Return Main Menu

Project RCC Road for Rm+Pm and Fg ware house
Item: 02D (A01E) E/Cutting with Excavator
Basis:100 cft
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Excavator
0.005
day
8000.00
40.00
Wheel Loader-Road
0.002
day
10000.00
20.00
Dump Truck
0.007
day
8300.00
58.10
Sub-Total(E1)
118.10
41.71
Total(1)
41.71
Add over head on Total(1)
3.0 %
1.25
Total(2)
42.96
Add Profit on Total(2)
8.0 %
3.44
Total(3)
46.39
Add VAT on Unit Price
4.5 %
2.19
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
48.58
Say
49
per M3
Item: 04A (A02A) Brick Flat Soling- Road
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Filling Sand
5.000
cft
8.50
42.50
Brick
300.000
no.
3.80
1140.00
Sub-Total(A1)
1182.50
127.28
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
0.100
nos.
100.00
10.00
Head Mason Supply
0.250
nos.
200.00
50.00
Sub-Total(L0)
60.00
6.46
Total(1)
133.74
Add over head on Total(1)
3.0 %
4.01
Total(2)
137.75
Add Profit on Total(2)
8.0 %
11.02
Total(3)
148.78
Add VAT on Unit Price
4.5 %
7.01
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
155.79
Say
156
per M2
Item: 05 (A02F) Single layer polythene
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Polythene
1.500
kg
77.00
115.50
Sub-Total(A1)
115.50
12.43
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
0.020
nos.
100.00
2.00
Sub-Total(L0)
2.00
0.22
Total(1)
12.65
Add over head on Total(1)
3.0 %
0.38
Total(2)
13.03
Add Profit on Total(2)
8.0 %
1.04
Total(3)
14.07
Add VAT on Unit Price
4.5 %
0.66
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
14.73
Say
15
per M2
Item: 04B (A02G) BFS with existing brick
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Filling Sand
5.000
cft
8.50
42.50
Sub-Total(A1)
42.50
4.57
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
0.400
nos.
100.00
40.00
Head Mason Supply
0.250
nos.
200.00
50.00
Sub-Total(L0)
90.00
9.69
Total(1)
14.26
Add over head on Total(1)
3.0 %
0.43
Total(2)
14.69
Add Profit on Total(2)
8.0 %
1.18
Total(3)
15.87
Add VAT on Unit Price
4.5 %
0.75
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
16.61
Say
17
per M2
Item: 08 (A03J) 50mm thick C.C (1:2:4) with-4% Ad
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
2.500
cft
13.00
32.50
Cement
3.000
bag
343.00
1029.00
Sand - Sylhet
5.000
cft
24.00
120.00
Stone-chips
15.000
cft
80.00
1200.00
Pudloo
6.000
kg
70.00
420.00
Sub-Total(A1)
2801.50
301.55
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
16.700
cft
2.00
33.40
Sub-Total(E1)
33.40
3.60
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
CC Work
16.700
cft
5.00
83.50
Sub-Total(L1)
83.50
8.99
Total(1)
314.14
Add over head on Total(1)
3.0 %
9.42
Total(2)
323.56
Add Profit on Total(2)
8.0 %
25.88
Total(3)
349.45
Add VAT on Unit Price
4.5 %
16.47
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
365.91
Say
366
per M2
Item: 02A (A05A) Sand filling bott of road-95%comp
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Filling Sand
130.000
cft
8.50
1105.00
Sub-Total(A1)
1105.00
390.23
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Roller hire ch. i/c fuel
0.050
day
6500.00
325.00
Wheel Loader-Road
0.010
day
10000.00
100.00
Gradder-Road
0.001
day
10000.00
10.00
Sub-Total(E1)
435.00
153.62
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
1.000
nos.
100.00
100.00
Sub-Total(L0)
100.00
35.32
Total(1)
579.17
Add over head on Total(1)
3.0 %
17.37
Total(2)
596.54
Add Profit on Total(2)
8.0 %
47.72
Total(3)
644.26
Add VAT on Unit Price
4.5 %
30.36
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
674.62
Say
675
per M3
Item: 02B (A05B) Sand filling foot path and other
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Filling Sand
130.000
cft
8.50
1105.00
Sub-Total(A1)
1105.00
390.23
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Wheel Loader-Road
0.015
day
10000.00
150.00
Sub-Total(E1)
150.00
52.97
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
1.250
nos.
100.00
125.00
Sub-Total(L0)
125.00
44.14
Total(1)
487.35
Add over head on Total(1)
3.0 %
14.62
Total(2)
501.97
Add Profit on Total(2)
8.0 %
40.16
Total(3)
542.12
Add VAT on Unit Price
4.5 %
25.55
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
567.67
Say
568
per M3
Item: 03 (A05C) 400mm thick Sub-base (40:60)
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Filling Sand
52.000
cft
8.50
442.00
Brick
819.000
no.
3.80
3112.20
Sub-Total(A1)
3554.20
1255.17
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Roller hire ch. i/c fuel
0.140
day
6500.00
910.00
Wheel Loader-Road
0.002
day
10000.00
20.00
Sub-Total(E1)
930.00
328.43
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
2.000
nos.
100.00
200.00
Brick-chips making 1 1/2"
819.000
no.
0.33
270.27
Sub-Total(L0)
470.27
166.08
Total(1)
1749.67
Add over head on Total(1)
3.0 %
52.49
Total(2)
1802.16
Add Profit on Total(2)
8.0 %
144.17
Total(3)
1946.33
Add VAT on Unit Price
4.5 %
91.71
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
2038.05
Say
2038
per M3
Item: 02C (A05E) Back Filling With Roller
Basis:100 cft
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Roller hire ch. i/c fuel
0.050
day
6500.00
325.00
Wheel Loader-Road
0.010
day
10000.00
100.00
Gradder-Road
0.001
day
10000.00
10.00
Sub-Total(E1)
435.00
153.62
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
1.000
nos.
100.00
100.00
Sub-Total(L0)
100.00
35.32
Total(1)
188.94
Add over head on Total(1)
3.0 %
5.67
Total(2)
194.60
Add Profit on Total(2)
8.0 %
15.57
Total(3)
210.17
Add VAT on Unit Price
4.5 %
9.90
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
220.07
Say
220
per M3
Item: 17 (A06E) Drain (Trench)-1000x11000mm
Basis:33 rft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Filling Sand
5.920
cft
8.50
50.32
Brick
1786.000
no.
3.80
6786.80
Sand - Local - Mymensingh
83.290
cft
13.00
1082.77
Polythene
1.700
kg
77.00
130.90
Cement
24.000
bag
343.00
8232.00
Sand - Sylhet
24.790
cft
24.00
594.96
Stone-chips
74.380
cft
80.00
5950.40
Re-bar G60
152.000
kg
40.20
6110.40
Sub-Total(A1)
28938.55
35.32
C1.Steel Structures
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS angle
47.570
kg
38.00
1807.66
M.S plate
14.860
kg
45.00
668.70
10 dia Rowel bolt
16.000
no
75.00
1200.00
Sub-Total(C1)
3676.36
35.32
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
67.980
cft
2.00
135.96
Sub-Total(E1)
135.96
35.32
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Formwork upto 10ft from P
37.670
sft
8.00
301.36
Dismentling F/W/Mar tile
134.550
sft
10.00
1345.50
Neat Cement Finishing
134.550
sft
1.00
134.55
RCC Casting.
67.980
cft
8.00
543.84
250mm Brickwork upto 7 ft
119.188
cft
4.25
506.55
Sub-Total(L0)
2831.80
35.32
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Earth Work in Excavation
423.780
cft
1.80
762.80
Filling
48.910
cft
1.00
48.91
Brck flat soling
118.404
sft
0.60
71.04
Patent stone with NCF
64.584
sft
3.00
193.75
Sub-Total(L1)
1076.51
35.32
L4.Labour-Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Drain Cover Slab Fixing
32.810
rft
20.00
656.20
Sub-Total(L4)
656.20
35.32
L5.Labour-MS Work
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS angle fixing with plat
31.490
rft
5.00
157.45
Sub-Total(L5)
157.45
35.32
S1.Sub-contractor-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Painting to MS surface
28.410
sft
5.00
142.05
Sub-Total(S1)
142.05
35.32
Total(1)
282.52
Add over head on Total(1)
3.0 %
8.48
Total(2)
291.00
Add Profit on Total(2)
8.0 %
23.28
Total(3)
314.28
Add VAT on Unit Price
4.5 %
14.81
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
329.08
Say
329
per RM
Item: 09 (A07D) 300x300x25-degn terracotta pavers
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
13.880
cft
13.00
180.44
Cement
3.700
bag
343.00
1269.10
Sub-Total(A1)
1449.54
156.03
A2.Material-Mosaic/Tile
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
300x300x25 P-Tiles-CC
105.000
sft
49.61
5209.05
Sub-Total(A2)
5209.05
560.70
L2.Labour-Tile/Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Paving Tiles Fitting
100.000
sft
20.00
2000.00
Sub-Total(L2)
2000.00
215.28
Total(1)
932.01
Add over head on Total(1)
3.0 %
27.96
Total(2)
959.97
Add Profit on Total(2)
8.0 %
76.80
Total(3)
1036.77
Add VAT on Unit Price
4.5 %
48.85
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
1085.62
Say
1086
per SQM
Item: 07B (A08N) Precast Kerb(1:1.5:3) Ex Rebar
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
13.750
cft
13.00
178.75
Cement
22.000
bag
343.00
7546.00
Sand - Sylhet
27.500
cft
24.00
660.00
Stone-chips
90.000
cft
80.00
7200.00
Sub-Total(A1)
15584.75
5503.75
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
100.000
cft
2.00
200.00
Sub-Total(E1)
200.00
70.63
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Formwork upto 10ft from P
200.000
sft
8.00
1600.00
Ordinary Labour Supply
10.000
nos.
100.00
1000.00
Head Mason Supply
5.000
nos.
200.00
1000.00
Sub-Total(L0)
3600.00
1271.34
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Forms
200.000
sft
5.00
1000.00
Sub-Total(M1)
1000.00
353.15
Total(1)
7198.87
Add over head on Total(1)
3.0 %
215.97
Total(2)
7414.84
Add Profit on Total(2)
8.0 %
593.19
Total(3)
8008.03
Add VAT on Unit Price
4.5 %
377.34
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
8385.37
Say
8385
per M3
Item: 06C (A08Q) RCC (1:2:4) as Cast Kerb ex Rebar
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
15.000
cft
13.00
195.00
Cement
18.000
bag
343.00
6174.00
Sand - Sylhet
30.000
cft
24.00
720.00
Stone-chips
90.000
cft
80.00
7200.00
Sub-Total(A1)
14289.00
5046.16
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
100.000
cft
2.00
200.00
Mini Dumper
100.000
cft
2.00
200.00
Sub-Total(E1)
400.00
141.26
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Formwork upto 10ft from P
650.000
sft
8.00
5200.00
RCC Casting.
100.000
cft
8.00
800.00
Sub-Total(L0)
6000.00
2118.90
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Forms
650.000
sft
5.00
3250.00
Sub-Total(M1)
3250.00
1147.74
Total(1)
8454.06
Add over head on Total(1)
3.0 %
253.62
Total(2)
8707.68
Add Profit on Total(2)
8.0 %
696.61
Total(3)
9404.29
Add VAT on Unit Price
4.5 %
443.13
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
9847.43
Say
9847
per M3
Item: 07A (A08S) Precast RCC(1:1.5:3)Kerb i/c Rebr
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
13.750
cft
13.00
178.75
Cement
22.000
bag
343.00
7546.00
Sand - Sylhet
27.500
cft
24.00
660.00
Stone-chips
90.000
cft
80.00
7200.00
GI Wire
2.330
kg
90.00
209.70
Re-bar G60
334.090
kg
40.20
13430.42
Sub-Total(A1)
29224.87
10320.76
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
100.000
cft
2.00
200.00
Sub-Total(E1)
200.00
70.63
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Re-bar Work
334.090
kg
1.65
551.25
Formwork upto 10ft from P
200.000
sft
8.00
1600.00
Ordinary Labour Supply
10.000
nos.
100.00
1000.00
Head Mason Supply
5.000
nos.
200.00
1000.00
Sub-Total(L0)
4151.25
1466.01
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Forms
200.000
sft
5.00
1000.00
Sub-Total(M1)
1000.00
353.15
Total(1)
12210.56
Add over head on Total(1)
3.0 %
366.32
Total(2)
12576.87
Add Profit on Total(2)
8.0 %
1006.15
Total(3)
13583.02
Add VAT on Unit Price
4.5 %
640.04
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
14223.06
Say
14223
per M3
Item: 06B (A08T) RCC(1:2:4) As Cast Kerb i/c Rebar
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
15.000
cft
13.00
195.00
Cement
18.000
bag
343.00
6174.00
Sand - Sylhet
30.000
cft
24.00
720.00
Stone-chips
90.000
cft
80.00
7200.00
GI Wire
1.560
kg
90.00
140.40
Re-bar G60
222.730
kg
40.20
8953.75
Sub-Total(A1)
23383.15
8257.76
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
100.000
cft
2.00
200.00
Mini Dumper
100.000
cft
2.00
200.00
Sub-Total(E1)
400.00
141.26
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Re-bar Work
222.730
kg
1.65
367.50
Formwork upto 10ft from P
650.000
sft
8.00
5200.00
RCC Casting.
100.000
cft
8.00
800.00
Sub-Total(L0)
6367.50
2248.68
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Forms
650.000
sft
5.00
3250.00
Sub-Total(M1)
3250.00
1147.74
Total(1)
11795.44
Add over head on Total(1)
3.0 %
353.86
Total(2)
12149.30
Add Profit on Total(2)
8.0 %
971.94
Total(3)
13121.25
Add VAT on Unit Price
4.5 %
618.28
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
13739.53
Say
13740
per M3
Item: 06A (A08U) Rcc Road, drain and parking-1:2:4
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
15.000
cft
13.00
195.00
Cement
18.000
bag
343.00
6174.00
Sand - Sylhet
30.000
cft
24.00
720.00
Stone-chips
90.000
cft
80.00
7200.00
Dowel Bar-20mm plain
13.200
kg
40.00
528.00
Rubber bush
9.700
no
22.00
213.40
Sub-Total(A1)
15030.40
5307.99
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
100.000
cft
2.00
200.00
Mini Dumper
100.000
cft
2.00
200.00
Sub-Total(E1)
400.00
141.26
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Formwork upto 10ft from P
8.000
sft
8.00
64.00
Ordinary Labour Supply
0.065
nos.
100.00
6.50
Head Mason Supply
0.150
nos.
200.00
30.00
RCC Casting.
100.000
cft
8.00
800.00
Sub-Total(L0)
900.50
318.01
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Wood shutter-3time
0.025
cft
350.00
8.75
Cork Sheet-12mm
20.000
sft
3.50
70.00
Sub-Total(M1)
78.75
27.81
Total(1)
5795.07
Add over head on Total(1)
3.0 %
173.85
Total(2)
5968.92
Add Profit on Total(2)
8.0 %
477.51
Total(3)
6446.43
Add VAT on Unit Price
4.5 %
303.76
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
6750.19
Say
6750
per M3
Item: 15 (A08V) Septic tank (5.5x2.5x2.25M)-out-o
Basis:1 no.
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Filling Sand
1009.290
cft
8.50
8578.97
Brick
520.000
no.
3.80
1976.00
Sand - Local - Mymensingh
115.000
cft
13.00
1495.00
Polythene
7.000
kg
77.00
539.00
Cement
100.000
bag
343.00
34300.00
Sand - Sylhet
160.000
cft
24.00
3840.00
GI Wire
10.500
kg
90.00
945.00
Re-bar G60
1560.000
kg
40.20
62712.00
Bitumens
21.450
kg
30.00
643.50
Sub-Total(A1)
115029.47
115029.47
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
CI Cover -450MM DIA
5.000
no.
2500.00
12500.00
Sub-Total(B1)
12500.00
12500.00
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Re-bar Work
1485.500
kg
1.65
2451.08
Formwork upto 10ft from P
1246.000
sft
8.00
9968.00
Dismentling F/W/Mar tile
667.370
sft
10.00
6673.70
Neat Cement Finishing
667.370
sft
1.00
667.37
RCC Casting.
443.450
cft
8.00
3547.60
Sub-Total(L0)
23307.75
23307.75
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Filling
869.010
cft
1.00
869.01
Brck flat soling
182.988
sft
0.60
109.79
Patent stone with NCF
156.074
sft
3.00
468.22
Bitumen painting
430.560
sft
1.00
430.56
Sub-Total(L1)
1877.58
1877.58
L4.Labour-Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Manhole Cover fixing
5.000
no.
300.00
1500.00
Sub-Total(L4)
1500.00
1500.00
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Forms
1246.000
sft
5.00
6230.00
Shoring for Excavation
711.000
sft
2.15
1528.65
Sub-Total(M1)
7758.65
7758.65
Total(1)
161973.44
Add over head on Total(1)
3.0 %
4859.20
Total(2)
166832.65
Add Profit on Total(2)
8.0 %
13346.61
Total(3)
180179.26
Add VAT on Unit Price
4.5 %
8490.12
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
188669.38
Say
188669
per NO
Item: 10 (A10A) Re-bar Grade 60
Basis:1000 kg.
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
GI Wire
10.000
kg
90.00
900.00
Re-bar G60
1050.000
kg
40.20
42210.00
Sub-Total(A1)
43110.00
7758.65
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Re-bar Work
1000.000
kg
1.65
1650.00
Local carrying Rod
0.000
kg
0.25
0.00
Sub-Total(L0)
1650.00
7758.65
Total(1)
15517.30
Add over head on Total(1)
3.0 %
465.52
Total(2)
15982.82
Add Profit on Total(2)
8.0 %
1278.63
Total(3)
17261.44
Add VAT on Unit Price
4.5 %
813.37
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
18074.81
Say
18075
per TON
Item: 01 (A18I) Dismantling CC, BFS, HBB
Basis:100 sft
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
1.500
nos.
100.00
150.00
Sub-Total(L0)
150.00
16.15
Total(1)
16.15
Add over head on Total(1)
3.0 %
0.48
Total(2)
16.63
Add Profit on Total(2)
8.0 %
1.33
Total(3)
17.96
Add VAT on Unit Price
4.5 %
0.85
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
18.81
Say
19
per M2
Item: 14A (A22A) Ins. pit A type 500x500-in-in
Basis:1 no.
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
21.000
no.
3.80
79.80
Sand - Local - Mymensingh
2.520
cft
13.00
32.76
Polythene
0.120
kg
77.00
9.24
Cement
3.160
bag
343.00
1083.88
Sand - Sylhet
4.000
cft
24.00
96.00
Stone-chips
11.930
cft
80.00
954.40
Re-bar - G40
31.940
kg
38.50
1229.69
GI Wire
0.220
kg
90.00
19.80
Sub-Total(A1)
3505.57
3505.57
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
CI Cover 300 mm dia
1.000
no.
750.00
750.00
Sub-Total(B1)
750.00
750.00
C1.Steel Structures
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Galvanized Angle 38x38
1.720
rft
125.00
215.00
MS Grating 200x75
1.000
no.
100.00
100.00
Sub-Total(C1)
315.00
315.00
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Re-bar Work
30.420
kg
1.65
50.19
Formwork upto 10ft from P
35.830
sft
8.00
286.64
Dismentling F/W/Mar tile
10.760
sft
10.00
107.60
Neat Cement Finishing
10.760
sft
1.00
10.76
RCC Casting.
13.660
cft
8.00
109.28
Sub-Total(L0)
564.47
564.47
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Earth Work in Excavation
55.440
cft
1.80
99.79
Filling
28.300
cft
1.00
28.30
Brck flat soling
6.880
sft
0.60
4.13
Patent stone with NCF
2.690
sft
3.00
8.07
Sub-Total(L1)
140.29
140.29
L4.Labour-Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Manhole Cover fixing
1.000
no.
300.00
300.00
Sub-Total(L4)
300.00
300.00
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Forms
35.830
sft
5.00
179.15
Sub-Total(M1)
179.15
179.15
Total(1)
5754.48
Add over head on Total(1)
3.0 %
172.63
Total(2)
5927.12
Add Profit on Total(2)
8.0 %
474.17
Total(3)
6401.29
Add VAT on Unit Price
4.5 %
301.63
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
6702.92
Say
6703
per NO
Item: 14B (A22B) Ins. pit B type 750x750-in-in
Basis:1 no.
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
32.000
no.
3.80
121.60
Sand - Local - Mymensingh
3.780
cft
13.00
49.14
Polythene
0.180
kg
77.00
13.86
Cement
4.740
bag
343.00
1625.82
Sand - Sylhet
6.000
cft
24.00
144.00
Stone-chips
17.900
cft
80.00
1432.00
Re-bar - G40
48.300
kg
38.50
1859.55
GI Wire
0.330
kg
90.00
29.70
Sub-Total(A1)
5275.67
5275.67
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
CI Cover 300 mm dia
1.000
no.
750.00
750.00
Sub-Total(B1)
750.00
750.00
C1.Steel Structures
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Galvanized Angle 38x38
2.580
rft
125.00
322.50
MS Grating 200x75
1.000
no.
100.00
100.00
Sub-Total(C1)
422.50
422.50
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
20.490
cft
2.00
40.98
Sub-Total(E1)
40.98
40.98
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Re-bar Work
46.000
kg
1.65
75.90
Formwork upto 10ft from P
53.740
sft
8.00
429.92
Dismentling F/W/Mar tile
16.140
sft
10.00
161.40
Neat Cement Finishing
16.140
sft
1.00
16.14
RCC Casting.
20.490
cft
8.00
163.92
Sub-Total(L0)
847.28
847.28
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Earth Work in Excavation
83.160
cft
1.80
149.69
Filling
42.450
cft
1.00
42.45
Brck flat soling
11.860
sft
0.60
7.12
Patent stone with NCF
4.035
sft
3.00
12.11
Sub-Total(L1)
211.36
211.36
L4.Labour-Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Manhole Cover fixing
1.000
no.
300.00
300.00
Sub-Total(L4)
300.00
300.00
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Forms
53.740
sft
5.00
268.70
Sub-Total(M1)
268.70
268.70
Total(1)
8116.49
Add over head on Total(1)
3.0 %
243.49
Total(2)
8359.98
Add Profit on Total(2)
8.0 %
668.80
Total(3)
9028.78
Add VAT on Unit Price
4.5 %
425.44
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
9454.22
Say
9454
per NO
Item: 14C (A22C) Ins. pit C type 1000x1000-in-in
Basis:1 no.
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
55.000
no.
3.80
209.00
Sand - Local - Mymensingh
5.040
cft
13.00
65.52
Polythene
0.240
kg
77.00
18.48
Cement
6.320
bag
343.00
2167.76
Sand - Sylhet
8.000
cft
24.00
192.00
Stone-chips
23.860
cft
80.00
1908.80
GI Wire
0.440
kg
90.00
39.60
Re-bar G60
63.880
kg
40.20
2567.98
Sub-Total(A1)
7169.14
7169.14
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
CI Cover 300 mm dia
1.000
no.
750.00
750.00
Sub-Total(B1)
750.00
750.00
C1.Steel Structures
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Galvanized Angle 38x38
1.720
rft
125.00
215.00
MS Grating 200x75
1.000
no.
100.00
100.00
Sub-Total(C1)
315.00
315.00
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Re-bar Work
60.840
kg
1.65
100.39
Formwork upto 10ft from P
71.660
sft
8.00
573.28
Dismentling F/W/Mar tile
21.520
sft
10.00
215.20
Neat Cement Finishing
21.520
sft
1.00
21.52
RCC Casting.
27.320
cft
8.00
218.56
Sub-Total(L0)
1128.95
1128.95
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Earth Work in Excavation
110.880
cft
1.80
199.58
Filling
56.600
cft
1.00
56.60
Brck flat soling
18.190
sft
0.60
10.91
Patent stone with NCF
5.380
sft
3.00
16.14
Sub-Total(L1)
283.24
283.24
L4.Labour-Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Manhole Cover fixing
1.000
no.
300.00
300.00
Sub-Total(L4)
300.00
300.00
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Forms
71.660
sft
5.00
358.30
Sub-Total(M1)
358.30
358.30
Total(1)
10304.62
Add over head on Total(1)
3.0 %
309.14
Total(2)
10613.76
Add Profit on Total(2)
8.0 %
849.10
Total(3)
11462.86
Add VAT on Unit Price
4.5 %
540.13
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
12002.99
Say
12003
per NO
Item: 14D (A22D) Ins. pit D type 1200x1200-in-in
Basis:1 no.
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
72.650
no.
3.80
276.07
Sand - Local - Mymensingh
6.040
cft
13.00
78.52
Polythene
0.350
kg
77.00
26.95
Cement
7.580
bag
343.00
2599.94
Sand - Sylhet
9.600
cft
24.00
230.40
Stone-chips
28.630
cft
80.00
2290.40
GI Wire
0.536
kg
90.00
48.24
Re-bar G60
76.660
kg
40.20
3081.73
Sub-Total(A1)
8632.25
8632.25
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
CI Cover 300 mm dia
1.000
no.
750.00
750.00
Sub-Total(B1)
750.00
750.00
C1.Steel Structures
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Galvanized Angle 38x38
1.720
rft
125.00
215.00
MS Grating 200x75
1.000
no.
100.00
100.00
Sub-Total(C1)
315.00
315.00
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
32.780
cft
2.00
65.56
Sub-Total(E1)
65.56
65.56
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Re-bar Work
73.010
kg
1.65
120.47
Formwork upto 10ft from P
86.000
sft
8.00
688.00
Dismentling F/W/Mar tile
25.820
sft
10.00
258.20
Neat Cement Finishing
25.820
sft
1.00
25.82
RCC Casting.
32.780
cft
8.00
262.24
Sub-Total(L0)
1354.73
1354.73
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Earth Work in Excavation
133.050
cft
1.80
239.49
Filling
67.920
cft
1.00
67.92
Patent stone with NCF
6.450
sft
3.00
19.35
Sub-Total(L1)
326.76
326.76
L4.Labour-Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Manhole Cover fixing
1.000
no.
300.00
300.00
Sub-Total(L4)
300.00
300.00
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Forms
86.000
sft
5.00
430.00
Sub-Total(M1)
430.00
430.00
Total(1)
12174.30
Add over head on Total(1)
3.0 %
365.23
Total(2)
12539.53
Add Profit on Total(2)
8.0 %
1003.16
Total(3)
13542.69
Add VAT on Unit Price
4.5 %
638.14
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
14180.83
Say
14181
per NO
Item: 14E (A22E) Ins. pit E type 1500x1500-in-in
Basis:1 no.
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
105.000
no.
3.80
399.00
Sand - Local - Mymensingh
7.560
cft
13.00
98.28
Polythene
0.360
kg
77.00
27.72
Cement
9.480
bag
343.00
3251.64
Sand - Sylhet
12.000
cft
24.00
288.00
Stone-chips
35.790
cft
80.00
2863.20
GI Wire
0.670
kg
90.00
60.30
Re-bar G60
95.830
kg
40.20
3852.37
Sub-Total(A1)
10840.51
10840.51
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
CI Cover 300 mm dia
1.000
no.
750.00
750.00
Sub-Total(B1)
750.00
750.00
C1.Steel Structures
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Galvanized Angle 38x38
1.720
rft
125.00
215.00
MS Grating 200x75
1.000
no.
100.00
100.00
Sub-Total(C1)
315.00
315.00
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Re-bar Work
91.270
kg
1.65
150.60
Formwork upto 10ft from P
107.490
sft
8.00
859.92
Dismentling F/W/Mar tile
32.280
sft
10.00
322.80
Neat Cement Finishing
32.280
sft
1.00
32.28
RCC Casting.
40.980
cft
8.00
327.84
Sub-Total(L0)
1693.44
1693.44
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Earth Work in Excavation
166.320
cft
1.80
299.38
Filling
84.900
cft
1.00
84.90
Brck flat soling
34.870
sft
0.60
20.92
Patent stone with NCF
8.070
sft
3.00
24.21
Sub-Total(L1)
429.41
429.41
L4.Labour-Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Manhole Cover fixing
1.000
no.
300.00
300.00
Sub-Total(L4)
300.00
300.00
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Forms
107.490
sft
5.00
537.45
Sub-Total(M1)
537.45
537.45
Total(1)
14865.80
Add over head on Total(1)
3.0 %
445.97
Total(2)
15311.77
Add Profit on Total(2)
8.0 %
1224.94
Total(3)
16536.72
Add VAT on Unit Price
4.5 %
779.22
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
17315.93
Say
17316
per NO
Item: 13A (B01A) uPVC Pipe - 150mm dia
Basis:319 rft
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
uPVC Pipe 150 dia
328.280
rft
115.00
37752.20
uPVC Bend 150mm dia
3.000
no.
560.00
1680.00
uPVC Tee - 150mm dia
21.000
no
950.00
19950.00
uPVC End Cap -150 dia
2.000
no
920.00
1840.00
Clamp
73.000
no
35.00
2555.00
Standing Urinal
1.000
no
150.00
150.00
Hole making (150 dia)
21.000
no
350.00
7350.00
S-cement tube
5.000
no
190.00
950.00
Solvent cement -500 ml
2.000
pot
490.00
980.00
Sub-Total(B1)
73207.20
537.45
L4.Labour-Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
uPVC Pipe Fitting -150mm
318.720
rft
20.00
6374.40
Sub-Total(L4)
6374.40
537.45
Total(1)
1074.90
Add over head on Total(1)
3.0 %
32.25
Total(2)
1107.15
Add Profit on Total(2)
8.0 %
88.57
Total(3)
1195.72
Add VAT on Unit Price
4.5 %
56.34
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
1252.06
Say
1252
per RM
Item: 13B (B01A1) uPVC Pipe -150mm Dia Ex Pipe
Basis:1 rft
L4.Labour-Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
uPVC Pipe Fitting -150mm
1.000
rft
20.00
20.00
Sub-Total(L4)
20.00
537.45
Total(1)
537.45
Add over head on Total(1)
3.0 %
16.12
Total(2)
553.57
Add Profit on Total(2)
8.0 %
44.29
Total(3)
597.86
Add VAT on Unit Price
4.5 %
28.17
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
626.03
Say
626
per RM
Item: 16 (C15) H.C.I grating-1000x300x40mm
Basis:1 no.
C1.Steel Structures
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
CI Grating
71.200
kg
42.00
2990.40
Galvanized Angle 38x38
6.890
rft
125.00
861.25
Sub-Total(C1)
3851.65
3851.65
L5.Labour-MS Work
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
CI Grating (1000x300) fix
1.000
no.
800.00
800.00
Sub-Total(L5)
800.00
800.00
Total(1)
4651.65
Add over head on Total(1)
3.0 %
139.55
Total(2)
4791.20
Add Profit on Total(2)
8.0 %
383.30
Total(3)
5174.50
Add VAT on Unit Price
4.5 %
243.82
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
5418.32
Say
5418
per NO
Item: 18 (F000) 150mm RCC Pipe
Basis:1 rft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
3.000
no.
3.80
11.40
Sand - Local - Mymensingh
0.540
cft
13.00
7.02
Cement
0.216
bag
343.00
74.09
Brick-chips
1.080
cft
40.00
43.20
Sub-Total(A1)
135.71
800.00
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
RCC Pipe 6" dia
1.050
rft
66.00
69.30
150mm dia Socket
0.250
no.
50.00
12.50
Sub-Total(B1)
81.80
800.00
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Earth Work in Excavation
2.640
cft
1.80
4.75
Brck flat soling
1.000
sft
0.60
0.60
CC Work
1.200
cft
5.00
6.00
150mm dia RCC Pipe
1.000
rft
20.00
20.00
Sub-Total(L1)
31.35
800.00
Total(1)
2400.00
Add over head on Total(1)
3.0 %
72.00
Total(2)
2472.00
Add Profit on Total(2)
8.0 %
197.76
Total(3)
2669.76
Add VAT on Unit Price
4.5 %
125.80
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
2795.56
Say
2796
per RM
Item: 11A (F001) 225 mm dia Rcc pipe(Capital)
Basis:1 rft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
3.000
no.
3.80
11.40
Sand - Local - Mymensingh
0.040
cft
13.00
0.52
Cement
0.030
bag
343.00
10.29
Brick-chips
0.080
cft
40.00
3.20
Sub-Total(A1)
25.41
800.00
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
RCC Pipe 9" dia
1.050
rft
108.00
113.40
Sub-Total(B1)
113.40
800.00
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Earth Work in Excavation
2.650
cft
1.80
4.77
Brck flat soling
1.000
sft
0.60
0.60
CC Work
0.135
cft
5.00
0.68
225mm dia RCC pipe
1.000
rft
25.00
25.00
Sub-Total(L1)
31.05
800.00
Total(1)
2400.00
Add over head on Total(1)
3.0 %
72.00
Total(2)
2472.00
Add Profit on Total(2)
8.0 %
197.76
Total(3)
2669.76
Add VAT on Unit Price
4.5 %
125.80
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
2795.56
Say
2796
per RM
Item: 11B (F002) 300 mm dia Rcc pipe (Capital)
Basis:1 rft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
4.000
no.
3.80
15.20
Sand - Local - Mymensingh
0.050
cft
13.00
0.65
Cement
0.030
bag
343.00
10.29
Brick-chips
0.120
cft
40.00
4.80
Sub-Total(A1)
30.94
800.00
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
RCC Pipe 12" dia
1.050
rft
210.00
220.50
Sub-Total(B1)
220.50
800.00
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Earth Work in Excavation
3.530
cft
1.80
6.35
Brck flat soling
1.330
sft
0.60
0.80
CC Work
0.200
cft
5.00
1.00
300mm dia RCC pipe
1.000
rft
33.00
33.00
Sub-Total(L1)
41.15
800.00
Total(1)
2400.00
Add over head on Total(1)
3.0 %
72.00
Total(2)
2472.00
Add Profit on Total(2)
8.0 %
197.76
Total(3)
2669.76
Add VAT on Unit Price
4.5 %
125.80
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
2795.56
Say
2796
per RM
Item: 11C (F003) 450 mm dia Rcc pipe (Capital)
Basis:1 rft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
6.000
no.
3.80
22.80
Sand - Local - Mymensingh
0.080
cft
13.00
1.04
Cement
0.045
bag
343.00
15.44
Brick-chips
0.200
cft
40.00
8.00
Sub-Total(A1)
47.28
800.00
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
RCC Pipe 18" dia
1.050
rft
300.00
315.00
Sub-Total(B1)
315.00
800.00
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Earth Work in Excavation
5.300
cft
1.80
9.54
Brck flat soling
2.000
sft
0.60
1.20
CC Work
0.300
cft
5.00
1.50
450mm dia RCC pipe
1.000
rft
50.00
50.00
Sub-Total(L1)
62.24
800.00
Total(1)
2400.00
Add over head on Total(1)
3.0 %
72.00
Total(2)
2472.00
Add Profit on Total(2)
8.0 %
197.76
Total(3)
2669.76
Add VAT on Unit Price
4.5 %
125.80
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
2795.56
Say
2796
per RM
Item: 11D (F004) 600 mm dia Rcc pipe (Capital)
Basis:1 rft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
8.000
no.
3.80
30.40
Sand - Local - Mymensingh
0.120
cft
13.00
1.56
Cement
0.060
bag
343.00
20.58
Brick-chips
0.220
cft
40.00
8.80
Sub-Total(A1)
61.34
800.00
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
RCC Pipe 24" dia
1.050
rft
498.00
522.90
Sub-Total(B1)
522.90
800.00
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Earth Work in Excavation
7.067
cft
1.80
12.72
Brck flat soling
2.670
sft
0.60
1.60
CC Work
0.400
cft
5.00
2.00
600mm dia RCC pipe
1.000
rft
67.00
67.00
Sub-Total(L1)
83.32
800.00
Total(1)
2400.00
Add over head on Total(1)
3.0 %
72.00
Total(2)
2472.00
Add Profit on Total(2)
8.0 %
197.76
Total(3)
2669.76
Add VAT on Unit Price
4.5 %
125.80
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
2795.56
Say
2796
per RM
Item: 12A (F006) 225mm dia Rcc pipe (Capital-RC)
Basis:1 rft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
3.000
no.
3.80
11.40
Sand - Local - Mymensingh
0.350
cft
13.00
4.55
Polythene
0.065
kg
77.00
5.01
Cement
0.200
bag
343.00
68.60
Brick-chips
0.700
cft
40.00
28.00
Sub-Total(A1)
117.56
800.00
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
RCC Pipe 9" dia
1.050
rft
108.00
113.40
Sub-Total(B1)
113.40
800.00
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
1.200
cft
2.00
2.40
Sub-Total(E1)
2.40
800.00
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Earth Work in Excavation
2.380
cft
1.80
4.28
Brck flat soling
1.000
sft
0.60
0.60
CC Work
1.200
cft
5.00
6.00
225mm dia RCC pipe
1.000
rft
25.00
25.00
Sub-Total(L1)
35.88
800.00
Total(1)
3200.00
Add over head on Total(1)
3.0 %
96.00
Total(2)
3296.00
Add Profit on Total(2)
8.0 %
263.68
Total(3)
3559.68
Add VAT on Unit Price
4.5 %
167.73
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
3727.41
Say
3727
per RM
Item: 12B (F007) 300mm dia Rcc pipe (Capital-RC)
Basis:1 rft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
4.000
no.
3.80
15.20
Sand - Local - Mymensingh
0.500
cft
13.00
6.50
Polythene
0.080
kg
77.00
6.16
Cement
0.250
bag
343.00
85.75
Brick-chips
0.900
cft
40.00
36.00
Sub-Total(A1)
149.61
800.00
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
RCC Pipe 12" dia
1.050
rft
210.00
220.50
Sub-Total(B1)
220.50
800.00
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
1.500
cft
2.00
3.00
Sub-Total(E1)
3.00
800.00
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Earth Work in Excavation
3.170
cft
1.80
5.71
Brck flat soling
1.330
sft
0.60
0.80
CC Work
1.500
cft
5.00
7.50
300mm dia RCC pipe
1.000
rft
33.00
33.00
Sub-Total(L1)
47.00
800.00
Total(1)
3200.00
Add over head on Total(1)
3.0 %
96.00
Total(2)
3296.00
Add Profit on Total(2)
8.0 %
263.68
Total(3)
3559.68
Add VAT on Unit Price
4.5 %
167.73
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
3727.41
Say
3727
per RM
Item: 12C (F008) 450mm dia Rcc pipe (Capital-RC)
Basis:1 rft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
6.000
no.
3.80
22.80
Sand - Local - Mymensingh
0.660
cft
13.00
8.58
Polythene
0.120
kg
77.00
9.24
Cement
0.350
bag
343.00
120.05
Brick-chips
1.300
cft
40.00
52.00
Sub-Total(A1)
212.67
800.00
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
RCC Pipe 18" dia
1.050
rft
300.00
315.00
Sub-Total(B1)
315.00
800.00
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
2.300
cft
2.00
4.60
Sub-Total(E1)
4.60
800.00
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Earth Work in Excavation
4.760
cft
1.80
8.57
Brck flat soling
2.000
sft
0.60
1.20
CC Work
2.300
cft
5.00
11.50
450mm dia RCC pipe
1.000
rft
50.00
50.00
Sub-Total(L1)
71.27
800.00
Total(1)
3200.00
Add over head on Total(1)
3.0 %
96.00
Total(2)
3296.00
Add Profit on Total(2)
8.0 %
263.68
Total(3)
3559.68
Add VAT on Unit Price
4.5 %
167.73
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
3727.41
Say
3727
per RM
Item: 12D (F009) 600mm dia Rcc pipe (Capital-RC)
Basis:1 rft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
8.000
no.
3.80
30.40
Sand - Local - Mymensingh
0.900
cft
13.00
11.70
Polythene
0.160
kg
77.00
12.32
Cement
0.500
bag
343.00
171.50
Brick-chips
1.800
cft
40.00
72.00
Sub-Total(A1)
297.92
800.00
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
RCC Pipe 24" dia
1.050
rft
498.00
522.90
Sub-Total(B1)
522.90
800.00
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
3.100
cft
2.00
6.20
Sub-Total(E1)
6.20
800.00
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Earth Work in Excavation
6.350
cft
1.80
11.43
Brck flat soling
2.670
sft
0.60
1.60
CC Work
3.100
cft
5.00
15.50
600mm dia RCC pipe
1.000
rft
67.00
67.00
Sub-Total(L1)
95.53
800.00
Total(1)
3200.00
Add over head on Total(1)
3.0 %
96.00
Total(2)
3296.00
Add Profit on Total(2)
8.0 %
263.68
Total(3)
3559.68
Add VAT on Unit Price
4.5 %
167.73
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
3727.41
Say
3727
per RM