Project BPL RM + PM Warehouse (Sub-structure) |
Item: 01A (A01) Earth work in Excavation |
|
Basis:1000
cft |
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Earth Work in Excavation |
1000.000 |
cft |
1.80 |
1800.00 |
|
|
Sub-Total(L1) |
1800.00
|
63.57
|
|
|
|
Total(1) |
|
63.57 |
|
Add over head on Total(1)
|
11.0 % |
6.99 |
|
|
|
Total(2) |
|
70.56 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
70.56 |
|
Add VAT on Unit Price |
4.5 % |
3.32 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
73.88
|
|
|
|
Say |
|
Item: 01B (A01F) Excavation beyond 1m with Excavat |
|
Basis:2825
cft |
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Diesel |
55.000 |
Ltr |
26.00 |
1430.00 |
|
Mobil |
12.000 |
Ltr |
70.00 |
840.00 |
|
Hydraulic Oil |
5.000 |
Ltr |
80.00 |
400.00 |
|
Excavator |
1.000 |
day |
8000.00 |
8000.00 |
|
|
Sub-Total(E1) |
10670.00
|
133.38
|
|
|
|
Total(1) |
|
133.38 |
|
Add over head on Total(1)
|
11.0 % |
14.67 |
|
|
|
Total(2) |
|
148.06 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
148.06 |
|
Add VAT on Unit Price |
4.5 % |
6.98 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
155.03
|
|
|
|
Say |
|
Item: 03 (A03F) (1.3.6) Mass Concrete |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Cement |
12.000 |
bag |
343.00 |
4116.00 |
|
Sand - Sylhet |
45.000 |
cft |
24.00 |
1080.00 |
|
Stone-chips |
90.000 |
cft |
80.00 |
7200.00 |
|
|
Sub-Total(A1) |
12396.00
|
4377.65
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mixer m/c and vibrator |
100.000 |
cft |
2.00 |
200.00 |
|
|
Sub-Total(E1) |
200.00
|
70.63
|
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
CC Work |
100.000 |
cft |
5.00 |
500.00 |
|
|
Sub-Total(L1) |
500.00
|
176.58
|
|
|
|
Total(1) |
|
4624.85 |
|
Add over head on Total(1)
|
11.0 % |
508.73 |
|
|
|
Total(2) |
|
5133.59 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
5133.59 |
|
Add VAT on Unit Price |
4.5 % |
241.90 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
5375.48
|
|
|
|
Say |
|
Item: 04 (A03G) 50mm DPC (1:1.5:3) |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
7.500 |
cft |
13.00 |
97.50 |
|
Cement |
4.000 |
bag |
343.00 |
1372.00 |
|
Stone-chips |
15.000 |
cft |
80.00 |
1200.00 |
|
Plastocrete super-Sika |
1.000 |
kg |
155.00 |
155.00 |
|
|
Sub-Total(A1) |
2824.50
|
304.03
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mixer m/c and vibrator |
16.700 |
cft |
2.00 |
33.40 |
|
|
Sub-Total(E1) |
33.40
|
3.60
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
D.P.C. |
100.000 |
sft |
3.00 |
300.00 |
|
|
Sub-Total(L0) |
300.00
|
32.29
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Wood shutter-3time |
1.110 |
cft |
350.00 |
388.50 |
|
|
Sub-Total(M1) |
388.50
|
41.82
|
|
|
|
Total(1) |
|
381.73 |
|
Add over head on Total(1)
|
11.0 % |
41.99 |
|
|
|
Total(2) |
|
423.73 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
423.73 |
|
Add VAT on Unit Price |
4.5 % |
19.97 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
443.69
|
|
|
|
Say |
|
Item: 05 (A03H) 25mm Hardonite floor finish |
|
Basis:100
sft |
|
|
|
Total(1) |
|
0.00 |
|
Add over head on Total(1)
|
11.0 % |
41.99 |
|
|
|
Total(2) |
|
423.73 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
423.73 |
|
Add VAT on Unit Price |
4.5 % |
19.97 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
443.69
|
|
|
|
Say |
|
Item: 05A (A03L) Hardonite Floor Finsh(Exc Labour) |
|
Basis:100
sft |
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Ordinary Labour Supply |
2.000 |
nos. |
100.00 |
200.00 |
|
Head Mason Supply |
1.000 |
nos. |
200.00 |
200.00 |
|
|
Sub-Total(L0) |
400.00
|
43.06
|
|
|
|
Total(1) |
|
43.06 |
|
Add over head on Total(1)
|
11.0 % |
4.74 |
|
|
|
Total(2) |
|
47.79 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
47.79 |
|
Add VAT on Unit Price |
4.5 % |
2.25 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
50.04
|
|
|
|
Say |
|
Item: 12A (A05) Sand Filling |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Filling Sand |
130.000 |
cft |
8.50 |
1105.00 |
|
|
Sub-Total(A1) |
1105.00
|
390.23
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mini Roller Compaction |
100.000 |
cft |
1.00 |
100.00 |
|
Mini Dumper |
130.000 |
cft |
2.00 |
260.00 |
|
Payloader |
0.000 |
day |
8000.00 |
0.00 |
|
Dump Truck |
0.000 |
day |
8300.00 |
0.00 |
|
|
Sub-Total(E1) |
360.00
|
127.13
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Ordinary Labour Supply |
0.800 |
nos. |
100.00 |
80.00 |
|
|
Sub-Total(L0) |
80.00
|
28.25
|
|
|
|
Total(1) |
|
545.62 |
|
Add over head on Total(1)
|
11.0 % |
60.02 |
|
|
|
Total(2) |
|
605.63 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
605.63 |
|
Add VAT on Unit Price |
4.5 % |
28.54 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
634.17
|
|
|
|
Say |
|
Item: 12B (A05D) Back filling-(Excluding Sand Supp |
|
Basis:100
cft |
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mini Roller Compaction |
25.000 |
cft |
1.00 |
25.00 |
|
Mini Dumper-Sand carrying |
50.000 |
cft |
1.00 |
50.00 |
|
|
Sub-Total(E1) |
75.00
|
26.49
|
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Filling |
100.000 |
cft |
1.00 |
100.00 |
|
|
Sub-Total(L1) |
100.00
|
35.32
|
|
|
|
Total(1) |
|
61.80 |
|
Add over head on Total(1)
|
11.0 % |
6.80 |
|
|
|
Total(2) |
|
68.60 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
68.60 |
|
Add VAT on Unit Price |
4.5 % |
3.23 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
71.83
|
|
|
|
Say |
|
Item: 08 (A06A) 125mm thick brick work (1:5) |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Brick |
500.000 |
no. |
3.80 |
1900.00 |
|
Sand - Local - Mymensingh |
17.000 |
cft |
13.00 |
221.00 |
|
Cement |
2.600 |
bag |
343.00 |
891.80 |
|
|
Sub-Total(A1) |
3012.80
|
324.30
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
125mm thick Brick Work |
100.000 |
sft |
6.00 |
600.00 |
|
|
Sub-Total(L0) |
600.00
|
64.58
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Scaffolding |
1.000 |
set |
100.00 |
100.00 |
|
|
Sub-Total(M1) |
100.00
|
10.76
|
|
|
|
Total(1) |
|
399.65 |
|
Add over head on Total(1)
|
11.0 % |
43.96 |
|
|
|
Total(2) |
|
443.61 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
443.61 |
|
Add VAT on Unit Price |
4.5 % |
20.90 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
464.51
|
|
|
|
Say |
|
Item: 09 (A06B) Brick Work 250mm in Foundation |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Brick |
1200.000 |
no. |
3.80 |
4560.00 |
|
Sand - Local - Mymensingh |
40.000 |
cft |
13.00 |
520.00 |
|
Cement |
5.000 |
bag |
343.00 |
1715.00 |
|
|
Sub-Total(A1) |
6795.00
|
2399.65
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
250mm Brickwork upto 7 ft |
100.000 |
cft |
4.25 |
425.00 |
|
|
Sub-Total(L0) |
425.00
|
150.09
|
|
|
|
Total(1) |
|
2549.74 |
|
Add over head on Total(1)
|
11.0 % |
280.47 |
|
|
|
Total(2) |
|
2830.21 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
2830.21 |
|
Add VAT on Unit Price |
4.5 % |
133.36 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
2963.58
|
|
|
|
Say |
|
Item: 06B (A08D) RCC (1:1.5:3) in GB/TB |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Cement |
22.000 |
bag |
343.00 |
7546.00 |
|
Sand - Sylhet |
43.000 |
cft |
24.00 |
1032.00 |
|
Stone-chips |
86.000 |
cft |
80.00 |
6880.00 |
|
|
Sub-Total(A1) |
15458.00
|
5458.99
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mixer m/c and vibrator |
100.000 |
cft |
2.00 |
200.00 |
|
Mini Dumper |
100.000 |
cft |
2.00 |
200.00 |
|
|
Sub-Total(E1) |
400.00
|
141.26
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Formwork upto 10ft from P |
242.000 |
sft |
8.00 |
1936.00 |
|
RCC Casting. |
100.000 |
cft |
8.00 |
800.00 |
|
|
Sub-Total(L0) |
2736.00
|
966.22
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel pipe with B-plate |
0.000 |
no |
11.00 |
0.00 |
|
wood use 5-time-Garjan |
0.100 |
cft |
850.00 |
85.00 |
|
Steel form,S-structure |
242.000 |
sft |
10.00 |
2420.00 |
|
Wood use-6time mango |
0.200 |
cft |
350.00 |
70.00 |
|
|
Sub-Total(M1) |
2575.00
|
909.36
|
|
|
|
Total(1) |
|
7475.83 |
|
Add over head on Total(1)
|
11.0 % |
822.34 |
|
|
|
Total(2) |
|
8298.17 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
8298.17 |
|
Add VAT on Unit Price |
4.5 % |
391.01 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
8689.19
|
|
|
|
Say |
|
Item: 06C (A08E) RCC (1:1.5:3) in Suspended slab |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Cement |
22.000 |
bag |
343.00 |
7546.00 |
|
Sand - Sylhet |
43.000 |
cft |
24.00 |
1032.00 |
|
Stone-chips |
86.000 |
cft |
80.00 |
6880.00 |
|
|
Sub-Total(A1) |
15458.00
|
5458.99
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mixer m/c and vibrator |
100.000 |
cft |
2.00 |
200.00 |
|
Mini Dumper |
0.000 |
cft |
2.00 |
0.00 |
|
|
Sub-Total(E1) |
200.00
|
70.63
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Formwork upto 10ft from P |
240.000 |
sft |
8.00 |
1920.00 |
|
RCC Casting. |
100.000 |
cft |
8.00 |
800.00 |
|
|
Sub-Total(L0) |
2720.00
|
960.57
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
wood use 5-time-Garjan |
0.500 |
cft |
850.00 |
425.00 |
|
B-plate with pipe |
0.000 |
no |
16.00 |
0.00 |
|
Steel form,S-structure |
240.000 |
sft |
10.00 |
2400.00 |
|
Steel beam,S-structure |
0.000 |
no |
40.00 |
0.00 |
|
Wood use-6time mango |
1.200 |
cft |
350.00 |
420.00 |
|
|
Sub-Total(M1) |
3245.00
|
1145.97
|
|
|
|
Total(1) |
|
7636.16 |
|
Add over head on Total(1)
|
11.0 % |
839.98 |
|
|
|
Total(2) |
|
8476.14 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
8476.14 |
|
Add VAT on Unit Price |
4.5 % |
399.40 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
8875.54
|
|
|
|
Say |
|
Item: 06D (A08J) R.C.C (1:1.5:3) P-prot. with NCF |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Cement |
23.000 |
bag |
343.00 |
7889.00 |
|
Sand - Sylhet |
43.000 |
cft |
24.00 |
1032.00 |
|
Stone-chips |
86.000 |
cft |
80.00 |
6880.00 |
|
|
Sub-Total(A1) |
15801.00
|
5580.12
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mixer m/c and vibrator |
100.000 |
cft |
2.00 |
200.00 |
|
Mini Dumper |
0.000 |
cft |
2.00 |
0.00 |
|
|
Sub-Total(E1) |
200.00
|
70.63
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Formwork upto 10ft from P |
200.000 |
sft |
8.00 |
1600.00 |
|
RCC Casting. |
100.000 |
cft |
8.00 |
800.00 |
|
|
Sub-Total(L0) |
2400.00
|
847.56
|
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
CC (50mm) With NCF |
200.000 |
sft |
3.00 |
600.00 |
|
|
Sub-Total(L1) |
600.00
|
211.89
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Forms |
200.000 |
sft |
5.00 |
1000.00 |
|
|
Sub-Total(M1) |
1000.00
|
353.15
|
|
|
|
Total(1) |
|
7063.35 |
|
Add over head on Total(1)
|
11.0 % |
776.97 |
|
|
|
Total(2) |
|
7840.32 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
7840.32 |
|
Add VAT on Unit Price |
4.5 % |
369.44 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
8209.76
|
|
|
|
Say |
|
Item: 06A (A08R) RCC Clmn (1:1.5:3) padestal |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Cement |
22.000 |
bag |
343.00 |
7546.00 |
|
Sand - Sylhet |
43.000 |
cft |
24.00 |
1032.00 |
|
Stone-chips |
86.000 |
cft |
80.00 |
6880.00 |
|
|
Sub-Total(A1) |
15458.00
|
5458.99
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mini Dumper |
100.000 |
cft |
2.00 |
200.00 |
|
Batching Plant , Vibrator |
100.000 |
cft |
8.00 |
800.00 |
|
|
Sub-Total(E1) |
1000.00
|
353.15
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Formwork upto 10ft from P |
305.000 |
sft |
8.00 |
2440.00 |
|
Sand Screening |
43.000 |
cft |
1.00 |
43.00 |
|
RCC Casting. |
100.000 |
cft |
8.00 |
800.00 |
|
|
Sub-Total(L0) |
3283.00
|
1159.39
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Forms |
305.000 |
sft |
5.00 |
1525.00 |
|
|
Sub-Total(M1) |
1525.00
|
538.55
|
|
|
|
Total(1) |
|
7510.09 |
|
Add over head on Total(1)
|
11.0 % |
826.11 |
|
|
|
Total(2) |
|
8336.20 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
8336.20 |
|
Add VAT on Unit Price |
4.5 % |
392.81 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
8729.00
|
|
|
|
Say |
|
Item: 07 (A10A) Re-bar Grade 60 |
|
Basis:1000
kg. |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
GI Wire |
10.000 |
kg |
90.00 |
900.00 |
|
Re-bar G60 |
1050.000 |
kg |
40.20 |
42210.00 |
|
|
Sub-Total(A1) |
43110.00
|
538.55
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Re-bar Work |
1000.000 |
kg |
1.65 |
1650.00 |
|
Local carrying Rod |
0.000 |
kg |
0.25 |
0.00 |
|
|
Sub-Total(L0) |
1650.00
|
538.55
|
|
|
|
Total(1) |
|
1077.11 |
|
Add over head on Total(1)
|
11.0 % |
118.48 |
|
|
|
Total(2) |
|
1195.59 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
1195.59 |
|
Add VAT on Unit Price |
4.5 % |
56.34 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
1251.93
|
|
|
|
Say |
|
Item: 10 (A12G) 12mmPlaster(1:6), Bitumen Coat |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
11.250 |
cft |
13.00 |
146.25 |
|
Cement |
1.000 |
bag |
343.00 |
343.00 |
|
|
Sub-Total(A1) |
489.25
|
52.66
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Dismentling F/W/Mar tile |
100.000 |
sft |
10.00 |
1000.00 |
|
Bitumen Paint |
50.000 |
sft |
1.00 |
50.00 |
|
|
Sub-Total(L0) |
1050.00
|
113.02
|
|
|
|
Total(1) |
|
165.68 |
|
Add over head on Total(1)
|
11.0 % |
18.23 |
|
|
|
Total(2) |
|
183.91 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
183.91 |
|
Add VAT on Unit Price |
4.5 % |
8.67 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
192.58
|
|
|
|
Say |
|
Item: 11 (A12H) 12mm Plaster (1:6) |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
11.250 |
cft |
13.00 |
146.25 |
|
Cement |
1.000 |
bag |
343.00 |
343.00 |
|
|
Sub-Total(A1) |
489.25
|
52.66
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Dismentling F/W/Mar tile |
100.000 |
sft |
10.00 |
1000.00 |
|
|
Sub-Total(L0) |
1000.00
|
107.64
|
|
|
|
Total(1) |
|
160.30 |
|
Add over head on Total(1)
|
11.0 % |
17.63 |
|
|
|
Total(2) |
|
177.94 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
177.94 |
|
Add VAT on Unit Price |
4.5 % |
8.38 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
186.32
|
|
|
|
Say |
|
Item: 02 (A18L) Pile head breaking |
|
Basis:10
cft |
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Dismantling RCC Pile head |
1.000 |
cft |
30.00 |
30.00 |
|
|
Sub-Total(L1) |
30.00
|
104.17
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Stone Cutting Disc - 175 |
1.000 |
no |
70.00 |
70.00 |
|
Diamond Cuting Disc- 175 |
0.100 |
no |
2200.00 |
220.00 |
|
Cheisel - Hammer |
1.000 |
no |
55.00 |
55.00 |
|
|
Sub-Total(M1) |
345.00
|
1198.00
|
|
|
|
Total(1) |
|
1302.18 |
|
Add over head on Total(1)
|
11.0 % |
143.24 |
|
|
|
Total(2) |
|
1445.41 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
1445.41 |
|
Add VAT on Unit Price |
4.5 % |
68.11 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
1513.52
|
|
|
|
Say |
|
Item: 13A (D04) Addil.Shutter-Warehouse-SubStruct |
|
Basis:1
no. |
|
|
|
Total(1) |
|
0.00 |
|
Add over head on Total(1)
|
11.0 % |
143.24 |
|
|
|
Total(2) |
|
1445.41 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
1445.41 |
|
Add VAT on Unit Price |
4.5 % |
68.11 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
1513.52
|
|
|
|
Say |
|