Return Main Menu

Project Refurbishment of Solid Project Office
Item: 01 (A09J) Dist. of CI roof shting i/c frame
Basis:1 sft
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Distle. CI sheet roofing.
1.000
sft
11.50
11.50
Sub-Total(L1)
11.50
123.79
Total(1)
123.79
Add over head on Total(1)
2.5 %
3.09
Total(2)
126.88
Add Profit on Total(2)
8.0 %
10.15
Total(3)
137.03
Add VAT on Unit Price
4.5 %
6.74
Add Income Tax on Unit Price
4.0 %
5.99
Unit Price
149.76
Say
150
per M2
Item: 02 (A09K) Dist. of T-ceiling/refitting
Basis:1 sft
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
T-Ceiling remove/Refittin
1.000
sft
11.50
11.50
Sub-Total(L1)
11.50
123.79
Total(1)
123.79
Add over head on Total(1)
2.5 %
3.09
Total(2)
126.88
Add Profit on Total(2)
8.0 %
10.15
Total(3)
137.03
Add VAT on Unit Price
4.5 %
6.74
Add Income Tax on Unit Price
4.0 %
5.99
Unit Price
149.76
Say
150
per M2
Item: 03 (A18) Dismantling of 250 Br-wall
Basis:1 cft
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Dismantle B/W 250mm thk
1.000
cft
5.00
5.00
Rubbish cleaning
1.000
cft
5.00
5.00
Sub-Total(L1)
10.00
353.15
Total(1)
353.15
Add over head on Total(1)
2.5 %
8.83
Total(2)
361.98
Add Profit on Total(2)
8.0 %
28.96
Total(3)
390.94
Add VAT on Unit Price
4.5 %
19.23
Add Income Tax on Unit Price
4.0 %
17.09
Unit Price
427.25
Say
427
per M3
Item: 04 (A06C) 250mm thick B-wall (1:5) - Supers
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
1200.000
no.
3.80
4560.00
Sand - Local - Mymensingh
40.000
cft
13.00
520.00
Cement
6.000
bag
343.00
2058.00
Sub-Total(A1)
7138.00
2520.78
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
B/w:15.5-27ft Scffld(Part
100.000
cft
6.00
600.00
Sub-Total(L0)
600.00
211.89
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Scaffolding
1.000
set
100.00
100.00
Sub-Total(M1)
100.00
35.32
Total(1)
2767.99
Add over head on Total(1)
2.5 %
69.20
Total(2)
2837.19
Add Profit on Total(2)
8.0 %
226.98
Total(3)
3064.16
Add VAT on Unit Price
4.5 %
150.70
Add Income Tax on Unit Price
4.0 %
133.95
Unit Price
3348.81
Say
3349
per M3
Item: 05 (A12A) Plaster(1:5) 20mm thick
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
8.250
cft
13.00
107.25
Cement
1.100
bag
343.00
377.30
Sub-Total(A1)
484.55
52.16
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
OutPlaster 30.5ft
100.000
sft
4.50
450.00
Sub-Total(L0)
450.00
48.44
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Scaffolding
1.500
set
100.00
150.00
Sub-Total(M1)
150.00
16.15
Total(1)
116.74
Add over head on Total(1)
2.5 %
2.92
Total(2)
119.66
Add Profit on Total(2)
8.0 %
9.57
Total(3)
129.23
Add VAT on Unit Price
4.5 %
6.36
Add Income Tax on Unit Price
4.0 %
5.65
Unit Price
141.24
Say
141
per M2
Item: 06 (A13F) Weather coat paint
Basis:100 sft
A3.Material-Paint
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Plastron Sealer
0.500
Ltr
160.00
80.00
Enamel paint
0.250
Ltr
170.00
42.50
Snowcel
2.500
kg
7.60
19.00
Thinner-T6/T7
0.500
Ltr
46.00
23.00
Weather Coat (ColorBank)
1.420
Ltr
227.85
323.55
Sub-Total(A3)
488.05
52.53
L6.Labour Paints
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Weather coat painting
100.000
sft
4.00
400.00
Sub-Total(L6)
400.00
43.06
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Scaffolding
1.000
set
100.00
100.00
Sub-Total(M1)
100.00
10.76
Total(1)
106.35
Add over head on Total(1)
2.5 %
2.66
Total(2)
109.01
Add Profit on Total(2)
8.0 %
8.72
Total(3)
117.73
Add VAT on Unit Price
4.5 %
5.79
Add Income Tax on Unit Price
4.0 %
5.15
Unit Price
128.67
Say
129
per M2
Item: 07 (C08) MS angle-Local
Basis:1000 kg.
C1.Steel Structures
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS angle
1050.000
kg
38.00
39900.00
Sub-Total(C1)
39900.00
10.76
L5.Labour-MS Work
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Truss making
1000.000
kg
8.00
8000.00
Sub-Total(L5)
8000.00
10.76
L6.Labour Paints
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS angle paint
1000.000
kg.
2.00
2000.00
Sub-Total(L6)
2000.00
10.76
Total(1)
32.29
Add over head on Total(1)
2.5 %
0.81
Total(2)
33.10
Add Profit on Total(2)
8.0 %
2.65
Total(3)
35.75
Add VAT on Unit Price
4.5 %
1.76
Add Income Tax on Unit Price
4.0 %
1.56
Unit Price
39.07
Say
39
per TON
Item: 08 (C14) CI sheet roofing (excl.angle)
Basis:100 sft
C1.Steel Structures
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
J-Hook
65.000
no
2.50
162.50
CI Sheet 0.45mm
0.700
Bun
3000.00
2100.00
Sub-Total(C1)
2262.50
243.54
S2.Alum,SS/MS,FalseCeil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
CI Sheet roofing
100.000
sft
2.75
275.00
Sub-Total(S2)
275.00
29.60
Total(1)
273.14
Add over head on Total(1)
2.5 %
6.83
Total(2)
279.96
Add Profit on Total(2)
8.0 %
22.40
Total(3)
302.36
Add VAT on Unit Price
4.5 %
14.87
Add Income Tax on Unit Price
4.0 %
13.22
Unit Price
330.45
Say
330
per M2
Item: 09A (A14D) T-Ceiling excluding Board
Basis:1 sft
S2.Alum,SS/MS,FalseCeil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
False Ceiling exclud Boar
1.000
sft
25.00
25.00
Sub-Total(S2)
25.00
269.10
Total(1)
269.10
Add over head on Total(1)
2.5 %
6.73
Total(2)
275.83
Add Profit on Total(2)
8.0 %
22.07
Total(3)
297.89
Add VAT on Unit Price
4.5 %
14.65
Add Income Tax on Unit Price
4.0 %
13.02
Unit Price
325.57
Say
326
per M2
Item: 09B (A03F) (1.3.6) Mass Concrete
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement
12.000
bag
343.00
4116.00
Sand - Sylhet
45.000
cft
24.00
1080.00
Stone-chips
90.000
cft
80.00
7200.00
Sub-Total(A1)
12396.00
4377.65
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
100.000
cft
2.00
200.00
Sub-Total(E1)
200.00
70.63
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
CC Work
100.000
cft
5.00
500.00
Sub-Total(L1)
500.00
176.58
Total(1)
4624.85
Add over head on Total(1)
2.5 %
115.62
Total(2)
4740.47
Add Profit on Total(2)
8.0 %
379.24
Total(3)
5119.71
Add VAT on Unit Price
4.5 %
251.79
Add Income Tax on Unit Price
4.0 %
223.81
Unit Price
5595.31
Say
5595
per M3
Item: 09C (B01B1) uPVC Pipe pipe fitting -100mm
Basis:1 rft
L4.Labour-Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
uPVC Pipe fitting-100 mm
1.000
rft
15.00
15.00
Sub-Total(L4)
15.00
176.58
Total(1)
176.58
Add over head on Total(1)
2.5 %
4.41
Total(2)
180.99
Add Profit on Total(2)
8.0 %
14.48
Total(3)
195.47
Add VAT on Unit Price
4.5 %
9.61
Add Income Tax on Unit Price
4.0 %
8.55
Unit Price
213.63
Say
214
per RM
Item: 09D (A13E1) Plastic paint to existing wall
Basis:100 sft
A3.Material-Paint
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Plastic Emulsion
0.655
Ltr
170.00
111.35
Enamel paint
0.300
Ltr
170.00
51.00
Snowcel
1.000
kg
7.60
7.60
Thinner-T6/T7
0.400
Ltr
46.00
18.40
Water Paper
0.200
nos
40.00
8.00
Sub-Total(A3)
196.35
21.14
L6.Labour Paints
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Plastic Paint (1-coat)
100.000
sft
1.25
125.00
Sub-Total(L6)
125.00
13.46
Total(1)
34.59
Add over head on Total(1)
2.5 %
0.86
Total(2)
35.45
Add Profit on Total(2)
8.0 %
2.84
Total(3)
38.29
Add VAT on Unit Price
4.5 %
1.88
Add Income Tax on Unit Price
4.0 %
1.67
Unit Price
41.85
Say
42
per M2