Project Automatic Sliding Gate |
Item: 03 (A01) Earth work in Excavation |
|
Basis:1000
cft |
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Earth Work in Excavation |
1000.000 |
cft |
1.80 |
1800.00 |
|
|
Sub-Total(L1) |
1800.00
|
63.57
|
|
|
|
Total(1) |
|
63.57 |
|
Add over head on Total(1)
|
2.5 % |
1.59 |
|
|
|
Total(2) |
|
65.16 |
|
Add Profit on Total(2) |
8.0 % |
5.21
|
|
|
|
Total(3) |
|
70.37 |
|
Add VAT on Unit Price |
4.5 % |
3.46 |
Add Income Tax on Unit Price
|
4.0 % |
3.08 |
|
|
|
Unit Price |
|
76.91
|
|
|
|
Say |
|
Item: 04 (A02A) Brick Flat Soling- Road |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Filling Sand |
5.000 |
cft |
8.50 |
42.50 |
|
Brick |
300.000 |
no. |
3.80 |
1140.00 |
|
|
Sub-Total(A1) |
1182.50
|
127.28
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Ordinary Labour Supply |
0.100 |
nos. |
100.00 |
10.00 |
|
Head Mason Supply |
0.250 |
nos. |
200.00 |
50.00 |
|
|
Sub-Total(L0) |
60.00
|
6.46
|
|
|
|
Total(1) |
|
133.74 |
|
Add over head on Total(1)
|
2.5 % |
3.34 |
|
|
|
Total(2) |
|
137.09 |
|
Add Profit on Total(2) |
8.0 % |
10.97
|
|
|
|
Total(3) |
|
148.05 |
|
Add VAT on Unit Price |
4.5 % |
7.28 |
Add Income Tax on Unit Price
|
4.0 % |
6.47 |
|
|
|
Unit Price |
|
161.81
|
|
|
|
Say |
|
Item: 05 (A02F) Single layer polythene |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Polythene |
1.500 |
kg |
77.00 |
115.50 |
|
|
Sub-Total(A1) |
115.50
|
12.43
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Ordinary Labour Supply |
0.020 |
nos. |
100.00 |
2.00 |
|
|
Sub-Total(L0) |
2.00
|
0.22
|
|
|
|
Total(1) |
|
12.65 |
|
Add over head on Total(1)
|
2.5 % |
0.32 |
|
|
|
Total(2) |
|
12.96 |
|
Add Profit on Total(2) |
8.0 % |
1.04
|
|
|
|
Total(3) |
|
14.00 |
|
Add VAT on Unit Price |
4.5 % |
0.69 |
Add Income Tax on Unit Price
|
4.0 % |
0.61 |
|
|
|
Unit Price |
|
15.30
|
|
|
|
Say |
|
Item: 06 (A08O) RCC Drain (1:1.5:3) |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
14.333 |
cft |
13.00 |
186.33 |
|
Cement |
22.000 |
bag |
343.00 |
7546.00 |
|
Sand - Sylhet |
28.667 |
cft |
24.00 |
688.01 |
|
Stone-chips |
86.000 |
cft |
80.00 |
6880.00 |
|
|
Sub-Total(A1) |
15300.34
|
5403.31
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mixer m/c and vibrator |
100.000 |
cft |
2.00 |
200.00 |
|
Mini Dumper |
100.000 |
cft |
2.00 |
200.00 |
|
|
Sub-Total(E1) |
400.00
|
141.26
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Formwork upto 10ft from P |
400.000 |
sft |
8.00 |
3200.00 |
|
Sand Screening |
43.000 |
cft |
1.00 |
43.00 |
|
RCC Casting. |
100.000 |
cft |
8.00 |
800.00 |
|
|
Sub-Total(L0) |
4043.00
|
1427.79
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Forms |
400.000 |
sft |
5.00 |
2000.00 |
|
Steel pipe with B-plate |
80.000 |
no |
11.00 |
880.00 |
|
Wood use-6time mango |
2.500 |
cft |
350.00 |
875.00 |
|
|
Sub-Total(M1) |
3755.00
|
1326.08
|
|
|
|
Total(1) |
|
8298.44 |
|
Add over head on Total(1)
|
2.5 % |
207.46 |
|
|
|
Total(2) |
|
8505.90 |
|
Add Profit on Total(2) |
8.0 % |
680.47
|
|
|
|
Total(3) |
|
9186.37 |
|
Add VAT on Unit Price |
4.5 % |
451.79 |
Add Income Tax on Unit Price
|
4.0 % |
401.59 |
|
|
|
Unit Price |
|
10039.75
|
|
|
|
Say |
|
Item: 07 (A10C) Re-bar 60 grade Local |
|
Basis:1000
kg. |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
GI Wire |
8.000 |
kg |
90.00 |
720.00 |
|
Re-bar 60 grade Local |
1000.000 |
kg |
35.00 |
35000.00 |
|
|
Sub-Total(A1) |
35720.00
|
1326.08
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Re-bar Work |
1000.000 |
kg |
1.65 |
1650.00 |
|
|
Sub-Total(L0) |
1650.00
|
1326.08
|
|
|
|
Total(1) |
|
2652.16 |
|
Add over head on Total(1)
|
2.5 % |
66.30 |
|
|
|
Total(2) |
|
2718.46 |
|
Add Profit on Total(2) |
8.0 % |
217.48
|
|
|
|
Total(3) |
|
2935.94 |
|
Add VAT on Unit Price |
4.5 % |
144.39 |
Add Income Tax on Unit Price
|
4.0 % |
128.35 |
|
|
|
Unit Price |
|
3208.67
|
|
|
|
Say |
|
Item: 02 (A18I) Dismantling CC, BFS, HBB |
|
Basis:100
sft |
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Ordinary Labour Supply |
1.500 |
nos. |
100.00 |
150.00 |
|
|
Sub-Total(L0) |
150.00
|
16.15
|
|
|
|
Total(1) |
|
16.15 |
|
Add over head on Total(1)
|
2.5 % |
0.40 |
|
|
|
Total(2) |
|
16.55 |
|
Add Profit on Total(2) |
8.0 % |
1.32
|
|
|
|
Total(3) |
|
17.87 |
|
Add VAT on Unit Price |
4.5 % |
0.88 |
Add Income Tax on Unit Price
|
4.0 % |
0.78 |
|
|
|
Unit Price |
|
19.53
|
|
|
|
Say |
|
Item: 01 (A18J) Dismantling of MS gate-2 |
|
Basis:1
sft |
L5.Labour-MS Work |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
MS gate remove |
1.000 |
sft |
15.00 |
15.00 |
|
|
Sub-Total(L5) |
15.00
|
161.46
|
|
|
|
Total(1) |
|
161.46 |
|
Add over head on Total(1)
|
2.5 % |
4.04 |
|
|
|
Total(2) |
|
165.50 |
|
Add Profit on Total(2) |
8.0 % |
13.24
|
|
|
|
Total(3) |
|
178.74 |
|
Add VAT on Unit Price |
4.5 % |
8.79 |
Add Income Tax on Unit Price
|
4.0 % |
7.81 |
|
|
|
Unit Price |
|
195.34
|
|
|
|
Say |
|
Item: 08 (A20) Automatic Sliding Gate |
|
Basis:266
sft |
C1.Steel Structures |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
50x50x3mm ss angle |
83.206 |
rft |
200.00 |
16641.20 |
|
50x50x5mm ss angle |
51.180 |
rft |
300.00 |
15354.00 |
|
100x3mm ss plate |
72.000 |
kg |
250.00 |
18000.00 |
|
Rowl Bolt |
32.000 |
no |
75.00 |
2400.00 |
|
SS angle, plate polng G |
1.000 |
L.s |
2460.00 |
2460.00 |
|
Hollow box 75x50x3mm |
141.020 |
rft |
185.00 |
26088.70 |
|
MS rod incl.welded |
15.000 |
kg |
40.00 |
600.00 |
|
SS plate cutting |
72.000 |
kg |
25.00 |
1800.00 |
|
Welding rod SS |
2.000 |
box |
1000.00 |
2000.00 |
|
S.S Bracket |
4.000 |
no |
305.00 |
1220.00 |
|
Roller (Lilon) |
8.000 |
no |
85.00 |
680.00 |
|
Hollow Met (25x25x2.3mm) |
945.000 |
rft |
70.00 |
66150.00 |
|
|
Sub-Total(C1) |
153393.90
|
6199.34
|
L5.Labour-MS Work |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
SS angle,plate fixing G |
1.000 |
L.s |
2460.00 |
2460.00 |
|
Carrying G |
1.000 |
L.s |
1000.00 |
1000.00 |
|
Sliding gate fitting fixi |
266.340 |
sft |
150.00 |
39951.00 |
|
|
Sub-Total(L5) |
43411.00
|
1754.43
|
|
|
|
Total(1) |
|
7953.77 |
|
Add over head on Total(1)
|
2.5 % |
198.84 |
|
|
|
Total(2) |
|
8152.62 |
|
Add Profit on Total(2) |
8.0 % |
652.21
|
|
|
|
Total(3) |
|
8804.83 |
|
Add VAT on Unit Price |
4.5 % |
433.02 |
Add Income Tax on Unit Price
|
4.0 % |
384.91 |
|
|
|
Unit Price |
|
9622.76
|
|
|
|
Say |
|