Return Main Menu

Project CC Block/Casting Warehouse N & N-E Area
Item: 02 (A01C) Earth Excavation
Basis:100 cft
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Earth Work in Excavation
100.000
cft
1.80
180.00
Sub-Total(L1)
180.00
63.57
Total(1)
63.57
Add over head on Total(1)
3.0 %
1.91
Total(2)
65.47
Add Profit on Total(2)
8.0 %
5.24
Total(3)
70.71
Add VAT on Unit Price
4.5 %
3.33
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
74.04
Say
74
per M3
Item: 04 (A02B) Brick Flat Soling
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Filling Sand
5.000
cft
8.50
42.50
Brick
300.000
no.
3.80
1140.00
Sub-Total(A1)
1182.50
127.28
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
0.100
nos.
100.00
10.00
Head Mason Supply
0.250
nos.
200.00
50.00
Sub-Total(L0)
60.00
6.46
Total(1)
133.74
Add over head on Total(1)
3.0 %
4.01
Total(2)
137.75
Add Profit on Total(2)
8.0 %
11.02
Total(3)
148.78
Add VAT on Unit Price
4.5 %
7.01
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
155.79
Say
156
per M2
Item: 05 (A02F) Single layer polythene
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Polythene
1.500
kg
77.00
115.50
Sub-Total(A1)
115.50
12.43
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
0.020
nos.
100.00
2.00
Sub-Total(L0)
2.00
0.22
Total(1)
12.65
Add over head on Total(1)
3.0 %
0.38
Total(2)
13.03
Add Profit on Total(2)
8.0 %
1.04
Total(3)
14.07
Add VAT on Unit Price
4.5 %
0.66
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
14.73
Say
15
per M2
Item: 07 (A03B) Pre-cast CC (1:1.5:3) Block-50mm
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
2.443
cft
13.00
31.76
Cement
3.740
bag
343.00
1282.82
Sand - Sylhet
4.886
cft
24.00
117.26
Stone-chips
14.620
cft
80.00
1169.60
Wire Mesh
105.000
sft
7.00
735.00
Sub-Total(A1)
3336.44
359.13
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Pre-cast block fitting
45.860
no
25.00
1146.50
Sub-Total(L1)
1146.50
123.41
Total(1)
482.54
Add over head on Total(1)
3.0 %
14.48
Total(2)
497.02
Add Profit on Total(2)
8.0 %
39.76
Total(3)
536.78
Add VAT on Unit Price
4.5 %
25.29
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
562.08
Say
562
per M2
Item: 13B (A03E) 75 mm thick CC with NCF
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
3.750
cft
13.00
48.75
Cement
5.000
bag
343.00
1715.00
Sand - Sylhet
7.500
cft
24.00
180.00
Brick-chips
22.500
cft
40.00
900.00
Sub-Total(A1)
2843.75
306.10
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
25.000
cft
2.00
50.00
Sub-Total(E1)
50.00
5.38
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
CC Work
25.000
cft
5.00
125.00
Sub-Total(L1)
125.00
13.46
Total(1)
324.94
Add over head on Total(1)
3.0 %
9.75
Total(2)
334.69
Add Profit on Total(2)
8.0 %
26.77
Total(3)
361.46
Add VAT on Unit Price
4.5 %
17.03
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
378.49
Say
378
per M2
Item: 08 (A03E1) 62.5mm CC(1:2:4)
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
9.450
cft
13.00
122.85
Cement
3.780
bag
343.00
1296.54
Brick-chips
18.900
cft
40.00
756.00
Sub-Total(A1)
2175.39
234.16
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
1.000
nos.
100.00
100.00
Head Mason Supply
0.500
nos.
200.00
100.00
Sub-Total(L0)
200.00
21.53
Total(1)
255.69
Add over head on Total(1)
3.0 %
7.67
Total(2)
263.36
Add Profit on Total(2)
8.0 %
21.07
Total(3)
284.43
Add VAT on Unit Price
4.5 %
13.40
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
297.83
Say
298
per M2
Item: 03 (A05) Sand Filling
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Filling Sand
130.000
cft
8.50
1105.00
Sub-Total(A1)
1105.00
390.23
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mini Roller Compaction
100.000
cft
1.00
100.00
Mini Dumper
130.000
cft
2.00
260.00
Payloader
0.000
day
8000.00
0.00
Dump Truck
0.000
day
8300.00
0.00
Sub-Total(E1)
360.00
127.13
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
0.800
nos.
100.00
80.00
Sub-Total(L0)
80.00
28.25
Total(1)
545.62
Add over head on Total(1)
3.0 %
16.37
Total(2)
561.99
Add Profit on Total(2)
8.0 %
44.96
Total(3)
606.94
Add VAT on Unit Price
4.5 %
28.60
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
635.54
Say
636
per M3
Item: 09A (A08H) Rcc Ins. pit (500x500x500)-in-in
Basis:1 no.
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Filling Sand
8.580
cft
8.50
72.93
Brick
27.000
no.
3.80
102.60
Sand - Local - Mymensingh
5.400
cft
13.00
70.20
Cement
3.000
bag
343.00
1029.00
Stone-chips
10.500
cft
80.00
840.00
Re-bar - G40
40.000
kg
38.50
1540.00
Sub-Total(A1)
3654.73
3654.73
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
9.820
cft
2.00
19.64
Sub-Total(E1)
19.64
19.64
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Re-bar Work
33.000
kg
1.65
54.45
Sub-Total(L0)
54.45
54.45
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Earth Work in Excavation
13.000
cft
1.80
23.40
Filling
13.000
cft
1.00
13.00
Plaster Work
26.910
sft
3.00
80.73
RCC Work
11.410
cft
6.00
68.46
Form work
35.000
sft
8.00
280.00
Sub-Total(L1)
465.59
465.59
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Wood shutter-3time
1.000
cft
350.00
350.00
Sub-Total(M1)
350.00
350.00
Total(1)
4544.41
Add over head on Total(1)
3.0 %
136.33
Total(2)
4680.74
Add Profit on Total(2)
8.0 %
374.46
Total(3)
5055.20
Add VAT on Unit Price
4.5 %
238.20
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
5293.40
Say
5293
per NO
Item: 09B (A08H1) Masonry Inspection Pit 500x500
Basis:1 no.
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
86.000
no.
3.80
326.80
Sand - Local - Mymensingh
5.400
cft
13.00
70.20
Cement
3.000
bag
343.00
1029.00
Stone-chips
0.370
cft
80.00
29.60
Re-bar - G40
1.000
kg
38.50
38.50
Sub-Total(A1)
1494.10
1494.10
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Re-bar Work
0.900
kg
1.65
1.49
Formwork upto 10ft from P
2.690
sft
8.00
21.52
Ordinary Labour Supply
0.130
nos.
100.00
13.00
Dismentling F/W/Mar tile
11.310
sft
10.00
113.10
RCC Casting.
0.410
cft
8.00
3.28
Sub-Total(L0)
152.39
152.39
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Forms
2.690
sft
5.00
13.45
Sub-Total(M1)
13.45
13.45
Total(1)
1659.94
Add over head on Total(1)
3.0 %
49.80
Total(2)
1709.73
Add Profit on Total(2)
8.0 %
136.78
Total(3)
1846.51
Add VAT on Unit Price
4.5 %
87.01
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
1933.52
Say
1934
per NO.
Item: 10 (A08H2) Re-aarangement of Inspectiion Pit
Basis:1 no.
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
26.000
no.
3.80
98.80
Sand - Local - Mymensingh
2.500
cft
13.00
32.50
Cement
1.000
bag
343.00
343.00
Stone-chips
0.370
cft
80.00
29.60
Re-bar - G40
1.000
kg
38.50
38.50
Sub-Total(A1)
542.40
542.40
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Re-bar Work
0.900
kg
1.65
1.49
Formwork upto 10ft from P
2.690
sft
8.00
21.52
Ordinary Labour Supply
0.130
nos.
100.00
13.00
Dismentling F/W/Mar tile
11.310
sft
10.00
113.10
Sub-Total(L0)
149.11
149.11
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Forms
2.690
sft
5.00
13.45
Sub-Total(M1)
13.45
13.45
Total(1)
704.96
Add over head on Total(1)
3.0 %
21.15
Total(2)
726.10
Add Profit on Total(2)
8.0 %
58.09
Total(3)
784.19
Add VAT on Unit Price
4.5 %
36.95
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
821.14
Say
821
per NO.
Item: 10A (A08H3) CI Manhole Cover
Basis:1 no.
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
1.000
cft
13.00
13.00
Cement
0.200
bag
343.00
68.60
Sub-Total(A1)
81.60
81.60
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
CI Cover 300 mm dia
1.000
no.
750.00
750.00
Sub-Total(B1)
750.00
750.00
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
0.500
nos.
100.00
50.00
Head Mason Supply
0.500
nos.
200.00
100.00
Sub-Total(L0)
150.00
150.00
Total(1)
981.60
Add over head on Total(1)
3.0 %
29.45
Total(2)
1011.05
Add Profit on Total(2)
8.0 %
80.88
Total(3)
1091.93
Add VAT on Unit Price
4.5 %
51.45
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
1143.38
Say
1143
per NO.
Item: 06 (A08O) RCC Drain (1:1.5:3)
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
14.333
cft
13.00
186.33
Cement
22.000
bag
343.00
7546.00
Sand - Sylhet
28.667
cft
24.00
688.01
Stone-chips
86.000
cft
80.00
6880.00
Sub-Total(A1)
15300.34
5403.31
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
100.000
cft
2.00
200.00
Mini Dumper
100.000
cft
2.00
200.00
Sub-Total(E1)
400.00
141.26
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Formwork upto 10ft from P
400.000
sft
8.00
3200.00
Sand Screening
43.000
cft
1.00
43.00
RCC Casting.
100.000
cft
8.00
800.00
Sub-Total(L0)
4043.00
1427.79
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Forms
400.000
sft
5.00
2000.00
Steel pipe with B-plate
80.000
no
11.00
880.00
Wood use-6time mango
2.500
cft
350.00
875.00
Sub-Total(M1)
3755.00
1326.08
Total(1)
8298.44
Add over head on Total(1)
3.0 %
248.95
Total(2)
8547.39
Add Profit on Total(2)
8.0 %
683.79
Total(3)
9231.18
Add VAT on Unit Price
4.5 %
434.98
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
9666.16
Say
9666
per M3
Item: 11 (A08S2) Pre-cast RCC Kerb i/c Re-bar
Basis:210 rft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
13.750
cft
13.00
178.75
Cement
22.000
bag
343.00
7546.00
Sand - Sylhet
27.500
cft
24.00
660.00
Stone-chips
90.000
cft
80.00
7200.00
GI Wire
2.330
kg
90.00
209.70
Re-bar G60
334.090
kg
40.20
13430.42
Sub-Total(A1)
29224.87
1326.08
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
100.000
cft
2.00
200.00
Sub-Total(E1)
200.00
1326.08
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Re-bar Work
334.090
kg
1.65
551.25
Formwork upto 10ft from P
200.000
sft
8.00
1600.00
Ordinary Labour Supply
10.000
nos.
100.00
1000.00
Head Mason Supply
5.000
nos.
200.00
1000.00
Sub-Total(L0)
4151.25
1326.08
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Forms
200.000
sft
5.00
1000.00
Sub-Total(M1)
1000.00
1326.08
Total(1)
5304.31
Add over head on Total(1)
3.0 %
159.13
Total(2)
5463.44
Add Profit on Total(2)
8.0 %
437.08
Total(3)
5900.52
Add VAT on Unit Price
4.5 %
278.03
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
6178.55
Say
6179
per RM
Item: 01A (A09E1) Dismantling of CC
Basis:1 sft
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
0.030
nos.
100.00
3.00
Sub-Total(L0)
3.00
32.29
Total(1)
32.29
Add over head on Total(1)
3.0 %
0.97
Total(2)
33.26
Add Profit on Total(2)
8.0 %
2.66
Total(3)
35.92
Add VAT on Unit Price
4.5 %
1.69
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
37.61
Say
38
per M2
Item: 01B (A09H) Dismantling of 125mm b/wall
Basis:1 sft
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
0.060
nos.
100.00
6.00
Sub-Total(L0)
6.00
64.58
Total(1)
64.58
Add over head on Total(1)
3.0 %
1.94
Total(2)
66.52
Add Profit on Total(2)
8.0 %
5.32
Total(3)
71.84
Add VAT on Unit Price
4.5 %
3.39
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
75.23
Say
75
per M2
Item: 13F (A12B) Plaster 12mm thick (1:4)
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
7.500
cft
13.00
97.50
Cement
1.000
bag
343.00
343.00
Sub-Total(A1)
440.50
47.42
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Plaster Work
100.000
sft
3.00
300.00
Sub-Total(L1)
300.00
32.29
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Scaffolding
1.000
set
100.00
100.00
Sub-Total(M1)
100.00
10.76
Total(1)
90.47
Add over head on Total(1)
3.0 %
2.71
Total(2)
93.19
Add Profit on Total(2)
8.0 %
7.45
Total(3)
100.64
Add VAT on Unit Price
4.5 %
4.74
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
105.38
Say
105
per M2
Item: 13G (A13F) Weather coat paint
Basis:100 sft
A3.Material-Paint
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Plastron Sealer
0.500
Ltr
160.00
80.00
Enamel paint
0.250
Ltr
170.00
42.50
Snowcel
2.500
kg
7.60
19.00
Thinner-T6/T7
0.500
Ltr
46.00
23.00
Weather Coat (ColorBank)
1.420
Ltr
227.85
323.55
Sub-Total(A3)
488.05
52.53
L6.Labour Paints
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Weather coat painting
100.000
sft
4.00
400.00
Sub-Total(L6)
400.00
43.06
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Scaffolding
1.000
set
100.00
100.00
Sub-Total(M1)
100.00
10.76
Total(1)
106.35
Add over head on Total(1)
3.0 %
3.19
Total(2)
109.54
Add Profit on Total(2)
8.0 %
8.76
Total(3)
118.31
Add VAT on Unit Price
4.5 %
5.57
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
123.88
Say
124
per M2
Item: 13D (B01B2) uPVC Pipe 75mm dia
Basis:1 rft
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
PVC Pipe - 75mm dia
1.050
rft
50.00
52.50
S-cement tube
0.100
no
190.00
19.00
Sub-Total(B1)
71.50
10.76
B2.Sanitary fittings
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
PVC Fittings-75mm dia
1.000
rft
10.00
10.00
Sub-Total(B2)
10.00
10.76
L4.Labour-Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
PVC Pipe fitting 75mm dia
1.000
rft
7.00
7.00
Sub-Total(L4)
7.00
10.76
Total(1)
32.29
Add over head on Total(1)
3.0 %
0.97
Total(2)
33.26
Add Profit on Total(2)
8.0 %
2.66
Total(3)
35.92
Add VAT on Unit Price
4.5 %
1.69
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
37.61
Say
38
per RM
Item: 13E (B01C2) uPVC Pipe 25mm dia
Basis:1 rft
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
PVC Pipe - 75mm dia
1.000
rft
50.00
50.00
S-cement tube
0.010
no
190.00
1.90
Sub-Total(B1)
51.90
10.76
B2.Sanitary fittings
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
PVC fitting - 25mm dia
1.000
rft
2.00
2.00
Sub-Total(B2)
2.00
10.76
L4.Labour-Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
PVC Pipe fitting -25mm di
1.000
rft
3.00
3.00
Sub-Total(L4)
3.00
10.76
Total(1)
32.29
Add over head on Total(1)
3.0 %
0.97
Total(2)
33.26
Add Profit on Total(2)
8.0 %
2.66
Total(3)
35.92
Add VAT on Unit Price
4.5 %
1.69
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
37.61
Say
38
per RM
Item: 12 (F000) 150mm RCC Pipe
Basis:1 rft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
3.000
no.
3.80
11.40
Sand - Local - Mymensingh
0.540
cft
13.00
7.02
Cement
0.216
bag
343.00
74.09
Brick-chips
1.080
cft
40.00
43.20
Sub-Total(A1)
135.71
10.76
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
RCC Pipe 6" dia
1.050
rft
66.00
69.30
150mm dia Socket
0.250
no.
50.00
12.50
Sub-Total(B1)
81.80
10.76
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Earth Work in Excavation
2.640
cft
1.80
4.75
Brck flat soling
1.000
sft
0.60
0.60
CC Work
1.200
cft
5.00
6.00
150mm dia RCC Pipe
1.000
rft
20.00
20.00
Sub-Total(L1)
31.35
10.76
Total(1)
32.29
Add over head on Total(1)
3.0 %
0.97
Total(2)
33.26
Add Profit on Total(2)
8.0 %
2.66
Total(3)
35.92
Add VAT on Unit Price
4.5 %
1.69
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
37.61
Say
38
per RM