Return Main Menu

Project MDI Finishing Work
Item: 03F (A11H) Aluminium Louver
Basis:1 sft
S2.Alum,SS/MS,FalseCeil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Aluminium Louver
1.000
sft
310.00
310.00
Sub-Total(S2)
310.00
3336.84
Total(1)
3336.84
Add over head on Total(1)
3.0 %
100.11
Total(2)
3436.95
Add Profit on Total(2)
8.0 %
274.96
Total(3)
3711.90
Add VAT on Unit Price
4.5 %
174.91
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
3886.81
Say
3887
per M2
Item: 01 (A13B1) Epoxy Paint - Floor-Final Coat
Basis:100 sft
A3.Material-Paint
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Epoxy Enamel
1.500
Ltr
387.00
580.50
Thinner-T6/T7
0.800
Ltr
46.00
36.80
Sub-Total(A3)
617.30
66.45
L6.Labour Paints
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Epoxy paint Wall(R/Final)
100.000
sft
1.50
150.00
Sub-Total(L6)
150.00
16.15
Total(1)
82.59
Add over head on Total(1)
3.0 %
2.48
Total(2)
85.07
Add Profit on Total(2)
8.0 %
6.81
Total(3)
91.88
Add VAT on Unit Price
4.5 %
4.33
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
96.20
Say
96
per M2
Item: 02 (A14C) Plaster board ceiling
Basis:100 sft
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Scaffolding
1.000
set
100.00
100.00
Sub-Total(M1)
100.00
10.76
S2.Alum,SS/MS,FalseCeil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Plaster Board Ceiling
100.000
sft
125.00
12500.00
Sub-Total(S2)
12500.00
1345.50
Total(1)
1356.26
Add over head on Total(1)
3.0 %
40.69
Total(2)
1396.95
Add Profit on Total(2)
8.0 %
111.76
Total(3)
1508.71
Add VAT on Unit Price
4.5 %
71.09
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
1579.80
Say
1580
per M2
Item: 03D (B13A) PVC Pipe 150D-L-150,25D-L-150
Basis:1 no.
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
uPVC Pipe 150 dia
1.000
rft
115.00
115.00
Sub-Total(B1)
115.00
115.00
L4.Labour-Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
uPVC Pipe fitting-100 mm
1.000
rft
15.00
15.00
Sub-Total(L4)
15.00
15.00
Total(1)
130.00
Add over head on Total(1)
3.0 %
3.90
Total(2)
133.90
Add Profit on Total(2)
8.0 %
10.71
Total(3)
144.61
Add VAT on Unit Price
4.5 %
6.81
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
151.43
Say
151
per NO.
Item: 03A (G03C) Wall Punch (200x100mm)
Basis:1 no.
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Head Mason Supply
0.500
nos.
200.00
100.00
Sub-Total(L0)
100.00
100.00
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Diamond Cutiing Disc -100
0.001
no
600.00
0.60
Cheisel - Hammer
0.500
no
55.00
27.50
Sub-Total(M1)
28.10
28.10
Total(1)
128.10
Add over head on Total(1)
3.0 %
3.84
Total(2)
131.94
Add Profit on Total(2)
8.0 %
10.56
Total(3)
142.50
Add VAT on Unit Price
4.5 %
6.71
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
149.21
Say
149
per NO.
Item: 03BC (G03E) Wall/ Ceiling Punch - 75mm dia
Basis:1 no.
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
1.000
nos.
100.00
100.00
Sub-Total(L0)
100.00
100.00
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Scaffolding
0.100
set
100.00
10.00
Cheisel - Hammer
1.000
no
55.00
55.00
Sub-Total(M1)
65.00
65.00
Total(1)
165.00
Add over head on Total(1)
3.0 %
4.95
Total(2)
169.95
Add Profit on Total(2)
8.0 %
13.60
Total(3)
183.55
Add VAT on Unit Price
4.5 %
8.65
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
192.19
Say
192
per NO.
Item: 03E (G03H) Louver Punch
Basis:1 no.
S2.Alum,SS/MS,FalseCeil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Aluminium Fabricator
2.000
no.
300.00
600.00
Sub-Total(S2)
600.00
600.00
Total(1)
600.00
Add over head on Total(1)
3.0 %
18.00
Total(2)
618.00
Add Profit on Total(2)
8.0 %
49.44
Total(3)
667.44
Add VAT on Unit Price
4.5 %
31.45
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
698.89
Say
699
per NO.