Return Main Menu

Project BPL RM + PM Warehouse (Sub-structure)
Item: 01A (A01) Earth work in Excavation
Basis:1000 cft
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Earth Work in Excavation
1000.000
cft
1.80
1800.00
Sub-Total(L1)
1800.00
63.57
Total(1)
63.57
Add over head on Total(1)
11.0 %
6.99
Total(2)
70.56
Add Profit on Total(2)
0.0 %
0.00
Total(3)
70.56
Add VAT on Unit Price
4.5 %
3.32
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
73.88
Say
74
per M3
Item: 01B (A01F) Excavation beyond 1m with Excavat
Basis:2825 cft
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Diesel
55.000
Ltr
26.00
1430.00
Mobil
12.000
Ltr
70.00
840.00
Hydraulic Oil
5.000
Ltr
80.00
400.00
Excavator
1.000
day
8000.00
8000.00
Sub-Total(E1)
10670.00
133.38
Total(1)
133.38
Add over head on Total(1)
11.0 %
14.67
Total(2)
148.06
Add Profit on Total(2)
0.0 %
0.00
Total(3)
148.06
Add VAT on Unit Price
4.5 %
6.98
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
155.03
Say
155
per M3
Item: 03 (A03F) (1.3.6) Mass Concrete
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement
12.000
bag
343.00
4116.00
Sand - Sylhet
45.000
cft
24.00
1080.00
Stone-chips
90.000
cft
80.00
7200.00
Sub-Total(A1)
12396.00
4377.65
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
100.000
cft
2.00
200.00
Sub-Total(E1)
200.00
70.63
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
CC Work
100.000
cft
5.00
500.00
Sub-Total(L1)
500.00
176.58
Total(1)
4624.85
Add over head on Total(1)
11.0 %
508.73
Total(2)
5133.59
Add Profit on Total(2)
0.0 %
0.00
Total(3)
5133.59
Add VAT on Unit Price
4.5 %
241.90
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
5375.48
Say
5375
per M3
Item: 04 (A03G) 50mm DPC (1:1.5:3)
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
7.500
cft
13.00
97.50
Cement
4.000
bag
343.00
1372.00
Stone-chips
15.000
cft
80.00
1200.00
Plastocrete super-Sika
1.000
kg
155.00
155.00
Sub-Total(A1)
2824.50
304.03
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
16.700
cft
2.00
33.40
Sub-Total(E1)
33.40
3.60
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
D.P.C.
100.000
sft
3.00
300.00
Sub-Total(L0)
300.00
32.29
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Wood shutter-3time
1.110
cft
350.00
388.50
Sub-Total(M1)
388.50
41.82
Total(1)
381.73
Add over head on Total(1)
11.0 %
41.99
Total(2)
423.73
Add Profit on Total(2)
0.0 %
0.00
Total(3)
423.73
Add VAT on Unit Price
4.5 %
19.97
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
443.69
Say
444
per M2
Item: 05 (A03H) 25mm Hardonite floor finish
Basis:100 sft
Total(1)
0.00
Add over head on Total(1)
11.0 %
41.99
Total(2)
423.73
Add Profit on Total(2)
0.0 %
0.00
Total(3)
423.73
Add VAT on Unit Price
4.5 %
19.97
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
443.69
Say
444
per M2
Item: 05A (A03L) Hardonite Floor Finsh(Exc Labour)
Basis:100 sft
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
2.000
nos.
100.00
200.00
Head Mason Supply
1.000
nos.
200.00
200.00
Sub-Total(L0)
400.00
43.06
Total(1)
43.06
Add over head on Total(1)
11.0 %
4.74
Total(2)
47.79
Add Profit on Total(2)
0.0 %
0.00
Total(3)
47.79
Add VAT on Unit Price
4.5 %
2.25
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
50.04
Say
50
per M2
Item: 12A (A05) Sand Filling
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Filling Sand
130.000
cft
8.50
1105.00
Sub-Total(A1)
1105.00
390.23
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mini Roller Compaction
100.000
cft
1.00
100.00
Mini Dumper
130.000
cft
2.00
260.00
Payloader
0.000
day
8000.00
0.00
Dump Truck
0.000
day
8300.00
0.00
Sub-Total(E1)
360.00
127.13
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
0.800
nos.
100.00
80.00
Sub-Total(L0)
80.00
28.25
Total(1)
545.62
Add over head on Total(1)
11.0 %
60.02
Total(2)
605.63
Add Profit on Total(2)
0.0 %
0.00
Total(3)
605.63
Add VAT on Unit Price
4.5 %
28.54
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
634.17
Say
634
per M3
Item: 12B (A05D) Back filling-(Excluding Sand Supp
Basis:100 cft
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mini Roller Compaction
25.000
cft
1.00
25.00
Mini Dumper-Sand carrying
50.000
cft
1.00
50.00
Sub-Total(E1)
75.00
26.49
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Filling
100.000
cft
1.00
100.00
Sub-Total(L1)
100.00
35.32
Total(1)
61.80
Add over head on Total(1)
11.0 %
6.80
Total(2)
68.60
Add Profit on Total(2)
0.0 %
0.00
Total(3)
68.60
Add VAT on Unit Price
4.5 %
3.23
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
71.83
Say
72
per M3
Item: 08 (A06A) 125mm thick brick work (1:5)
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
500.000
no.
3.80
1900.00
Sand - Local - Mymensingh
17.000
cft
13.00
221.00
Cement
2.600
bag
343.00
891.80
Sub-Total(A1)
3012.80
324.30
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
125mm thick Brick Work
100.000
sft
6.00
600.00
Sub-Total(L0)
600.00
64.58
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Scaffolding
1.000
set
100.00
100.00
Sub-Total(M1)
100.00
10.76
Total(1)
399.65
Add over head on Total(1)
11.0 %
43.96
Total(2)
443.61
Add Profit on Total(2)
0.0 %
0.00
Total(3)
443.61
Add VAT on Unit Price
4.5 %
20.90
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
464.51
Say
465
per M2
Item: 09 (A06B) Brick Work 250mm in Foundation
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
1200.000
no.
3.80
4560.00
Sand - Local - Mymensingh
40.000
cft
13.00
520.00
Cement
5.000
bag
343.00
1715.00
Sub-Total(A1)
6795.00
2399.65
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
250mm Brickwork upto 7 ft
100.000
cft
4.25
425.00
Sub-Total(L0)
425.00
150.09
Total(1)
2549.74
Add over head on Total(1)
11.0 %
280.47
Total(2)
2830.21
Add Profit on Total(2)
0.0 %
0.00
Total(3)
2830.21
Add VAT on Unit Price
4.5 %
133.36
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
2963.58
Say
2964
per M3
Item: 06B (A08D) RCC (1:1.5:3) in GB/TB
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement
22.000
bag
343.00
7546.00
Sand - Sylhet
43.000
cft
24.00
1032.00
Stone-chips
86.000
cft
80.00
6880.00
Sub-Total(A1)
15458.00
5458.99
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
100.000
cft
2.00
200.00
Mini Dumper
100.000
cft
2.00
200.00
Sub-Total(E1)
400.00
141.26
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Formwork upto 10ft from P
242.000
sft
8.00
1936.00
RCC Casting.
100.000
cft
8.00
800.00
Sub-Total(L0)
2736.00
966.22
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel pipe with B-plate
0.000
no
11.00
0.00
wood use 5-time-Garjan
0.100
cft
850.00
85.00
Steel form,S-structure
242.000
sft
10.00
2420.00
Wood use-6time mango
0.200
cft
350.00
70.00
Sub-Total(M1)
2575.00
909.36
Total(1)
7475.83
Add over head on Total(1)
11.0 %
822.34
Total(2)
8298.17
Add Profit on Total(2)
0.0 %
0.00
Total(3)
8298.17
Add VAT on Unit Price
4.5 %
391.01
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
8689.19
Say
8689
per M3
Item: 06C (A08E) RCC (1:1.5:3) in Suspended slab
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement
22.000
bag
343.00
7546.00
Sand - Sylhet
43.000
cft
24.00
1032.00
Stone-chips
86.000
cft
80.00
6880.00
Sub-Total(A1)
15458.00
5458.99
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
100.000
cft
2.00
200.00
Mini Dumper
0.000
cft
2.00
0.00
Sub-Total(E1)
200.00
70.63
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Formwork upto 10ft from P
240.000
sft
8.00
1920.00
RCC Casting.
100.000
cft
8.00
800.00
Sub-Total(L0)
2720.00
960.57
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
wood use 5-time-Garjan
0.500
cft
850.00
425.00
B-plate with pipe
0.000
no
16.00
0.00
Steel form,S-structure
240.000
sft
10.00
2400.00
Steel beam,S-structure
0.000
no
40.00
0.00
Wood use-6time mango
1.200
cft
350.00
420.00
Sub-Total(M1)
3245.00
1145.97
Total(1)
7636.16
Add over head on Total(1)
11.0 %
839.98
Total(2)
8476.14
Add Profit on Total(2)
0.0 %
0.00
Total(3)
8476.14
Add VAT on Unit Price
4.5 %
399.40
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
8875.54
Say
8876
per M3
Item: 06D (A08J) R.C.C (1:1.5:3) P-prot. with NCF
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement
23.000
bag
343.00
7889.00
Sand - Sylhet
43.000
cft
24.00
1032.00
Stone-chips
86.000
cft
80.00
6880.00
Sub-Total(A1)
15801.00
5580.12
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
100.000
cft
2.00
200.00
Mini Dumper
0.000
cft
2.00
0.00
Sub-Total(E1)
200.00
70.63
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Formwork upto 10ft from P
200.000
sft
8.00
1600.00
RCC Casting.
100.000
cft
8.00
800.00
Sub-Total(L0)
2400.00
847.56
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
CC (50mm) With NCF
200.000
sft
3.00
600.00
Sub-Total(L1)
600.00
211.89
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Forms
200.000
sft
5.00
1000.00
Sub-Total(M1)
1000.00
353.15
Total(1)
7063.35
Add over head on Total(1)
11.0 %
776.97
Total(2)
7840.32
Add Profit on Total(2)
0.0 %
0.00
Total(3)
7840.32
Add VAT on Unit Price
4.5 %
369.44
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
8209.76
Say
8210
per M3
Item: 06A (A08R) RCC Clmn (1:1.5:3) padestal
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement
22.000
bag
343.00
7546.00
Sand - Sylhet
43.000
cft
24.00
1032.00
Stone-chips
86.000
cft
80.00
6880.00
Sub-Total(A1)
15458.00
5458.99
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mini Dumper
100.000
cft
2.00
200.00
Batching Plant , Vibrator
100.000
cft
8.00
800.00
Sub-Total(E1)
1000.00
353.15
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Formwork upto 10ft from P
305.000
sft
8.00
2440.00
Sand Screening
43.000
cft
1.00
43.00
RCC Casting.
100.000
cft
8.00
800.00
Sub-Total(L0)
3283.00
1159.39
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Forms
305.000
sft
5.00
1525.00
Sub-Total(M1)
1525.00
538.55
Total(1)
7510.09
Add over head on Total(1)
11.0 %
826.11
Total(2)
8336.20
Add Profit on Total(2)
0.0 %
0.00
Total(3)
8336.20
Add VAT on Unit Price
4.5 %
392.81
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
8729.00
Say
8729
per M3
Item: 07 (A10A) Re-bar Grade 60
Basis:1000 kg.
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
GI Wire
10.000
kg
90.00
900.00
Re-bar G60
1050.000
kg
40.20
42210.00
Sub-Total(A1)
43110.00
538.55
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Re-bar Work
1000.000
kg
1.65
1650.00
Local carrying Rod
0.000
kg
0.25
0.00
Sub-Total(L0)
1650.00
538.55
Total(1)
1077.11
Add over head on Total(1)
11.0 %
118.48
Total(2)
1195.59
Add Profit on Total(2)
0.0 %
0.00
Total(3)
1195.59
Add VAT on Unit Price
4.5 %
56.34
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
1251.93
Say
1252
per TON
Item: 10 (A12G) 12mmPlaster(1:6), Bitumen Coat
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
11.250
cft
13.00
146.25
Cement
1.000
bag
343.00
343.00
Sub-Total(A1)
489.25
52.66
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Dismentling F/W/Mar tile
100.000
sft
10.00
1000.00
Bitumen Paint
50.000
sft
1.00
50.00
Sub-Total(L0)
1050.00
113.02
Total(1)
165.68
Add over head on Total(1)
11.0 %
18.23
Total(2)
183.91
Add Profit on Total(2)
0.0 %
0.00
Total(3)
183.91
Add VAT on Unit Price
4.5 %
8.67
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
192.58
Say
193
per M2
Item: 11 (A12H) 12mm Plaster (1:6)
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
11.250
cft
13.00
146.25
Cement
1.000
bag
343.00
343.00
Sub-Total(A1)
489.25
52.66
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Dismentling F/W/Mar tile
100.000
sft
10.00
1000.00
Sub-Total(L0)
1000.00
107.64
Total(1)
160.30
Add over head on Total(1)
11.0 %
17.63
Total(2)
177.94
Add Profit on Total(2)
0.0 %
0.00
Total(3)
177.94
Add VAT on Unit Price
4.5 %
8.38
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
186.32
Say
186
per M2
Item: 02 (A18L) Pile head breaking
Basis:10 cft
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Dismantling RCC Pile head
1.000
cft
30.00
30.00
Sub-Total(L1)
30.00
104.17
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Stone Cutting Disc - 175
1.000
no
70.00
70.00
Diamond Cuting Disc- 175
0.100
no
2200.00
220.00
Cheisel - Hammer
1.000
no
55.00
55.00
Sub-Total(M1)
345.00
1198.00
Total(1)
1302.18
Add over head on Total(1)
11.0 %
143.24
Total(2)
1445.41
Add Profit on Total(2)
0.0 %
0.00
Total(3)
1445.41
Add VAT on Unit Price
4.5 %
68.11
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
1513.52
Say
1514
per M3
Item: 13A (D04) Addil.Shutter-Warehouse-SubStruct
Basis:1 no.
Total(1)
0.00
Add over head on Total(1)
11.0 %
143.24
Total(2)
1445.41
Add Profit on Total(2)
0.0 %
0.00
Total(3)
1445.41
Add VAT on Unit Price
4.5 %
68.11
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
1513.52
Say
1514
per LS