Project New Liquids Utility Building-Foundation |
Item: 01 (A09A) Dismantle BFS and Rubbish Shiftin |
|
Basis:1
sft |
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Dismantling CC-BFS |
1.000 |
sft |
3.00 |
3.00 |
|
|
Sub-Total(L1) |
3.00
|
32.29
|
|
|
|
Total(1) |
|
32.29 |
|
Add over head on Total(1)
|
3.0 % |
0.97 |
|
|
|
Total(2) |
|
33.26 |
|
Add Profit on Total(2) |
8.0 % |
2.66
|
|
|
|
Total(3) |
|
35.92 |
|
Add VAT on Unit Price |
4.5 % |
1.69 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
37.61
|
|
|
|
Say |
|
Item: 02 (A09P) Deduction of Old Brick |
|
Basis:1
no. |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Used Brick |
1.000 |
no. |
1.70 |
1.70 |
|
|
Sub-Total(A1) |
1.70
|
1.70
|
|
|
|
Total(1) |
|
1.70 |
|
Add over head on Total(1)
|
3.0 % |
0.05 |
|
|
|
Total(2) |
|
1.75 |
|
Add Profit on Total(2) |
8.0 % |
0.14
|
|
|
|
Total(3) |
|
1.89 |
|
Add VAT on Unit Price |
4.5 % |
0.09 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
1.98
|
|
|
|
Say |
|
Item: 03 (A01D) E/Cuting with shoring,soil remove |
|
Basis:100
cft |
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Earth Work in Excavation |
100.000 |
cft |
1.80 |
180.00 |
|
|
Sub-Total(L1) |
180.00
|
63.57
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Shoring for Excavation |
38.440 |
sft |
2.15 |
82.65 |
|
|
Sub-Total(M1) |
82.65
|
29.19
|
|
|
|
Total(1) |
|
92.75 |
|
Add over head on Total(1)
|
3.0 % |
2.78 |
|
|
|
Total(2) |
|
95.54 |
|
Add Profit on Total(2) |
8.0 % |
7.64
|
|
|
|
Total(3) |
|
103.18 |
|
Add VAT on Unit Price |
4.5 % |
4.86 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
108.04
|
|
|
|
Say |
|
Item: 04 (A05) Sand Filling |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Filling Sand |
130.000 |
cft |
8.50 |
1105.00 |
|
|
Sub-Total(A1) |
1105.00
|
390.23
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mini Roller Compaction |
100.000 |
cft |
1.00 |
100.00 |
|
Mini Dumper |
130.000 |
cft |
2.00 |
260.00 |
|
Payloader |
0.000 |
day |
8000.00 |
0.00 |
|
Dump Truck |
0.000 |
day |
8300.00 |
0.00 |
|
|
Sub-Total(E1) |
360.00
|
127.13
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Ordinary Labour Supply |
0.800 |
nos. |
100.00 |
80.00 |
|
|
Sub-Total(L0) |
80.00
|
28.25
|
|
|
|
Total(1) |
|
545.62 |
|
Add over head on Total(1)
|
3.0 % |
16.37 |
|
|
|
Total(2) |
|
561.99 |
|
Add Profit on Total(2) |
8.0 % |
44.96
|
|
|
|
Total(3) |
|
606.94 |
|
Add VAT on Unit Price |
4.5 % |
28.60 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
635.54
|
|
|
|
Say |
|
Item: 05 (A02B) Brick Flat Soling |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Filling Sand |
5.000 |
cft |
8.50 |
42.50 |
|
Brick |
300.000 |
no. |
3.80 |
1140.00 |
|
|
Sub-Total(A1) |
1182.50
|
127.28
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Ordinary Labour Supply |
0.100 |
nos. |
100.00 |
10.00 |
|
Head Mason Supply |
0.250 |
nos. |
200.00 |
50.00 |
|
|
Sub-Total(L0) |
60.00
|
6.46
|
|
|
|
Total(1) |
|
133.74 |
|
Add over head on Total(1)
|
3.0 % |
4.01 |
|
|
|
Total(2) |
|
137.75 |
|
Add Profit on Total(2) |
8.0 % |
11.02
|
|
|
|
Total(3) |
|
148.78 |
|
Add VAT on Unit Price |
4.5 % |
7.01 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
155.79
|
|
|
|
Say |
|
Item: 06 (A02E) Double Layer Polythene |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Polythene |
3.000 |
kg |
77.00 |
231.00 |
|
|
Sub-Total(A1) |
231.00
|
24.86
|
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Polythene laying |
200.000 |
sft |
0.20 |
40.00 |
|
|
Sub-Total(L1) |
40.00
|
4.31
|
|
|
|
Total(1) |
|
29.17 |
|
Add over head on Total(1)
|
3.0 % |
0.88 |
|
|
|
Total(2) |
|
30.05 |
|
Add Profit on Total(2) |
8.0 % |
2.40
|
|
|
|
Total(3) |
|
32.45 |
|
Add VAT on Unit Price |
4.5 % |
1.53 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
33.98
|
|
|
|
Say |
|
Item: 07 (A03I) 75mm thick cc (1:3:6)-U-footing |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
15.000 |
cft |
13.00 |
195.00 |
|
Cement |
12.000 |
bag |
343.00 |
4116.00 |
|
Sand - Sylhet |
30.000 |
cft |
24.00 |
720.00 |
|
Brick-chips |
90.000 |
cft |
40.00 |
3600.00 |
|
|
Sub-Total(A1) |
8631.00
|
3048.04
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mixer m/c and vibrator |
100.000 |
cft |
2.00 |
200.00 |
|
Mini Dumper |
100.000 |
cft |
2.00 |
200.00 |
|
|
Sub-Total(E1) |
400.00
|
141.26
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand Screening |
45.000 |
cft |
1.00 |
45.00 |
|
|
Sub-Total(L0) |
45.00
|
15.89
|
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
CC Work |
100.000 |
cft |
5.00 |
500.00 |
|
|
Sub-Total(L1) |
500.00
|
176.58
|
|
|
|
Total(1) |
|
3381.76 |
|
Add over head on Total(1)
|
3.0 % |
101.45 |
|
|
|
Total(2) |
|
3483.22 |
|
Add Profit on Total(2) |
8.0 % |
278.66
|
|
|
|
Total(3) |
|
3761.87 |
|
Add VAT on Unit Price |
4.5 % |
177.26 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
3939.14
|
|
|
|
Say |
|
Item: 08A (A08B) RCC (1:1.5:3) in Footing |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
14.330 |
cft |
13.00 |
186.29 |
|
Cement |
22.000 |
bag |
343.00 |
7546.00 |
|
Sand - Sylhet |
28.670 |
cft |
24.00 |
688.08 |
|
Stone-chips |
86.000 |
cft |
80.00 |
6880.00 |
|
|
Sub-Total(A1) |
15300.37
|
5403.33
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mixer m/c and vibrator |
100.000 |
cft |
2.00 |
200.00 |
|
Mini Dumper |
100.000 |
cft |
2.00 |
200.00 |
|
|
Sub-Total(E1) |
400.00
|
141.26
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Formwork upto 10ft from P |
61.820 |
sft |
8.00 |
494.56 |
|
Sand Screening |
43.000 |
cft |
1.00 |
43.00 |
|
RCC Casting. |
100.000 |
cft |
8.00 |
800.00 |
|
|
Sub-Total(L0) |
1337.56
|
472.36
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Forms |
61.820 |
sft |
5.00 |
309.10 |
|
|
Sub-Total(M1) |
309.10
|
109.16
|
|
|
|
Total(1) |
|
6126.10 |
|
Add over head on Total(1)
|
3.0 % |
183.78 |
|
|
|
Total(2) |
|
6309.89 |
|
Add Profit on Total(2) |
8.0 % |
504.79
|
|
|
|
Total(3) |
|
6814.68 |
|
Add VAT on Unit Price |
4.5 % |
321.11 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
7135.79
|
|
|
|
Say |
|
Item: 08B (A08D) RCC (1:1.5:3) in GB/TB |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Cement |
22.000 |
bag |
343.00 |
7546.00 |
|
Sand - Sylhet |
43.000 |
cft |
24.00 |
1032.00 |
|
Stone-chips |
86.000 |
cft |
80.00 |
6880.00 |
|
|
Sub-Total(A1) |
15458.00
|
5458.99
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mixer m/c and vibrator |
100.000 |
cft |
2.00 |
200.00 |
|
Mini Dumper |
100.000 |
cft |
2.00 |
200.00 |
|
|
Sub-Total(E1) |
400.00
|
141.26
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Formwork upto 10ft from P |
242.000 |
sft |
8.00 |
1936.00 |
|
RCC Casting. |
100.000 |
cft |
8.00 |
800.00 |
|
|
Sub-Total(L0) |
2736.00
|
966.22
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel pipe with B-plate |
0.000 |
no |
11.00 |
0.00 |
|
wood use 5-time-Garjan |
0.100 |
cft |
850.00 |
85.00 |
|
Steel form,S-structure |
242.000 |
sft |
10.00 |
2420.00 |
|
Wood use-6time mango |
0.200 |
cft |
350.00 |
70.00 |
|
|
Sub-Total(M1) |
2575.00
|
909.36
|
|
|
|
Total(1) |
|
7475.83 |
|
Add over head on Total(1)
|
3.0 % |
224.27 |
|
|
|
Total(2) |
|
7700.11 |
|
Add Profit on Total(2) |
8.0 % |
616.01
|
|
|
|
Total(3) |
|
8316.12 |
|
Add VAT on Unit Price |
4.5 % |
391.86 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
8707.97
|
|
|
|
Say |
|
Item: 08C (A08O) RCC Drain (1:1.5:3) |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
14.333 |
cft |
13.00 |
186.33 |
|
Cement |
22.000 |
bag |
343.00 |
7546.00 |
|
Sand - Sylhet |
28.667 |
cft |
24.00 |
688.01 |
|
Stone-chips |
86.000 |
cft |
80.00 |
6880.00 |
|
|
Sub-Total(A1) |
15300.34
|
5403.31
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mixer m/c and vibrator |
100.000 |
cft |
2.00 |
200.00 |
|
Mini Dumper |
100.000 |
cft |
2.00 |
200.00 |
|
|
Sub-Total(E1) |
400.00
|
141.26
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Formwork upto 10ft from P |
400.000 |
sft |
8.00 |
3200.00 |
|
Sand Screening |
43.000 |
cft |
1.00 |
43.00 |
|
RCC Casting. |
100.000 |
cft |
8.00 |
800.00 |
|
|
Sub-Total(L0) |
4043.00
|
1427.79
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Forms |
400.000 |
sft |
5.00 |
2000.00 |
|
Steel pipe with B-plate |
80.000 |
no |
11.00 |
880.00 |
|
Wood use-6time mango |
2.500 |
cft |
350.00 |
875.00 |
|
|
Sub-Total(M1) |
3755.00
|
1326.08
|
|
|
|
Total(1) |
|
8298.44 |
|
Add over head on Total(1)
|
3.0 % |
248.95 |
|
|
|
Total(2) |
|
8547.39 |
|
Add Profit on Total(2) |
8.0 % |
683.79
|
|
|
|
Total(3) |
|
9231.18 |
|
Add VAT on Unit Price |
4.5 % |
434.98 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
9666.16
|
|
|
|
Say |
|
Item: 08D (A08R) RCC Clmn (1:1.5:3) padestal |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Cement |
22.000 |
bag |
343.00 |
7546.00 |
|
Sand - Sylhet |
43.000 |
cft |
24.00 |
1032.00 |
|
Stone-chips |
86.000 |
cft |
80.00 |
6880.00 |
|
|
Sub-Total(A1) |
15458.00
|
5458.99
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mini Dumper |
100.000 |
cft |
2.00 |
200.00 |
|
Batching Plant , Vibrator |
100.000 |
cft |
8.00 |
800.00 |
|
|
Sub-Total(E1) |
1000.00
|
353.15
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Formwork upto 10ft from P |
305.000 |
sft |
8.00 |
2440.00 |
|
Sand Screening |
43.000 |
cft |
1.00 |
43.00 |
|
RCC Casting. |
100.000 |
cft |
8.00 |
800.00 |
|
|
Sub-Total(L0) |
3283.00
|
1159.39
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Forms |
305.000 |
sft |
5.00 |
1525.00 |
|
|
Sub-Total(M1) |
1525.00
|
538.55
|
|
|
|
Total(1) |
|
7510.09 |
|
Add over head on Total(1)
|
3.0 % |
225.30 |
|
|
|
Total(2) |
|
7735.39 |
|
Add Profit on Total(2) |
8.0 % |
618.83
|
|
|
|
Total(3) |
|
8354.22 |
|
Add VAT on Unit Price |
4.5 % |
393.65 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
8747.88
|
|
|
|
Say |
|
Item: 08E (A08P) RCC(1:1.5:3) Gr.Flr Slab on Grade |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
21.830 |
cft |
13.00 |
283.79 |
|
Cement |
23.000 |
bag |
343.00 |
7889.00 |
|
Sand - Sylhet |
28.670 |
cft |
24.00 |
688.08 |
|
Stone-chips |
86.000 |
cft |
80.00 |
6880.00 |
|
|
Sub-Total(A1) |
15740.87
|
5558.89
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mixer m/c and vibrator |
100.000 |
cft |
2.00 |
200.00 |
|
Mini Dumper |
100.000 |
cft |
2.00 |
200.00 |
|
|
Sub-Total(E1) |
400.00
|
141.26
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Formwork upto 10ft from P |
240.000 |
sft |
8.00 |
1920.00 |
|
Sand Screening |
43.000 |
cft |
1.00 |
43.00 |
|
RCC Casting. |
100.000 |
cft |
8.00 |
800.00 |
|
|
Sub-Total(L0) |
2763.00
|
975.75
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Forms |
240.000 |
sft |
5.00 |
1200.00 |
|
Steel beam,S-structure |
8.000 |
no |
40.00 |
320.00 |
|
|
Sub-Total(M1) |
1520.00
|
536.79
|
|
|
|
Total(1) |
|
7212.69 |
|
Add over head on Total(1)
|
3.0 % |
216.38 |
|
|
|
Total(2) |
|
7429.07 |
|
Add Profit on Total(2) |
8.0 % |
594.33
|
|
|
|
Total(3) |
|
8023.40 |
|
Add VAT on Unit Price |
4.5 % |
378.07 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
8401.46
|
|
|
|
Say |
|
Item: 09 (A10A) Re-bar Grade 60 |
|
Basis:1000
kg. |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
GI Wire |
10.000 |
kg |
90.00 |
900.00 |
|
Re-bar G60 |
1050.000 |
kg |
40.20 |
42210.00 |
|
|
Sub-Total(A1) |
43110.00
|
536.79
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Re-bar Work |
1000.000 |
kg |
1.65 |
1650.00 |
|
Local carrying Rod |
0.000 |
kg |
0.25 |
0.00 |
|
|
Sub-Total(L0) |
1650.00
|
536.79
|
|
|
|
Total(1) |
|
1073.58 |
|
Add over head on Total(1)
|
3.0 % |
32.21 |
|
|
|
Total(2) |
|
1105.78 |
|
Add Profit on Total(2) |
8.0 % |
88.46
|
|
|
|
Total(3) |
|
1194.25 |
|
Add VAT on Unit Price |
4.5 % |
56.27 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
1250.52
|
|
|
|
Say |
|
Item: 10 (A06B) Brick Work 250mm in Foundation |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Brick |
1200.000 |
no. |
3.80 |
4560.00 |
|
Sand - Local - Mymensingh |
40.000 |
cft |
13.00 |
520.00 |
|
Cement |
5.000 |
bag |
343.00 |
1715.00 |
|
|
Sub-Total(A1) |
6795.00
|
2399.65
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
250mm Brickwork upto 7 ft |
100.000 |
cft |
4.25 |
425.00 |
|
|
Sub-Total(L0) |
425.00
|
150.09
|
|
|
|
Total(1) |
|
2549.74 |
|
Add over head on Total(1)
|
3.0 % |
76.49 |
|
|
|
Total(2) |
|
2626.24 |
|
Add Profit on Total(2) |
8.0 % |
210.10
|
|
|
|
Total(3) |
|
2836.33 |
|
Add VAT on Unit Price |
4.5 % |
133.65 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
2969.98
|
|
|
|
Say |
|
Item: 11 (A12A) Plaster(1:5) 20mm thick |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
8.250 |
cft |
13.00 |
107.25 |
|
Cement |
1.100 |
bag |
343.00 |
377.30 |
|
|
Sub-Total(A1) |
484.55
|
52.16
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
OutPlaster 30.5ft |
100.000 |
sft |
4.50 |
450.00 |
|
|
Sub-Total(L0) |
450.00
|
48.44
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Scaffolding |
1.500 |
set |
100.00 |
150.00 |
|
|
Sub-Total(M1) |
150.00
|
16.15
|
|
|
|
Total(1) |
|
116.74 |
|
Add over head on Total(1)
|
3.0 % |
3.50 |
|
|
|
Total(2) |
|
120.24 |
|
Add Profit on Total(2) |
8.0 % |
9.62
|
|
|
|
Total(3) |
|
129.86 |
|
Add VAT on Unit Price |
4.5 % |
6.12 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
135.98
|
|
|
|
Say |
|
Item: 12 (A03D) 40mm Thick Patent Stone with NCF |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
5.400 |
cft |
13.00 |
70.20 |
|
Cement |
2.660 |
bag |
343.00 |
912.38 |
|
Brick-chips |
10.800 |
cft |
40.00 |
432.00 |
|
|
Sub-Total(A1) |
1414.58
|
152.27
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mixer m/c and vibrator |
12.000 |
cft |
2.00 |
24.00 |
|
|
Sub-Total(E1) |
24.00
|
2.58
|
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
CC (50mm) With NCF |
100.000 |
sft |
3.00 |
300.00 |
|
|
Sub-Total(L1) |
300.00
|
32.29
|
|
|
|
Total(1) |
|
187.14 |
|
Add over head on Total(1)
|
3.0 % |
5.61 |
|
|
|
Total(2) |
|
192.75 |
|
Add Profit on Total(2) |
8.0 % |
15.42
|
|
|
|
Total(3) |
|
208.18 |
|
Add VAT on Unit Price |
4.5 % |
9.81 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
217.98
|
|
|
|
Say |
|
Item: 13A (A09E) Dismantling - Precast CC Block |
|
Basis:1
sft |
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Dismantling - PC Block |
1.000 |
sft |
2.00 |
2.00 |
|
|
Sub-Total(L1) |
2.00
|
21.53
|
|
|
|
Total(1) |
|
21.53 |
|
Add over head on Total(1)
|
3.0 % |
0.65 |
|
|
|
Total(2) |
|
22.17 |
|
Add Profit on Total(2) |
8.0 % |
1.77
|
|
|
|
Total(3) |
|
23.95 |
|
Add VAT on Unit Price |
4.5 % |
1.13 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
25.08
|
|
|
|
Say |
|
Item: 13B (A09F) Dismantling - 250mm Brick Wall |
|
Basis:1
cft |
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Dismatle - B/W |
1.000 |
cft |
3.50 |
3.50 |
|
|
Sub-Total(L1) |
3.50
|
123.60
|
|
|
|
Total(1) |
|
123.60 |
|
Add over head on Total(1)
|
3.0 % |
3.71 |
|
|
|
Total(2) |
|
127.31 |
|
Add Profit on Total(2) |
8.0 % |
10.18
|
|
|
|
Total(3) |
|
137.50 |
|
Add VAT on Unit Price |
4.5 % |
6.48 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
143.97
|
|
|
|
Say |
|
Item: 13C (A09) RCC Dismatling |
|
Basis:1
cft |
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Dismantling RCC |
1.000 |
cft |
30.00 |
30.00 |
|
|
Sub-Total(L1) |
30.00
|
1059.45
|
|
|
|
Total(1) |
|
1059.45 |
|
Add over head on Total(1)
|
3.0 % |
31.78 |
|
|
|
Total(2) |
|
1091.23 |
|
Add Profit on Total(2) |
8.0 % |
87.30
|
|
|
|
Total(3) |
|
1178.53 |
|
Add VAT on Unit Price |
4.5 % |
55.53 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
1234.07
|
|
|
|
Say |
|
Item: 13D (D08) Mud/ Clay Carrying by Truck |
|
Basis:1
no. |
|
|
|
Total(1) |
|
0.00 |
|
Add over head on Total(1)
|
3.0 % |
31.78 |
|
|
|
Total(2) |
|
1091.23 |
|
Add Profit on Total(2) |
8.0 % |
87.30
|
|
|
|
Total(3) |
|
1178.53 |
|
Add VAT on Unit Price |
4.5 % |
55.53 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
1234.07
|
|
|
|
Say |
|