Project Pile Found-Solid Track-II Utility Buildn |
Item: 01 (A09I) Dismantling of Shed i/c celg,wall |
|
Basis:1
sft |
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Dismantle Existing Store |
1.000 |
sft |
9.50 |
9.50 |
|
|
Sub-Total(L1) |
9.50
|
102.26
|
|
|
|
Total(1) |
|
102.26 |
|
Add over head on Total(1)
|
3.0 % |
3.07 |
|
|
|
Total(2) |
|
105.33 |
|
Add Profit on Total(2) |
8.0 % |
8.43
|
|
|
|
Total(3) |
|
113.75 |
|
Add VAT on Unit Price |
4.5 % |
5.36 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
119.11
|
|
|
|
Say |
|
Item: 02 (A08M) RCC(1:1.5:3) -500mm Bored Pile |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Cement |
26.400 |
bag |
343.00 |
9055.20 |
|
Sand - Sylhet |
51.600 |
cft |
24.00 |
1238.40 |
|
Stone-chips |
103.200 |
cft |
80.00 |
8256.00 |
|
|
Sub-Total(A1) |
18549.60
|
6550.79
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Rig,Mixer M/c |
120.000 |
cft |
10.00 |
1200.00 |
|
|
Sub-Total(E1) |
1200.00
|
423.78
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
RCC Casting. |
120.000 |
cft |
8.00 |
960.00 |
|
|
Sub-Total(L0) |
960.00
|
339.02
|
|
|
|
Total(1) |
|
7313.60 |
|
Add over head on Total(1)
|
3.0 % |
219.41 |
|
|
|
Total(2) |
|
7533.00 |
|
Add Profit on Total(2) |
8.0 % |
602.64
|
|
|
|
Total(3) |
|
8135.64 |
|
Add VAT on Unit Price |
4.5 % |
383.35 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
8519.00
|
|
|
|
Say |
|
Item: 03 (A10D) Re-bar (G60) - Bored Pile |
|
Basis:1000
kg. |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
GI Wire |
8.000 |
kg |
90.00 |
720.00 |
|
Re-bar G60 |
1050.000 |
kg |
40.20 |
42210.00 |
|
|
Sub-Total(A1) |
42930.00
|
339.02
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Welding M/c |
1000.000 |
kg |
0.50 |
500.00 |
|
|
Sub-Total(E1) |
500.00
|
339.02
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Re-bar Work |
1000.000 |
kg |
1.65 |
1650.00 |
|
|
Sub-Total(L0) |
1650.00
|
339.02
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Welding Electrode VM 8-no |
3.000 |
pack |
520.00 |
1560.00 |
|
|
Sub-Total(M1) |
1560.00
|
339.02
|
|
|
|
Total(1) |
|
1356.10 |
|
Add over head on Total(1)
|
3.0 % |
40.68 |
|
|
|
Total(2) |
|
1396.78 |
|
Add Profit on Total(2) |
8.0 % |
111.74
|
|
|
|
Total(3) |
|
1508.52 |
|
Add VAT on Unit Price |
4.5 % |
71.08 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
1579.60
|
|
|
|
Say |
|
Item: 04 (A15A) Insitu Pile Boring -400mm dia |
|
Basis:1
rft |
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Bored Piling Equipment |
1.000 |
rft |
30.00 |
30.00 |
|
|
Sub-Total(E1) |
30.00
|
339.02
|
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Pile Boring - 500mm dia |
1.000 |
rft |
90.00 |
90.00 |
|
|
Sub-Total(L1) |
90.00
|
339.02
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Bentonite |
1.000 |
kg |
20.00 |
20.00 |
|
|
Sub-Total(M1) |
20.00
|
339.02
|
|
|
|
Total(1) |
|
1017.07 |
|
Add over head on Total(1)
|
3.0 % |
30.51 |
|
|
|
Total(2) |
|
1047.58 |
|
Add Profit on Total(2) |
8.0 % |
83.81
|
|
|
|
Total(3) |
|
1131.39 |
|
Add VAT on Unit Price |
4.5 % |
53.31 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
1184.70
|
|
|
|
Say |
|