Return Main Menu

Project Q.A. Office Upgrade Work
Item: 01 (A06F) 125 B/Wall (1:4)
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
500.000
no.
3.80
1900.00
Sand - Local - Mymensingh
17.000
cft
13.00
221.00
Cement
3.000
bag
343.00
1029.00
Sub-Total(A1)
3150.00
339.07
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
125mm thick Brick Work
100.000
sft
6.00
600.00
Sub-Total(L0)
600.00
64.58
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Scaffolding
0.000
set
100.00
0.00
Sub-Total(M1)
0.00
0.00
Total(1)
403.65
Add over head on Total(1)
3.0 %
12.11
Total(2)
415.76
Add Profit on Total(2)
8.0 %
33.26
Total(3)
449.02
Add VAT on Unit Price
4.5 %
21.16
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
470.18
Say
470
per M2
Item: 02 (A12B) Plaster 12mm thick (1:4)
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
7.500
cft
13.00
97.50
Cement
1.000
bag
343.00
343.00
Sub-Total(A1)
440.50
47.42
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Plaster Work
100.000
sft
3.00
300.00
Sub-Total(L1)
300.00
32.29
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Scaffolding
1.000
set
100.00
100.00
Sub-Total(M1)
100.00
10.76
Total(1)
90.47
Add over head on Total(1)
3.0 %
2.71
Total(2)
93.19
Add Profit on Total(2)
8.0 %
7.45
Total(3)
100.64
Add VAT on Unit Price
4.5 %
4.74
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
105.38
Say
105
per M2
Item: 03 (A08Y) Beam, Lintel (1:1.5:3)
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement
22.000
bag
343.00
7546.00
Sand - Sylhet
46.000
cft
24.00
1104.00
Stone-chips
91.000
cft
80.00
7280.00
Sub-Total(A1)
15930.00
5625.68
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
100.000
cft
2.00
200.00
Mini Dumper
100.000
cft
2.00
200.00
Sub-Total(E1)
400.00
141.26
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
1.000
nos.
100.00
100.00
RCC Casting-Superstructur
100.000
sft
10.00
1000.00
FormWork:24-33ft from PL
357.000
sft
10.00
3570.00
Sub-Total(L0)
4670.00
1649.21
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Forms
357.000
sft
5.00
1785.00
Steel pipe with B-plate
15.000
no
11.00
165.00
Wood shutter-3time
2.000
cft
350.00
700.00
Steel beam,S-structure
8.000
no
40.00
320.00
Sub-Total(M1)
2970.00
1048.86
Total(1)
8465.01
Add over head on Total(1)
3.0 %
253.95
Total(2)
8718.96
Add Profit on Total(2)
8.0 %
697.52
Total(3)
9416.47
Add VAT on Unit Price
4.5 %
443.71
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
9860.18
Say
9860
per M3
Item: 04 (A13G) Epoxy paint to wall (New)
Basis:100 sft
A3.Material-Paint
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Epoxy Primer
2.000
Ltr
170.00
340.00
Epoxy Enamel
3.080
Ltr
387.00
1191.96
Thinner-T6/T7
1.600
Ltr
46.00
73.60
Chalk powder
1.330
kg
18.00
23.94
Mosaic stone
0.200
no
110.00
22.00
Scrap
1.000
L.s
30.00
30.00
Sub-Total(A3)
1681.50
181.00
L6.Labour Paints
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Epoxy Paint to wall
100.000
sft
10.00
1000.00
Sub-Total(L6)
1000.00
107.64
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Scaffolding
1.000
set
100.00
100.00
Sub-Total(M1)
100.00
10.76
Total(1)
299.40
Add over head on Total(1)
3.0 %
8.98
Total(2)
308.38
Add Profit on Total(2)
8.0 %
24.67
Total(3)
333.05
Add VAT on Unit Price
4.5 %
15.69
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
348.75
Say
349
per M2
Item: 05 (A14A) Laminated Gypsum Board Ceiling
Basis:100 sft
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Scaffolding
1.000
set
100.00
100.00
Sub-Total(M1)
100.00
10.76
S2.Alum,SS/MS,FalseCeil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Lamint GypsumBoardCeiling
100.000
sft
42.00
4200.00
Sub-Total(S2)
4200.00
452.09
Total(1)
462.85
Add over head on Total(1)
3.0 %
13.89
Total(2)
476.74
Add Profit on Total(2)
8.0 %
38.14
Total(3)
514.88
Add VAT on Unit Price
4.5 %
24.26
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
539.14
Say
539
per M2
Item: 06 (A11G) Alum(PC) swing door Plastic-Glass
Basis:1 sft
S2.Alum,SS/MS,FalseCeil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Alum.Swing doorGlass-Plas
1.000
sft
470.00
470.00
Sub-Total(S2)
470.00
5059.08
Total(1)
5059.08
Add over head on Total(1)
3.0 %
151.77
Total(2)
5210.85
Add Profit on Total(2)
8.0 %
416.87
Total(3)
5627.72
Add VAT on Unit Price
4.5 %
265.18
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
5892.90
Say
5893
per M2
Item: 07A (A09D2) Plywood partition remove
Basis:1 sft
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
0.030
nos.
100.00
3.00
Sub-Total(L0)
3.00
32.29
Total(1)
32.29
Add over head on Total(1)
3.0 %
0.97
Total(2)
33.26
Add Profit on Total(2)
8.0 %
2.66
Total(3)
35.92
Add VAT on Unit Price
4.5 %
1.69
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
37.61
Say
38
per M2
Item: 07B (A11B1) Alum Slising Window(Ex.glass)
Basis:1 sft
S2.Alum,SS/MS,FalseCeil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Al.Sliding Window-ExGlass
1.000
sft
135.00
135.00
Sub-Total(S2)
135.00
1453.14
Total(1)
1453.14
Add over head on Total(1)
3.0 %
43.59
Total(2)
1496.73
Add Profit on Total(2)
8.0 %
119.74
Total(3)
1616.47
Add VAT on Unit Price
4.5 %
76.17
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
1692.64
Say
1693
per M2
Item: 07C (G03D1) RCC Beam punch-100mm dia
Basis:1 no.
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
1.000
nos.
100.00
100.00
Head Mason Supply
2.000
nos.
200.00
400.00
Sub-Total(L0)
500.00
500.00
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cheisel - Hammer
2.000
no
55.00
110.00
Sub-Total(M1)
110.00
110.00
Total(1)
610.00
Add over head on Total(1)
3.0 %
18.30
Total(2)
628.30
Add Profit on Total(2)
8.0 %
50.26
Total(3)
678.56
Add VAT on Unit Price
4.5 %
31.97
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
710.54
Say
711
per NO.
Item: 07D (G03E) Wall/ Ceiling Punch - 75mm dia
Basis:1 no.
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
1.000
nos.
100.00
100.00
Sub-Total(L0)
100.00
100.00
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Scaffolding
0.100
set
100.00
10.00
Cheisel - Hammer
1.000
no
55.00
55.00
Sub-Total(M1)
65.00
65.00
Total(1)
165.00
Add over head on Total(1)
3.0 %
4.95
Total(2)
169.95
Add Profit on Total(2)
8.0 %
13.60
Total(3)
183.55
Add VAT on Unit Price
4.5 %
8.65
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
192.19
Say
192
per NO.
Item: 07E (A11K1) Reflected Glass with frosted
Basis:1 sft
S2.Alum,SS/MS,FalseCeil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Reflected Glass with fros
1.000
sft
160.00
160.00
Sub-Total(S2)
160.00
1722.24
Total(1)
1722.24
Add over head on Total(1)
3.0 %
51.67
Total(2)
1773.91
Add Profit on Total(2)
8.0 %
141.91
Total(3)
1915.82
Add VAT on Unit Price
4.5 %
90.27
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
2006.09
Say
2006
per M2