Return Main Menu

Project Approach Road for Solvent Store
Item: 03 (A02B) Brick Flat Soling
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Filling Sand
5.000
cft
8.50
42.50
Brick
300.000
no.
3.80
1140.00
Sub-Total(A1)
1182.50
127.28
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
0.100
nos.
100.00
10.00
Head Mason Supply
0.250
nos.
200.00
50.00
Sub-Total(L0)
60.00
6.46
Total(1)
133.74
Add over head on Total(1)
3.0 %
4.01
Total(2)
137.75
Add Profit on Total(2)
8.0 %
11.02
Total(3)
148.78
Add VAT on Unit Price
4.5 %
7.01
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
155.79
Say
156
per M2
Item: 06C (A02H) BFS with m-joint(1:4)-3% pudlu
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
300.000
no.
3.80
1140.00
Sand - Local - Mymensingh
5.000
cft
13.00
65.00
Cement
2.000
bag
343.00
686.00
Pudloo
3.000
kg
70.00
210.00
Sub-Total(A1)
2101.00
226.15
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
BFS with Morter joint
100.000
sft
1.50
150.00
Sub-Total(L1)
150.00
16.15
Total(1)
242.30
Add over head on Total(1)
3.0 %
7.27
Total(2)
249.57
Add Profit on Total(2)
8.0 %
19.97
Total(3)
269.53
Add VAT on Unit Price
4.5 %
12.70
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
282.23
Say
282
per M2
Item: 06E (A02N) Turfing
Basis:100 sft
S1.Sub-contractor-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Turfing
100.000
sft
1.00
100.00
Sub-Total(S1)
100.00
10.76
Total(1)
10.76
Add over head on Total(1)
3.0 %
0.32
Total(2)
11.09
Add Profit on Total(2)
8.0 %
0.89
Total(3)
11.97
Add VAT on Unit Price
4.5 %
0.56
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
12.54
Say
13
per M2
Item: 06B (A02P) 75mm CC With Polythene Sheet
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
3.750
cft
13.00
48.75
Polythene
3.000
kg
77.00
231.00
Cement
5.000
bag
343.00
1715.00
Sand - Sylhet
7.500
cft
24.00
180.00
Brick-chips
22.500
cft
40.00
900.00
Sub-Total(A1)
3074.75
330.97
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
25.000
cft
2.00
50.00
Sub-Total(E1)
50.00
5.38
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
RCC Casting.
25.000
cft
8.00
200.00
Sub-Total(L0)
200.00
21.53
Total(1)
357.88
Add over head on Total(1)
3.0 %
10.74
Total(2)
368.61
Add Profit on Total(2)
8.0 %
29.49
Total(3)
398.10
Add VAT on Unit Price
4.5 %
18.76
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
416.86
Say
417
per M2
Item: 02 (A03O) HBB
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Filling Sand
8.000
cft
8.50
68.00
Brick
500.000
no.
3.80
1900.00
Sub-Total(A1)
1968.00
211.84
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
0.200
nos.
100.00
20.00
Head Mason Supply
0.500
nos.
200.00
100.00
Sub-Total(L0)
120.00
12.92
Total(1)
224.75
Add over head on Total(1)
3.0 %
6.74
Total(2)
231.49
Add Profit on Total(2)
8.0 %
18.52
Total(3)
250.01
Add VAT on Unit Price
4.5 %
11.78
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
261.80
Say
262
per M2
Item: 06A (A03O1) Plinth Protection HBB
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
500.000
no.
3.80
1900.00
Sand - Local - Mymensingh
16.000
cft
13.00
208.00
Cement
2.600
bag
343.00
891.80
Sub-Total(A1)
2999.80
322.90
Total(1)
322.90
Add over head on Total(1)
3.0 %
9.69
Total(2)
332.59
Add Profit on Total(2)
8.0 %
26.61
Total(3)
359.19
Add VAT on Unit Price
4.5 %
16.93
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
376.12
Say
376
per M2
Item: 04 (A03P) Brick on Edging
Basis:100 rft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Filling Sand
5.000
cft
8.50
42.50
Brick
270.000
no.
3.80
1026.00
Sub-Total(A1)
1068.50
322.90
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
0.400
nos.
100.00
40.00
Head Mason Supply
0.300
nos.
200.00
60.00
Sub-Total(L0)
100.00
322.90
Total(1)
645.80
Add over head on Total(1)
3.0 %
19.37
Total(2)
665.17
Add Profit on Total(2)
8.0 %
53.21
Total(3)
718.38
Add VAT on Unit Price
4.5 %
33.85
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
752.24
Say
752
per RM
Item: 01B (A05) Sand Filling
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Filling Sand
130.000
cft
8.50
1105.00
Sub-Total(A1)
1105.00
390.23
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mini Roller Compaction
100.000
cft
1.00
100.00
Mini Dumper
130.000
cft
2.00
260.00
Payloader
0.000
day
8000.00
0.00
Dump Truck
0.000
day
8300.00
0.00
Sub-Total(E1)
360.00
127.13
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
0.800
nos.
100.00
80.00
Sub-Total(L0)
80.00
28.25
Total(1)
545.62
Add over head on Total(1)
3.0 %
16.37
Total(2)
561.99
Add Profit on Total(2)
8.0 %
44.96
Total(3)
606.94
Add VAT on Unit Price
4.5 %
28.60
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
635.54
Say
636
per M3
Item: 01A (A05A) Sand filling bott of road-95%comp
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Filling Sand
130.000
cft
8.50
1105.00
Sub-Total(A1)
1105.00
390.23
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Roller hire ch. i/c fuel
0.050
day
6500.00
325.00
Wheel Loader-Road
0.010
day
10000.00
100.00
Gradder-Road
0.001
day
10000.00
10.00
Sub-Total(E1)
435.00
153.62
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
1.000
nos.
100.00
100.00
Sub-Total(L0)
100.00
35.32
Total(1)
579.17
Add over head on Total(1)
3.0 %
17.37
Total(2)
596.54
Add Profit on Total(2)
8.0 %
47.72
Total(3)
644.26
Add VAT on Unit Price
4.5 %
30.36
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
674.62
Say
675
per M3
Item: 05 (A05C) 400mm thick Sub-base (40:60)
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Filling Sand
52.000
cft
8.50
442.00
Brick
819.000
no.
3.80
3112.20
Sub-Total(A1)
3554.20
1255.17
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Roller hire ch. i/c fuel
0.140
day
6500.00
910.00
Wheel Loader-Road
0.002
day
10000.00
20.00
Sub-Total(E1)
930.00
328.43
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
2.000
nos.
100.00
200.00
Brick-chips making 1 1/2"
819.000
no.
0.33
270.27
Sub-Total(L0)
470.27
166.08
Total(1)
1749.67
Add over head on Total(1)
3.0 %
52.49
Total(2)
1802.16
Add Profit on Total(2)
8.0 %
144.17
Total(3)
1946.33
Add VAT on Unit Price
4.5 %
91.71
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
2038.05
Say
2038
per M3
Item: 06F (A05G1) Earth Filling
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Filling Earth
130.000
cft
6.60
858.00
Sub-Total(A1)
858.00
303.00
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mini Roller Compaction
100.000
cft
1.00
100.00
Sub-Total(E1)
100.00
35.32
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
1.000
nos.
100.00
100.00
Sub-Total(L0)
100.00
35.32
Total(1)
373.63
Add over head on Total(1)
3.0 %
11.21
Total(2)
384.84
Add Profit on Total(2)
8.0 %
30.79
Total(3)
415.63
Add VAT on Unit Price
4.5 %
19.58
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
435.21
Say
435
per M3
Item: 06D (A08S1) Pre-cast RCC Kerb fitting
Basis:2 rft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
7.000
no.
3.80
26.60
Sand - Local - Mymensingh
1.000
cft
13.00
13.00
Cement
0.120
bag
343.00
41.16
Brick-chips
0.600
cft
40.00
24.00
Sub-Total(A1)
104.76
35.32
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
1.000
nos.
100.00
100.00
Head Mason Supply
0.150
nos.
200.00
30.00
Sub-Total(L0)
130.00
35.32
Total(1)
70.63
Add over head on Total(1)
3.0 %
2.12
Total(2)
72.75
Add Profit on Total(2)
8.0 %
5.82
Total(3)
78.57
Add VAT on Unit Price
4.5 %
3.70
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
82.27
Say
82
per RM