Return Main Menu

Project Pile Found-Solid Track-II Utility Buildn
Item: 01 (A09I) Dismantling of Shed i/c celg,wall
Basis:1 sft
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Dismantle Existing Store
1.000
sft
9.50
9.50
Sub-Total(L1)
9.50
102.26
Total(1)
102.26
Add over head on Total(1)
3.0 %
3.07
Total(2)
105.33
Add Profit on Total(2)
8.0 %
8.43
Total(3)
113.75
Add VAT on Unit Price
4.5 %
5.36
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
119.11
Say
119
per M2
Item: 02 (A08M) RCC(1:1.5:3) -500mm Bored Pile
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement
26.400
bag
343.00
9055.20
Sand - Sylhet
51.600
cft
24.00
1238.40
Stone-chips
103.200
cft
80.00
8256.00
Sub-Total(A1)
18549.60
6550.79
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Rig,Mixer M/c
120.000
cft
10.00
1200.00
Sub-Total(E1)
1200.00
423.78
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
RCC Casting.
120.000
cft
8.00
960.00
Sub-Total(L0)
960.00
339.02
Total(1)
7313.60
Add over head on Total(1)
3.0 %
219.41
Total(2)
7533.00
Add Profit on Total(2)
8.0 %
602.64
Total(3)
8135.64
Add VAT on Unit Price
4.5 %
383.35
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
8519.00
Say
8519
per M3
Item: 03 (A10D) Re-bar (G60) - Bored Pile
Basis:1000 kg.
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
GI Wire
8.000
kg
90.00
720.00
Re-bar G60
1050.000
kg
40.20
42210.00
Sub-Total(A1)
42930.00
339.02
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Welding M/c
1000.000
kg
0.50
500.00
Sub-Total(E1)
500.00
339.02
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Re-bar Work
1000.000
kg
1.65
1650.00
Sub-Total(L0)
1650.00
339.02
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Welding Electrode VM 8-no
3.000
pack
520.00
1560.00
Sub-Total(M1)
1560.00
339.02
Total(1)
1356.10
Add over head on Total(1)
3.0 %
40.68
Total(2)
1396.78
Add Profit on Total(2)
8.0 %
111.74
Total(3)
1508.52
Add VAT on Unit Price
4.5 %
71.08
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
1579.60
Say
1580
per TON
Item: 04 (A15A) Insitu Pile Boring -400mm dia
Basis:1 rft
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Bored Piling Equipment
1.000
rft
30.00
30.00
Sub-Total(E1)
30.00
339.02
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Pile Boring - 500mm dia
1.000
rft
90.00
90.00
Sub-Total(L1)
90.00
339.02
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Bentonite
1.000
kg
20.00
20.00
Sub-Total(M1)
20.00
339.02
Total(1)
1017.07
Add over head on Total(1)
3.0 %
30.51
Total(2)
1047.58
Add Profit on Total(2)
8.0 %
83.81
Total(3)
1131.39
Add VAT on Unit Price
4.5 %
53.31
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
1184.70
Say
1185
per RM