
819.000 |
no. |
3.80 |
3112.20 |
|
|
Sub-Total(A1) |
3554.20
|
1255.17
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Roller hire ch. i/c fuel |
0.140 |
day |
6500.00 |
910.00 |
|
Wheel Loader-Road |
0.002 |
day |
10000.00 |
20.00 |
|
|
Sub-Total(E1) |
930.00
|
328.43
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Ordinary Labour Supply |
2.000 |
nos. |
100.00 |
200.00 |
|
Brick-chips making 1 1/2" |
819.000 |
no. |
0.33 |
270.27 |
|
|
Sub-Total(L0) |
470.27
|
166.08
|
|
|
|
Total(1) |
|
1749.67 |
|
Add over head on Total(1)
|
3.0 % |
52.49 |
|
|
|
Total(2) |
|
1802.16 |
|
Add Profit on Total(2) |
8.0 % |
144.17
|
|
|
|
Total(3) |
|
1946.33 |
|
Add VAT on Unit Price |
4.5 % |
91.71 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
2038.05
|
|
|
|
Say |
|
Item: 02C (A05E) Back Filling With Roller |
|
Basis:100
cft |
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Roller hire ch. i/c fuel |
0.050 |
day |
6500.00 |
325.00 |
|
Wheel Loader-Road |
0.010 |
day |
10000.00 |
100.00 |
|
Gradder-Road |
0.001 |
day |
10000.00 |
10.00 |
|
|
Sub-Total(E1) |
435.00
|
153.62
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Ordinary Labour Supply |
1.000 |
nos. |
100.00 |
100.00 |
|
|
Sub-Total(L0) |
100.00
|
35.32
|
|
|
|
Total(1) |
|
188.94 |
|
Add over head on Total(1)
|
3.0 % |
5.67 |
|
|
|
Total(2) |
|
194.60 |
|
Add Profit on Total(2) |
8.0 % |
15.57
|
|
|
|
Total(3) |
|
210.17 |
|
Add VAT on Unit Price |
4.5 % |
9.90 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
220.07
|
|
|
|
Say |
|
Item: 17 (A06E) Drain (Trench)-1000x11000mm |
|
Basis:33
rft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Filling Sand |
5.920 |
cft |
8.50 |
50.32 |
|
Brick |
1786.000 |
no. |
3.80 |
6786.80 |
|
Sand - Local - Mymensingh |
83.290 |
cft |
13.00 |
1082.77 |
|
Polythene |
1.700 |
kg |
77.00 |
130.90 |
|
Cement |
24.000 |
bag |
343.00 |
8232.00 |
|
Sand - Sylhet |
24.790 |
cft |
24.00 |
594.96 |
|
Stone-chips |
74.380 |
cft |
80.00 |
5950.40 |
|
Re-bar G60 |
152.000 |
kg |
40.20 |
6110.40 |
|
|
Sub-Total(A1) |
28938.55
|
35.32
|
C1.Steel Structures |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
MS angle |
47.570 |
kg |
38.00 |
1807.66 |
|
M.S plate |
14.860 |
kg |
45.00 |
668.70 |
|
10 dia Rowel bolt |
16.000 |
no |
75.00 |
1200.00 |
|
|
Sub-Total(C1) |
3676.36
|
35.32
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mixer m/c and vibrator |
67.980 |
cft |
2.00 |
135.96 |
|
|
Sub-Total(E1) |
135.96
|
35.32
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Formwork upto 10ft from P |
37.670 |
sft |
8.00 |
301.36 |
|
Dismentling F/W/Mar tile |
134.550 |
sft |
10.00 |
1345.50 |
|
Neat Cement Finishing |
134.550 |
sft |
1.00 |
134.55 |
|
RCC Casting. |
67.980 |
cft |
8.00 |
543.84 |
|
250mm Brickwork upto 7 ft |
119.188 |
cft |
4.25 |
506.55 |
|
|
Sub-Total(L0) |
2831.80
|
35.32
|
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Earth Work in Excavation |
423.780 |
cft |
1.80 |
762.80 |
|
Filling |
48.910 |
cft |
1.00 |
48.91 |
|
Brck flat soling |
118.404 |
sft |
0.60 |
71.04 |
|
Patent stone with NCF |
64.584 |
sft |
3.00 |
193.75 |
|
|
Sub-Total(L1) |
1076.51
|
35.32
|
L4.Labour-Sanitary |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Drain Cover Slab Fixing |
32.810 |
rft |
20.00 |
656.20 |
|
|
Sub-Total(L4) |
656.20
|
35.32
|
L5.Labour-MS Work |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
MS angle fixing with plat |
31.490 |
rft |
5.00 |
157.45 |
|
|
Sub-Total(L5) |
157.45
|
35.32
|
S1.Sub-contractor-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Painting to MS surface |
28.410 |
sft |
5.00 |
142.05 |
|
|
Sub-Total(S1) |
142.05
|
35.32
|
|
|
|
Total(1) |
|
282.52 |
|
Add over head on Total(1)
|
3.0 % |
8.48 |
|
|
|
Total(2) |
|
291.00 |
|
Add Profit on Total(2) |
8.0 % |
23.28
|
|
|
|
Total(3) |
|
314.28 |
|
Add VAT on Unit Price |
4.5 % |
14.81 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
329.08
|
|
|
|
Say |
|
Item: 09 (A07D) 300x300x25-degn terracotta pavers |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
13.880 |
cft |
13.00 |
180.44 |
|
Cement |
3.700 |
bag |
343.00 |
1269.10 |
|
|
Sub-Total(A1) |
1449.54
|
156.03
|
A2.Material-Mosaic/Tile |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
300x300x25 P-Tiles-CC |
105.000 |
sft |
49.61 |
5209.05 |
|
|
Sub-Total(A2) |
5209.05
|
560.70
|
L2.Labour-Tile/Sanitary |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Paving Tiles Fitting |
100.000 |
sft |
20.00 |
2000.00 |
|
|
Sub-Total(L2) |
2000.00
|
215.28
|
|
|
|
Total(1) |
|
932.01 |
|
Add over head on Total(1)
|
3.0 % |
27.96 |
|
|
|
Total(2) |
|
959.97 |
|
Add Profit on Total(2) |
8.0 % |
76.80
|
|
|
|
Total(3) |
|
1036.77 |
|
Add VAT on Unit Price |
4.5 % |
48.85 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
1085.62
|
|
|
|
Say |
|
Item: 07B (A08N) Precast Kerb(1:1.5:3) Ex Rebar |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
13.750 |
cft |
13.00 |
178.75 |
|
Cement |
22.000 |
bag |
343.00 |
7546.00 |
|
Sand - Sylhet |
27.500 |
cft |
24.00 |
660.00 |
|
Stone-chips |
90.000 |
cft |
80.00 |
7200.00 |
|
|
Sub-Total(A1) |
15584.75
|
5503.75
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mixer m/c and vibrator |
100.000 |
cft |
2.00 |
200.00 |
|
|
Sub-Total(E1) |
200.00
|
70.63
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Formwork upto 10ft from P |
200.000 |
sft |
8.00 |
1600.00 |
|
Ordinary Labour Supply |
10.000 |
nos. |
100.00 |
1000.00 |
|
Head Mason Supply |
5.000 |
nos. |
200.00 |
1000.00 |
|
|
Sub-Total(L0) |
3600.00
|
1271.34
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Forms |
200.000 |
sft |
5.00 |
1000.00 |
|
|
Sub-Total(M1) |
1000.00
|
353.15
|
|
|
|
Total(1) |
|
7198.87 |
|
Add over head on Total(1)
|
3.0 % |
215.97 |
|
|
|
Total(2) |
|
7414.84 |
|
Add Profit on Total(2) |
8.0 % |
593.19
|
|
|
|
Total(3) |
|
8008.03 |
|
Add VAT on Unit Price |
4.5 % |
377.34 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
8385.37
|
|
|
|
Say |
|
Item: 06C (A08Q) RCC (1:2:4) as Cast Kerb ex Rebar |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
15.000 |
cft |
13.00 |
195.00 |
|
Cement |
18.000 |
bag |
343.00 |
6174.00 |
|
Sand - Sylhet |
30.000 |
cft |
24.00 |
720.00 |
|
Stone-chips |
90.000 |
cft |
80.00 |
7200.00 |
|
|
Sub-Total(A1) |
14289.00
|
5046.16
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mixer m/c and vibrator |
100.000 |
cft |
2.00 |
200.00 |
|
Mini Dumper |
100.000 |
cft |
2.00 |
200.00 |
|
|
Sub-Total(E1) |
400.00
|
141.26
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Formwork upto 10ft from P |
650.000 |
sft |
8.00 |
5200.00 |
|
RCC Casting. |
100.000 |
cft |
8.00 |
800.00 |
|
|
Sub-Total(L0) |
6000.00
|
2118.90
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Forms |
650.000 |
sft |
5.00 |
3250.00 |
|
|
Sub-Total(M1) |
3250.00
|
1147.74
|
|
|
|
Total(1) |
|
8454.06 |
|
Add over head on Total(1)
|
3.0 % |
253.62 |
|
|
|
Total(2) |
|
8707.68 |
|
Add Profit on Total(2) |
8.0 % |
696.61
|
|
|
|
Total(3) |
|
9404.29 |
|
Add VAT on Unit Price |
4.5 % |
443.13 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
9847.43
|
|
|
|
Say |
|
Item: 07A (A08S) Precast RCC(1:1.5:3)Kerb i/c Rebr |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
13.750 |
cft |
13.00 |
178.75 |
|
Cement |
22.000 |
bag |
343.00 |
7546.00 |
|
Sand - Sylhet |
27.500 |
cft |
24.00 |
660.00 |
|
Stone-chips |
90.000 |
cft |
80.00 |
7200.00 |
|
GI Wire |
2.330 |
kg |
90.00 |
209.70 |
|
Re-bar G60 |
334.090 |
kg |
40.20 |
13430.42 |
|
|
Sub-Total(A1) |
29224.87
|
10320.76
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mixer m/c and vibrator |
100.000 |
cft |
2.00 |
200.00 |
|
|
Sub-Total(E1) |
200.00
|
70.63
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Re-bar Work |
334.090 |
kg |
1.65 |
551.25 |
|
Formwork upto 10ft from P |
200.000 |
sft |
8.00 |
1600.00 |
|
Ordinary Labour Supply |
10.000 |
nos. |
100.00 |
1000.00 |
|
Head Mason Supply |
5.000 |
nos. |
200.00 |
1000.00 |
|
|
Sub-Total(L0) |
4151.25
|
1466.01
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Forms |
200.000 |
sft |
5.00 |
1000.00 |
|
|
Sub-Total(M1) |
1000.00
|
353.15
|
|
|
|
Total(1) |
|
12210.56 |
|
Add over head on Total(1)
|
3.0 % |
366.32 |
|
|
|
Total(2) |
|
12576.87 |
|
Add Profit on Total(2) |
8.0 % |
1006.15
|
|
|
|
Total(3) |
|
13583.02 |
|
Add VAT on Unit Price |
4.5 % |
640.04 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
14223.06
|
|
|
|
Say |
|
Item: 06B (A08T) RCC(1:2:4) As Cast Kerb i/c Rebar |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
15.000 |
cft |
13.00 |
195.00 |
|
Cement |
18.000 |
bag |
343.00 |
6174.00 |
|
Sand - Sylhet |
30.000 |
cft |
24.00 |
720.00 |
|
Stone-chips |
90.000 |
cft |
80.00 |
7200.00 |
|
GI Wire |
1.560 |
kg |
90.00 |
140.40 |
|
Re-bar G60 |
222.730 |
kg |
40.20 |
8953.75 |
|
|
Sub-Total(A1) |
23383.15
|
8257.76
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mixer m/c and vibrator |
100.000 |
cft |
2.00 |
200.00 |
|
Mini Dumper |
100.000 |
cft |
2.00 |
200.00 |
|
|
Sub-Total(E1) |
400.00
|
141.26
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Re-bar Work |
222.730 |
kg |
1.65 |
367.50 |
|
Formwork upto 10ft from P |
650.000 |
sft |
8.00 |
5200.00 |
|
RCC Casting. |
100.000 |
cft |
8.00 |
800.00 |
|
|
Sub-Total(L0) |
6367.50
|
2248.68
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Forms |
650.000 |
sft |
5.00 |
3250.00 |
|
|
Sub-Total(M1) |
3250.00
|
1147.74
|
|
|
|
Total(1) |
|
11795.44 |
|
Add over head on Total(1)
|
3.0 % |
353.86 |
|
|
|
Total(2) |
|
12149.30 |
|
Add Profit on Total(2) |
8.0 % |
971.94
|
|
|
|
Total(3) |
|
13121.25 |
|
Add VAT on Unit Price |
4.5 % |
618.28 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
13739.53
|
|
|
|
Say |
|
Item: 06A (A08U) Rcc Road, drain and parking-1:2:4 |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
15.000 |
cft |
13.00 |
195.00 |
|
Cement |
18.000 |
bag |
343.00 |
6174.00 |
|
Sand - Sylhet |
30.000 |
cft |
24.00 |
720.00 |
|
Stone-chips |
90.000 |
cft |
80.00 |
7200.00 |
|
Dowel Bar-20mm plain |
13.200 |
kg |
40.00 |
528.00 |
|
Rubber bush |
9.700 |
no |
22.00 |
213.40 |
|
|
Sub-Total(A1) |
15030.40
|
5307.99
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mixer m/c and vibrator |
100.000 |
cft |
2.00 |
200.00 |
|
Mini Dumper |
100.000 |
cft |
2.00 |
200.00 |
|
|
Sub-Total(E1) |
400.00
|
141.26
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Formwork upto 10ft from P |
8.000 |
sft |
8.00 |
64.00 |
|
Ordinary Labour Supply |
0.065 |
nos. |
100.00 |
6.50 |
|
Head Mason Supply |
0.150 |
nos. |
200.00 |
30.00 |
|
RCC Casting. |
100.000 |
cft |
8.00 |
800.00 |
|
|
Sub-Total(L0) |
900.50
|
318.01
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Wood shutter-3time |
0.025 |
cft |
350.00 |
8.75 |
|
Cork Sheet-12mm |
20.000 |
sft |
3.50 |
70.00 |
|
|
Sub-Total(M1) |
78.75
|
27.81
|
|
|
|
Total(1) |
|
5795.07 |
|
Add over head on Total(1)
|
3.0 % |
173.85 |
|
|
|
Total(2) |
|
5968.92 |
|
Add Profit on Total(2) |
8.0 % |
477.51
|
|
|
|
Total(3) |
|
6446.43 |
|
Add VAT on Unit Price |
4.5 % |
303.76 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
6750.19
|
|
|
|
Say |
|
Item: 15 (A08V) Septic tank (5.5x2.5x2.25M)-out-o |
|
Basis:1
no. |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Filling Sand |
1009.290 |
cft |
8.50 |
8578.97 |
|
Brick |
520.000 |
no. |
3.80 |
1976.00 |
|
Sand - Local - Mymensingh |
115.000 |
cft |
13.00 |
1495.00 |
|
Polythene |
7.000 |
kg |
77.00 |
539.00 |
|
Cement |
100.000 |
bag |
343.00 |
34300.00 |
|
Sand - Sylhet |
160.000 |
cft |
24.00 |
3840.00 |
|
GI Wire |
10.500 |
kg |
90.00 |
945.00 |
|
Re-bar G60 |
1560.000 |
kg |
40.20 |
62712.00 |
|
Bitumens |
21.450 |
kg |
30.00 |
643.50 |
|
|
Sub-Total(A1) |
115029.47
|
115029.47
|
B1.Plumbing/Sanitr Pipe |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
CI Cover -450MM DIA |
5.000 |
no. |
2500.00 |
12500.00 |
|
|
Sub-Total(B1) |
12500.00
|
12500.00
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Re-bar Work |
1485.500 |
kg |
1.65 |
2451.08 |
|
Formwork upto 10ft from P |
1246.000 |
sft |
8.00 |
9968.00 |
|
Dismentling F/W/Mar tile |
667.370 |
sft |
10.00 |
6673.70 |
|
Neat Cement Finishing |
667.370 |
sft |
1.00 |
667.37 |
|
RCC Casting. |
443.450 |
cft |
8.00 |
3547.60 |
|
|
Sub-Total(L0) |
23307.75
|
23307.75
|
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Filling |
869.010 |
cft |
1.00 |
869.01 |
|
Brck flat soling |
182.988 |
sft |
0.60 |
109.79 |
|
Patent stone with NCF |
156.074 |
sft |
3.00 |
468.22 |
|
Bitumen painting |
430.560 |
sft |
1.00 |
430.56 |
|
|
Sub-Total(L1) |
1877.58
|
1877.58
|
L4.Labour-Sanitary |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Manhole Cover fixing |
5.000 |
no. |
300.00 |
1500.00 |
|
|
Sub-Total(L4) |
1500.00
|
1500.00
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Forms |
1246.000 |
sft |
5.00 |
6230.00 |
|
Shoring for Excavation |
711.000 |
sft |
2.15 |
1528.65 |
|
|
Sub-Total(M1) |
7758.65
|
7758.65
|
|
|
|
Total(1) |
|
161973.44 |
|
Add over head on Total(1)
|
3.0 % |
4859.20 |
|
|
|
Total(2) |
|
166832.65 |
|
Add Profit on Total(2) |
8.0 % |
13346.61
|
|
|
|
Total(3) |
|
180179.26 |
|
Add VAT on Unit Price |
4.5 % |
8490.12 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
188669.38
|
|
|
|
Say |
|
Item: 10 (A10A) Re-bar Grade 60 |
|
Basis:1000
kg. |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
GI Wire |
10.000 |
kg |
90.00 |
900.00 |
|
Re-bar G60 |
1050.000 |
kg |
40.20 |
42210.00 |
|
|
Sub-Total(A1) |
43110.00
|
7758.65
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Re-bar Work |
1000.000 |
kg |
1.65 |
1650.00 |
|
Local carrying Rod |
0.000 |
kg |
0.25 |
0.00 |
|
|
Sub-Total(L0) |
1650.00
|
7758.65
|
|
|
|
Total(1) |
|
15517.30 |
|
Add over head on Total(1)
|
3.0 % |
465.52 |
|
|
|
Total(2) |
|
15982.82 |
|
Add Profit on Total(2) |
8.0 % |
1278.63
|
|
|
|
Total(3) |
|
17261.44 |
|
Add VAT on Unit Price |
4.5 % |
813.37 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
18074.81
|
|
|
|
Say |
|
Item: 01 (A18I) Dismantling CC, BFS, HBB |
|
Basis:100
sft |
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Ordinary Labour Supply |
1.500 |
nos. |
100.00 |
150.00 |
|
|
Sub-Total(L0) |
150.00
|
16.15
|
|
|
|
Total(1) |
|
16.15 |
|
Add over head on Total(1)
|
3.0 % |
0.48 |
|
|
|
Total(2) |
|
16.63 |
|
Add Profit on Total(2) |
8.0 % |
1.33
|
|
|
|
Total(3) |
|
17.96 |
|
Add VAT on Unit Price |
4.5 % |
0.85 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
18.81
|
|
|
|
Say |
|
Item: 14A (A22A) Ins. pit A type 500x500-in-in |
|
Basis:1
no. |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Brick |
21.000 |
no. |
3.80 |
79.80 |
|
Sand - Local - Mymensingh |
2.520 |
cft |
13.00 |
32.76 |
|
Polythene |
0.120 |
kg |
77.00 |
9.24 |
|
Cement |
3.160 |
bag |
343.00 |
1083.88 |
|
Sand - Sylhet |
4.000 |
cft |
24.00 |
96.00 |
|
Stone-chips |
11.930 |
cft |
80.00 |
954.40 |
|
Re-bar - G40 |
31.940 |
kg |
38.50 |
1229.69 |
|
GI Wire |
0.220 |
kg |
90.00 |
19.80 |
|
|
Sub-Total(A1) |
3505.57
|
3505.57
|
B1.Plumbing/Sanitr Pipe |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
CI Cover 300 mm dia |
1.000 |
no. |
750.00 |
750.00 |
|
|
Sub-Total(B1) |
750.00
|
750.00
|
C1.Steel Structures |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Galvanized Angle 38x38 |
1.720 |
rft |
125.00 |
215.00 |
|
MS Grating 200x75 |
1.000 |
no. |
100.00 |
100.00 |
|
|
Sub-Total(C1) |
315.00
|
315.00
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Re-bar Work |
30.420 |
kg |
1.65 |
50.19 |
|
Formwork upto 10ft from P |
35.830 |
sft |
8.00 |
286.64 |
|
Dismentling F/W/Mar tile |
10.760 |
sft |
10.00 |
107.60 |
|
Neat Cement Finishing |
10.760 |
sft |
1.00 |
10.76 |
|
RCC Casting. |
13.660 |
cft |
8.00 |
109.28 |
|
|
Sub-Total(L0) |
564.47
|
564.47
|
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Earth Work in Excavation |
55.440 |
cft |
1.80 |
99.79 |
|
Filling |
28.300 |
cft |
1.00 |
28.30 |
|
Brck flat soling |
6.880 |
sft |
0.60 |
4.13 |
|
Patent stone with NCF |
2.690 |
sft |
3.00 |
8.07 |
|
|
Sub-Total(L1) |
140.29
|
140.29
|
L4.Labour-Sanitary |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Manhole Cover fixing |
1.000 |
no. |
300.00 |
300.00 |
|
|
Sub-Total(L4) |
300.00
|
300.00
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Forms |
35.830 |
sft |
5.00 |
179.15 |
|
|
Sub-Total(M1) |
179.15
|
179.15
|
|
|
|
Total(1) |
|
5754.48 |
|
Add over head on Total(1)
|
3.0 % |
172.63 |
|
|
|
Total(2) |
|
5927.12 |
|
Add Profit on Total(2) |
8.0 % |
474.17
|
|
|
|
Total(3) |
|
6401.29 |
|
Add VAT on Unit Price |
4.5 % |
301.63 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
6702.92
|
|
|
|
Say |
|
Item: 14B (A22B) Ins. pit B type 750x750-in-in |
|
Basis:1
no. |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Brick |
32.000 |
no. |
3.80 |
121.60 |
|
Sand - Local - Mymensingh |
3.780 |
cft |
13.00 |
49.14 |
|
Polythene |
0.180 |
kg |
77.00 |
13.86 |
|
Cement |
4.740 |
bag |
343.00 |
1625.82 |
|
Sand - Sylhet |
6.000 |
cft |
24.00 |
144.00 |
|
Stone-chips |
17.900 |
cft |
80.00 |
1432.00 |
|
Re-bar - G40 |
48.300 |
kg |
38.50 |
1859.55 |
|
GI Wire |
0.330 |
kg |
90.00 |
29.70 |
|
|
Sub-Total(A1) |
5275.67
|
5275.67
|
B1.Plumbing/Sanitr Pipe |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
CI Cover 300 mm dia |
1.000 |
no. |
750.00 |
750.00 |
|
|
Sub-Total(B1) |
750.00
|
750.00
|
C1.Steel Structures |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Galvanized Angle 38x38 |
2.580 |
rft |
125.00 |
322.50 |
|
MS Grating 200x75 |
1.000 |
no. |
100.00 |
100.00 |
|
|
Sub-Total(C1) |
422.50
|
422.50
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mixer m/c and vibrator |
20.490 |
cft |
2.00 |
40.98 |
|
|
Sub-Total(E1) |
40.98
|
40.98
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Re-bar Work |
46.000 |
kg |
1.65 |
75.90 |
|
Formwork upto 10ft from P |
53.740 |
sft |
8.00 |
429.92 |
|
Dismentling F/W/Mar tile |
16.140 |
sft |
10.00 |
161.40 |
|
Neat Cement Finishing |
16.140 |
sft |
1.00 |
16.14 |
|
RCC Casting. |
20.490 |
cft |
8.00 |
163.92 |
|
|
Sub-Total(L0) |
847.28
|
847.28
|
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Earth Work in Excavation |
83.160 |
cft |
1.80 |
149.69 |
|
Filling |
42.450 |
cft |
1.00 |
42.45 |
|
Brck flat soling |
11.860 |
sft |
0.60 |
7.12 |
|
Patent stone with NCF |
4.035 |
sft |
3.00 |
12.11 |
|
|
Sub-Total(L1) |
211.36
|
211.36
|
L4.Labour-Sanitary |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Manhole Cover fixing |
1.000 |
no. |
300.00 |
300.00 |
|
|
Sub-Total(L4) |
300.00
|
300.00
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Forms |
53.740 |
sft |
5.00 |
268.70 |
|
|
Sub-Total(M1) |
268.70
|
268.70
|
|
|
|
Total(1) |
|
8116.49 |
|
Add over head on Total(1)
|
3.0 % |
243.49 |
|
|
|
Total(2) |
|
8359.98 |
|
Add Profit on Total(2) |
8.0 % |
668.80
|
|
|
|
Total(3) |
|
9028.78 |
|
Add VAT on Unit Price |
4.5 % |
425.44 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
9454.22
|
|
|
|
Say |
|
Item: 14C (A22C) Ins. pit C type 1000x1000-in-in |
|
Basis:1
no. |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Brick |
55.000 |
no. |
3.80 |
209.00 |
|
Sand - Local - Mymensingh |
5.040 |
cft |
13.00 |
65.52 |
|
Polythene |
0.240 |
kg |
77.00 |
18.48 |
|
Cement |
6.320 |
bag |
343.00 |
2167.76 |
|
Sand - Sylhet |
8.000 |
cft |
24.00 |
192.00 |
|
Stone-chips |
23.860 |
cft |
80.00 |
1908.80 |
|
GI Wire |
0.440 |
kg |
90.00 |
39.60 |
|
Re-bar G60 |
63.880 |
kg |
40.20 |
2567.98 |
|
|
Sub-Total(A1) |
7169.14
|
7169.14
|
B1.Plumbing/Sanitr Pipe |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
CI Cover 300 mm dia |
1.000 |
no. |
750.00 |
750.00 |
|
|
Sub-Total(B1) |
750.00
|
750.00
|
C1.Steel Structures |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Galvanized Angle 38x38 |
1.720 |
rft |
125.00 |
215.00 |
|
MS Grating 200x75 |
1.000 |
no. |
100.00 |
100.00 |
|
|
Sub-Total(C1) |
315.00
|
315.00
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Re-bar Work |
60.840 |
kg |
1.65 |
100.39 |
|
Formwork upto 10ft from P |
71.660 |
sft |
8.00 |
573.28 |
|
Dismentling F/W/Mar tile |
21.520 |
sft |
10.00 |
215.20 |
|
Neat Cement Finishing |
21.520 |
sft |
1.00 |
21.52 |
|
RCC Casting. |
27.320 |
cft |
8.00 |
218.56 |
|
|
Sub-Total(L0) |
1128.95
|
1128.95
|
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Earth Work in Excavation |
110.880 |
cft |
1.80 |
199.58 |
|
Filling |
56.600 |
cft |
1.00 |
56.60 |
|
Brck flat soling |
18.190 |
sft |
0.60 |
10.91 |
|
Patent stone with NCF |
5.380 |
sft |
3.00 |
16.14 |
|
|
Sub-Total(L1) |
283.24
|
283.24
|
L4.Labour-Sanitary |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Manhole Cover fixing |
1.000 |
no. |
300.00 |
300.00 |
|
|
Sub-Total(L4) |
300.00
|
300.00
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Forms |
71.660 |
sft |
5.00 |
358.30 |
|
|
Sub-Total(M1) |
358.30
|
358.30
|
|
|
|
Total(1) |
|
10304.62 |
|
Add over head on Total(1)
|
3.0 % |
309.14 |
|
|
|
Total(2) |
|
10613.76 |
|
Add Profit on Total(2) |
8.0 % |
849.10
|
|
|
|
Total(3) |
|
11462.86 |
|
Add VAT on Unit Price |
4.5 % |
540.13 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
12002.99
|
|
|
|
Say |
|
Item: 14D (A22D) Ins. pit D type 1200x1200-in-in |
|
Basis:1
no. |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Brick |
72.650 |
no. |
3.80 |
276.07 |
|
Sand - Local - Mymensingh |
6.040 |
cft |
13.00 |
78.52 |
|
Polythene |
0.350 |
kg |
77.00 |
26.95 |
|
Cement |
7.580 |
bag |
343.00 |
2599.94 |
|
Sand - Sylhet |
9.600 |
cft |
24.00 |
230.40 |
|
Stone-chips |
28.630 |
cft |
80.00 |
2290.40 |
|
GI Wire |
0.536 |
kg |
90.00 |
48.24 |
|
Re-bar G60 |
76.660 |
kg |
40.20 |
3081.73 |
|
|
Sub-Total(A1) |
8632.25
|
8632.25
|
B1.Plumbing/Sanitr Pipe |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
CI Cover 300 mm dia |
1.000 |
no. |
750.00 |
750.00 |
|
|
Sub-Total(B1) |
750.00
|
750.00
|
C1.Steel Structures |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Galvanized Angle 38x38 |
1.720 |
rft |
125.00 |
215.00 |
|
MS Grating 200x75 |
1.000 |
no. |
100.00 |
100.00 |
|
|
Sub-Total(C1) |
315.00
|
315.00
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mixer m/c and vibrator |
32.780 |
cft |
2.00 |
65.56 |
|
|
Sub-Total(E1) |
65.56
|
65.56
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Re-bar Work |
73.010 |
kg |
1.65 |
120.47 |
|
Formwork upto 10ft from P |
86.000 |
sft |
8.00 |
688.00 |
|
Dismentling F/W/Mar tile |
25.820 |
sft |
10.00 |
258.20 |
|
Neat Cement Finishing |
25.820 |
sft |
1.00 |
25.82 |
|
RCC Casting. |
32.780 |
cft |
8.00 |
262.24 |
|
|
Sub-Total(L0) |
1354.73
|
1354.73
|
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Earth Work in Excavation |
133.050 |
cft |
1.80 |
239.49 |
|
Filling |
67.920 |
cft |
1.00 |
67.92 |
|
Patent stone with NCF |
6.450 |
sft |
3.00 |
19.35 |
|
|
Sub-Total(L1) |
326.76
|
326.76
|
L4.Labour-Sanitary |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Manhole Cover fixing |
1.000 |
no. |
300.00 |
300.00 |
|
|
Sub-Total(L4) |
300.00
|
300.00
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Forms |
86.000 |
sft |
5.00 |
430.00 |
|
|
Sub-Total(M1) |
430.00
|
430.00
|
|
|
|
Total(1) |
|
12174.30 |
|
Add over head on Total(1)
|
3.0 % |
365.23 |
|
|
|
Total(2) |
|
12539.53 |
|
Add Profit on Total(2) |
8.0 % |
1003.16
|
|
|
|
Total(3) |
|
13542.69 |
|
Add VAT on Unit Price |
4.5 % |
638.14 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
14180.83
|
|
|
|
Say |
|
Item: 14E (A22E) Ins. pit E type 1500x1500-in-in |
|
Basis:1
no. |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Brick |
105.000 |
no. |
3.80 |
399.00 |
|
Sand - Local - Mymensingh |
7.560 |
cft |
13.00 |
98.28 |
|
Polythene |
0.360 |
kg |
77.00 |
27.72 |
|
Cement |
9.480 |
bag |
343.00 |
3251.64 |
|
Sand - Sylhet |
12.000 |
cft |
24.00 |
288.00 |
|
Stone-chips |
35.790 |
cft |
80.00 |
2863.20 |
|
GI Wire |
0.670 |
kg |
90.00 |
60.30 |
|
Re-bar G60 |
95.830 |
kg |
40.20 |
3852.37 |
|
|
Sub-Total(A1) |
10840.51
|
10840.51
|
B1.Plumbing/Sanitr Pipe |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
CI Cover 300 mm dia |
1.000 |
no. |
750.00 |
750.00 |
|
|
Sub-Total(B1) |
750.00
|
750.00
|
C1.Steel Structures |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Galvanized Angle 38x38 |
1.720 |
rft |
125.00 |
215.00 |
|
MS Grating 200x75 |
1.000 |
no. |
100.00 |
100.00 |
|
|
Sub-Total(C1) |
315.00
|
315.00
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Re-bar Work |
91.270 |
kg |
1.65 |
150.60 |
|
Formwork upto 10ft from P |
107.490 |
sft |
8.00 |
859.92 |
|
Dismentling F/W/Mar tile |
32.280 |
sft |
10.00 |
322.80 |
|
Neat Cement Finishing |
32.280 |
sft |
1.00 |
32.28 |
|
RCC Casting. |
40.980 |
cft |
8.00 |
327.84 |
|
|
Sub-Total(L0) |
1693.44
|
1693.44
|
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Earth Work in Excavation |
166.320 |
cft |
1.80 |
299.38 |
|
Filling |
84.900 |
cft |
1.00 |
84.90 |
|
Brck flat soling |
34.870 |
sft |
0.60 |
20.92 |
|
Patent stone with NCF |
8.070 |
sft |
3.00 |
24.21 |
|
|
Sub-Total(L1) |
429.41
|
429.41
|
L4.Labour-Sanitary |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Manhole Cover fixing |
1.000 |
no. |
300.00 |
300.00 |
|
|
Sub-Total(L4) |
300.00
|
300.00
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Forms |
107.490 |
sft |
5.00 |
537.45 |
|
|
Sub-Total(M1) |
537.45
|
537.45
|
|
|
|
Total(1) |
|
14865.80 |
|
Add over head on Total(1)
|
3.0 % |
445.97 |
|
|
|
Total(2) |
|
15311.77 |
|
Add Profit on Total(2) |
8.0 % |
1224.94
|
|
|
|
Total(3) |
|
16536.72 |
|
Add VAT on Unit Price |
4.5 % |
779.22 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
17315.93
|
|
|
|
Say |
|
Item: 13A (B01A) uPVC Pipe - 150mm dia |
|
Basis:319
rft |
B1.Plumbing/Sanitr Pipe |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
uPVC Pipe 150 dia |
328.280 |
rft |
115.00 |
37752.20 |
|
uPVC Bend 150mm dia |
3.000 |
no. |
560.00 |
1680.00 |
|
uPVC Tee - 150mm dia |
21.000 |
no |
950.00 |
19950.00 |
|
uPVC End Cap -150 dia |
2.000 |
no |
920.00 |
1840.00 |
|
Clamp |
73.000 |
no |
35.00 |
2555.00 |
|
Standing Urinal |
1.000 |
no |
150.00 |
150.00 |
|
Hole making (150 dia) |
21.000 |
no |
350.00 |
7350.00 |
|
S-cement tube |
5.000 |
no |
190.00 |
950.00 |
|
Solvent cement -500 ml |
2.000 |
pot |
490.00 |
980.00 |
|
|
Sub-Total(B1) |
73207.20
|
537.45
|
L4.Labour-Sanitary |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
uPVC Pipe Fitting -150mm |
318.720 |
rft |
20.00 |
6374.40 |
|
|
Sub-Total(L4) |
6374.40
|
537.45
|
|
|
|
Total(1) |
|
1074.90 |
|
Add over head on Total(1)
|
3.0 % |
32.25 |
|
|
|
Total(2) |
|
1107.15 |
|
Add Profit on Total(2) |
8.0 % |
88.57
|
|
|
|
Total(3) |
|
1195.72 |
|
Add VAT on Unit Price |
4.5 % |
56.34 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
1252.06
|
|
|
|
Say |
|
Item: 13B (B01A1) uPVC Pipe -150mm Dia Ex Pipe |
|
Basis:1
rft |
L4.Labour-Sanitary |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
uPVC Pipe Fitting -150mm |
1.000 |
rft |
20.00 |
20.00 |
|
|
Sub-Total(L4) |
20.00
|
537.45
|
|
|
|
Total(1) |
|
537.45 |
|
Add over head on Total(1)
|
3.0 % |
16.12 |
|
|
|
Total(2) |
|
553.57 |
|
Add Profit on Total(2) |
8.0 % |
44.29
|
|
|
|
Total(3) |
|
597.86 |
|
Add VAT on Unit Price |
4.5 % |
28.17 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
626.03
|
|
|
|
Say |
|
Item: 16 (C15) H.C.I grating-1000x300x40mm |
|
Basis:1
no. |
C1.Steel Structures |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
CI Grating |
71.200 |
kg |
42.00 |
2990.40 |
|
Galvanized Angle 38x38 |
6.890 |
rft |
125.00 |
861.25 |
|
|
Sub-Total(C1) |
3851.65
|
3851.65
|
L5.Labour-MS Work |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
CI Grating (1000x300) fix |
1.000 |
no. |
800.00 |
800.00 |
|
|
Sub-Total(L5) |
800.00
|
800.00
|
|
|
|
Total(1) |
|
4651.65 |
|
Add over head on Total(1)
|
3.0 % |
139.55 |
|
|
|
Total(2) |
|
4791.20 |
|
Add Profit on Total(2) |
8.0 % |
383.30
|
|
|
|
Total(3) |
|
5174.50 |
|
Add VAT on Unit Price |
4.5 % |
243.82 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
5418.32
|
|
|
|
Say |
|
Item: 18 (F000) 150mm RCC Pipe |
|
Basis:1
rft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Brick |
3.000 |
no. |
3.80 |
11.40 |
|
Sand - Local - Mymensingh |
0.540 |
cft |
13.00 |
7.02 |
|
Cement |
0.216 |
bag |
343.00 |
74.09 |
|
Brick-chips |
1.080 |
cft |
40.00 |
43.20 |
|
|
Sub-Total(A1) |
135.71
|
800.00
|
B1.Plumbing/Sanitr Pipe |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
RCC Pipe 6" dia |
1.050 |
rft |
66.00 |
69.30 |
|
150mm dia Socket |
0.250 |
no. |
50.00 |
12.50 |
|
|
Sub-Total(B1) |
81.80
|
800.00
|
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Earth Work in Excavation |
2.640 |
cft |
1.80 |
4.75 |
|
Brck flat soling |
1.000 |
sft |
0.60 |
0.60 |
|
CC Work |
1.200 |
cft |
5.00 |
6.00 |
|
150mm dia RCC Pipe |
1.000 |
rft |
20.00 |
20.00 |
|
|
Sub-Total(L1) |
31.35
|
800.00
|
|
|
|
Total(1) |
|
2400.00 |
|
Add over head on Total(1)
|
3.0 % |
72.00 |
|
|
|
Total(2) |
|
2472.00 |
|
Add Profit on Total(2) |
8.0 % |
197.76
|
|
|
|
Total(3) |
|
2669.76 |
|
Add VAT on Unit Price |
4.5 % |
125.80 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
2795.56
|
|
|
|
Say |
|
Item: 11A (F001) 225 mm dia Rcc pipe(Capital) |
|
Basis:1
rft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Brick |
3.000 |
no. |
3.80 |
11.40 |
|
Sand - Local - Mymensingh |
0.040 |
cft |
13.00 |
0.52 |
|
Cement |
0.030 |
bag |
343.00 |
10.29 |
|
Brick-chips |
0.080 |
cft |
40.00 |
3.20 |
|
|
Sub-Total(A1) |
25.41
|
800.00
|
B1.Plumbing/Sanitr Pipe |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
RCC Pipe 9" dia |
1.050 |
rft |
108.00 |
113.40 |
|
|
Sub-Total(B1) |
113.40
|
800.00
|
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Earth Work in Excavation |
2.650 |
cft |
1.80 |
4.77 |
|
Brck flat soling |
1.000 |
sft |
0.60 |
0.60 |
|
CC Work |
0.135 |
cft |
5.00 |
0.68 |
|
225mm dia RCC pipe |
1.000 |
rft |
25.00 |
25.00 |
|
|
Sub-Total(L1) |
31.05
|
800.00
|
|
|
|
Total(1) |
|
2400.00 |
|
Add over head on Total(1)
|
3.0 % |
72.00 |
|
|
|
Total(2) |
|
2472.00 |
|
Add Profit on Total(2) |
8.0 % |
197.76
|
|
|
|
Total(3) |
|
2669.76 |
|
Add VAT on Unit Price |
4.5 % |
125.80 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
2795.56
|
|
|
|
Say |
|
Item: 11B (F002) 300 mm dia Rcc pipe (Capital) |
|
Basis:1
rft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Brick |
4.000 |
no. |
3.80 |
15.20 |
|
Sand - Local - Mymensingh |
0.050 |
cft |
13.00 |
0.65 |
|
Cement |
0.030 |
bag |
343.00 |
10.29 |
|
Brick-chips |
0.120 |
cft |
40.00 |
4.80 |
|
|
Sub-Total(A1) |
30.94
|
800.00
|
B1.Plumbing/Sanitr Pipe |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
RCC Pipe 12" dia |
1.050 |
rft |
210.00 |
220.50 |
|
|
Sub-Total(B1) |
220.50
|
800.00
|
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Earth Work in Excavation |
3.530 |
cft |
1.80 |
6.35 |
|
Brck flat soling |
1.330 |
sft |
0.60 |
0.80 |
|
CC Work |
0.200 |
cft |
5.00 |
1.00 |
|
300mm dia RCC pipe |
1.000 |
rft |
33.00 |
33.00 |
|
|
Sub-Total(L1) |
41.15
|
800.00
|
|
|
|
Total(1) |
|
2400.00 |
|
Add over head on Total(1)
|
3.0 % |
72.00 |
|
|
|
Total(2) |
|
2472.00 |
|
Add Profit on Total(2) |
8.0 % |
197.76
|
|
|
|
Total(3) |
|
2669.76 |
|
Add VAT on Unit Price |
4.5 % |
125.80 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
2795.56
|
|
|
|
Say |
|
Item: 11C (F003) 450 mm dia Rcc pipe (Capital) |
|
Basis:1
rft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Brick |
6.000 |
no. |
3.80 |
22.80 |
|
Sand - Local - Mymensingh |
0.080 |
cft |
13.00 |
1.04 |
|
Cement |
0.045 |
bag |
343.00 |
15.44 |
|
Brick-chips |
0.200 |
cft |
40.00 |
8.00 |
|
|
Sub-Total(A1) |
47.28
|
800.00
|
B1.Plumbing/Sanitr Pipe |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
RCC Pipe 18" dia |
1.050 |
rft |
300.00 |
315.00 |
|
|
Sub-Total(B1) |
315.00
|
800.00
|
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Earth Work in Excavation |
5.300 |
cft |
1.80 |
9.54 |
|
Brck flat soling |
2.000 |
sft |
0.60 |
1.20 |
|
CC Work |
0.300 |
cft |
5.00 |
1.50 |
|
450mm dia RCC pipe |
1.000 |
rft |
50.00 |
50.00 |
|
|
Sub-Total(L1) |
62.24
|
800.00
|
|
|
|
Total(1) |
|
2400.00 |
|
Add over head on Total(1)
|
3.0 % |
72.00 |
|
|
|
Total(2) |
|
2472.00 |
|
Add Profit on Total(2) |
8.0 % |
197.76
|
|
|
|
Total(3) |
|
2669.76 |
|
Add VAT on Unit Price |
4.5 % |
125.80 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
2795.56
|
|
|
|
Say |
|
Item: 11D (F004) 600 mm dia Rcc pipe (Capital) |
|
Basis:1
rft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Brick |
8.000 |
no. |
3.80 |
30.40 |
|
Sand - Local - Mymensingh |
0.120 |
cft |
13.00 |
1.56 |
|
Cement |
0.060 |
bag |
343.00 |
20.58 |
|
Brick-chips |
0.220 |
cft |
40.00 |
8.80 |
|
|
Sub-Total(A1) |
61.34
|
800.00
|
B1.Plumbing/Sanitr Pipe |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
RCC Pipe 24" dia |
1.050 |
rft |
498.00 |
522.90 |
|
|
Sub-Total(B1) |
522.90
|
800.00
|
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Earth Work in Excavation |
7.067 |
cft |
1.80 |
12.72 |
|
Brck flat soling |
2.670 |
sft |
0.60 |
1.60 |
|
CC Work |
0.400 |
cft |
5.00 |
2.00 |
|
600mm dia RCC pipe |
1.000 |
rft |
67.00 |
67.00 |
|
|
Sub-Total(L1) |
83.32
|
800.00
|
|
|
|
Total(1) |
|
2400.00 |
|
Add over head on Total(1)
|
3.0 % |
72.00 |
|
|
|
Total(2) |
|
2472.00 |
|
Add Profit on Total(2) |
8.0 % |
197.76
|
|
|
|
Total(3) |
|
2669.76 |
|
Add VAT on Unit Price |
4.5 % |
125.80 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
2795.56
|
|
|
|
Say |
|
Item: 12A (F006) 225mm dia Rcc pipe (Capital-RC) |
|
Basis:1
rft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Brick |
3.000 |
no. |
3.80 |
11.40 |
|
Sand - Local - Mymensingh |
0.350 |
cft |
13.00 |
4.55 |
|
Polythene |
0.065 |
kg |
77.00 |
5.01 |
|
Cement |
0.200 |
bag |
343.00 |
68.60 |
|
Brick-chips |
0.700 |
cft |
40.00 |
28.00 |
|
|
Sub-Total(A1) |
117.56
|
800.00
|
B1.Plumbing/Sanitr Pipe |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
RCC Pipe 9" dia |
1.050 |
rft |
108.00 |
113.40 |
|
|
Sub-Total(B1) |
113.40
|
800.00
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mixer m/c and vibrator |
1.200 |
cft |
2.00 |
2.40 |
|
|
Sub-Total(E1) |
2.40
|
800.00
|
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Earth Work in Excavation |
2.380 |
cft |
1.80 |
4.28 |
|
Brck flat soling |
1.000 |
sft |
0.60 |
0.60 |
|
CC Work |
1.200 |
cft |
5.00 |
6.00 |
|
225mm dia RCC pipe |
1.000 |
rft |
25.00 |
25.00 |
|
|
Sub-Total(L1) |
35.88
|
800.00
|
|
|
|
Total(1) |
|
3200.00 |
|
Add over head on Total(1)
|
3.0 % |
96.00 |
|
|
|
Total(2) |
|
3296.00 |
|
Add Profit on Total(2) |
8.0 % |
263.68
|
|
|
|
Total(3) |
|
3559.68 |
|
Add VAT on Unit Price |
4.5 % |
167.73 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
3727.41
|
|
|
|
Say |
|
Item: 12B (F007) 300mm dia Rcc pipe (Capital-RC) |
|
Basis:1
rft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Brick |
4.000 |
no. |
3.80 |
15.20 |
|
Sand - Local - Mymensingh |
0.500 |
cft |
13.00 |
6.50 |
|
Polythene |
0.080 |
kg |
77.00 |
6.16 |
|
Cement |
0.250 |
bag |
343.00 |
85.75 |
|
Brick-chips |
0.900 |
cft |
40.00 |
36.00 |
|
|
Sub-Total(A1) |
149.61
|
800.00
|
B1.Plumbing/Sanitr Pipe |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
RCC Pipe 12" dia |
1.050 |
rft |
210.00 |
220.50 |
|
|
Sub-Total(B1) |
220.50
|
800.00
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mixer m/c and vibrator |
1.500 |
cft |
2.00 |
3.00 |
|
|
Sub-Total(E1) |
3.00
|
800.00
|
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Earth Work in Excavation |
3.170 |
cft |
1.80 |
5.71 |
|
Brck flat soling |
1.330 |
sft |
0.60 |
0.80 |
|
CC Work |
1.500 |
cft |
5.00 |
7.50 |
|
300mm dia RCC pipe |
1.000 |
rft |
33.00 |
33.00 |
|
|
Sub-Total(L1) |
47.00
|
800.00
|
|
|
|
Total(1) |
|
3200.00 |
|
Add over head on Total(1)
|
3.0 % |
96.00 |
|
|
|
Total(2) |
|
3296.00 |
|
Add Profit on Total(2) |
8.0 % |
263.68
|
|
|
|
Total(3) |
|
3559.68 |
|
Add VAT on Unit Price |
4.5 % |
167.73 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
3727.41
|
|
|
|
Say |
|
Item: 12C (F008) 450mm dia Rcc pipe (Capital-RC) |
|
Basis:1
rft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Brick |
6.000 |
no. |
3.80 |
22.80 |
|
Sand - Local - Mymensingh |
0.660 |
cft |
13.00 |
8.58 |
|
Polythene |
0.120 |
kg |
77.00 |
9.24 |
|
Cement |
0.350 |
bag |
343.00 |
120.05 |
|
Brick-chips |
1.300 |
cft |
40.00 |
52.00 |
|
|
Sub-Total(A1) |
212.67
|
800.00
|
B1.Plumbing/Sanitr Pipe |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
RCC Pipe 18" dia |
1.050 |
rft |
300.00 |
315.00 |
|
|
Sub-Total(B1) |
315.00
|
800.00
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mixer m/c and vibrator |
2.300 |
cft |
2.00 |
4.60 |
|
|
Sub-Total(E1) |
4.60
|
800.00
|
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Earth Work in Excavation |
4.760 |
cft |
1.80 |
8.57 |
|
Brck flat soling |
2.000 |
sft |
0.60 |
1.20 |
|
CC Work |
2.300 |
cft |
5.00 |
11.50 |
|
450mm dia RCC pipe |
1.000 |
rft |
50.00 |
50.00 |
|
|
Sub-Total(L1) |
71.27
|
800.00
|
|
|
|
Total(1) |
|
3200.00 |
|
Add over head on Total(1)
|
3.0 % |
96.00 |
|
|
|
Total(2) |
|
3296.00 |
|
Add Profit on Total(2) |
8.0 % |
263.68
|
|
|
|
Total(3) |
|
3559.68 |
|
Add VAT on Unit Price |
4.5 % |
167.73 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
3727.41
|
|
|
|
Say |
|
Item: 12D (F009) 600mm dia Rcc pipe (Capital-RC) |
|
Basis:1
rft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Brick |
8.000 |
no. |
3.80 |
30.40 |
|
Sand - Local - Mymensingh |
0.900 |
cft |
13.00 |
11.70 |
|
Polythene |
0.160 |
kg |
77.00 |
12.32 |
|
Cement |
0.500 |
bag |
343.00 |
171.50 |
|
Brick-chips |
1.800 |
cft |
40.00 |
72.00 |
|
|
Sub-Total(A1) |
297.92
|
800.00
|
B1.Plumbing/Sanitr Pipe |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
RCC Pipe 24" dia |
1.050 |
rft |
498.00 |
522.90 |
|
|
Sub-Total(B1) |
522.90
|
800.00
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mixer m/c and vibrator |
3.100 |
cft |
2.00 |
6.20 |
|
|
Sub-Total(E1) |
6.20
|
800.00
|
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Earth Work in Excavation |
6.350 |
cft |
1.80 |
11.43 |
|
Brck flat soling |
2.670 |
sft |
0.60 |
1.60 |
|
CC Work |
3.100 |
cft |
5.00 |
15.50 |
|
600mm dia RCC pipe |
1.000 |
rft |
67.00 |
67.00 |
|
|
Sub-Total(L1) |
95.53
|
800.00
|
|
|
|
Total(1) |
|
3200.00 |
|
Add over head on Total(1)
|
3.0 % |
96.00 |
|
|
|
Total(2) |
|
3296.00 |
|
Add Profit on Total(2) |
8.0 % |
263.68
|
|
|
|
Total(3) |
|
3559.68 |
|
Add VAT on Unit Price |
4.5 % |
167.73 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
3727.41
|
|
|
|
Say |
|