Project Cable Trench Cutting GH-Solvent Store
Item: 01 (A01A) Excavtion with shoring
Basis:2825 cft
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Diesel
92.000
Ltr
26.00
2392.00
Mobil
25.000
Ltr
70.00
1750.00
Hydraulic Oil
14.000
Ltr
80.00
1120.00
Excavator
1.000
day
8000.00
8000.00
Payloader
0.600
day
8000.00
4800.00
Labour
3.000
no
100.00
300.00
Exc-Carrying Trailer
0.200
day
5000.00
1000.00
Sub-Total(E1)
19362.00
242.04
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Shoring for pile E-Cuttin
129.160
sft
50.00
6458.00
Sub-Total(M1)
6458.00
80.73
Total(1)
322.77
Add over head on Total(1)
3.0 %
9.68
Total(2)
332.46
Add Profit on Total(2)
8.0 %
26.60
Total(3)
359.05
Add VAT on Unit Price
4.5 %
16.92
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
375.97
Say
376
per M3