Return Main Menu

Project Sub-station Upgrade
Item: 15C (A03E) 75 mm thick CC with NCF
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
3.750
cft
13.00
48.75
Cement
5.000
bag
343.00
1715.00
Sand - Sylhet
7.500
cft
24.00
180.00
Brick-chips
22.500
cft
40.00
900.00
Sub-Total(A1)
2843.75
306.10
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
25.000
cft
2.00
50.00
Sub-Total(E1)
50.00
5.38
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
CC Work
25.000
cft
5.00
125.00
Sub-Total(L1)
125.00
13.46
Total(1)
324.94
Add over head on Total(1)
3.0 %
9.75
Total(2)
334.69
Add Profit on Total(2)
8.0 %
26.77
Total(3)
361.46
Add VAT on Unit Price
4.5 %
17.03
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
378.49
Say
378
per M2
Item: 03 (A03Q) Duct Filling,CC,Plaster NCF
Basis:1 no.
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
5.000
cft
13.00
65.00
Cement
0.500
bag
343.00
171.50
Brick-chips
10.000
cft
40.00
400.00
Sub-Total(A1)
636.50
636.50
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
2.000
nos.
100.00
200.00
Head Mason Supply
1.000
nos.
200.00
200.00
Sub-Total(L0)
400.00
400.00
Total(1)
1036.50
Add over head on Total(1)
3.0 %
31.10
Total(2)
1067.60
Add Profit on Total(2)
8.0 %
85.41
Total(3)
1153.00
Add VAT on Unit Price
4.5 %
54.33
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
1207.33
Say
1207
per NO.
Item: 05 (A06C) 250mm thick B-wall (1:5) - Supers
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
1200.000
no.
3.80
4560.00
Sand - Local - Mymensingh
40.000
cft
13.00
520.00
Cement
6.000
bag
343.00
2058.00
Sub-Total(A1)
7138.00
2520.78
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
B/w:15.5-27ft Scffld(Part
100.000
cft
6.00
600.00
Sub-Total(L0)
600.00
211.89
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Scaffolding
1.000
set
100.00
100.00
Sub-Total(M1)
100.00
35.32
Total(1)
2767.99
Add over head on Total(1)
3.0 %
83.04
Total(2)
2851.03
Add Profit on Total(2)
8.0 %
228.08
Total(3)
3079.11
Add VAT on Unit Price
4.5 %
145.09
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
3224.20
Say
3224
per M3
Item: 04 (A06F) 125 B/Wall (1:4)
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
500.000
no.
3.80
1900.00
Sand - Local - Mymensingh
17.000
cft
13.00
221.00
Cement
3.000
bag
343.00
1029.00
Sub-Total(A1)
3150.00
339.07
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
125mm thick Brick Work
100.000
sft
6.00
600.00
Sub-Total(L0)
600.00
64.58
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Scaffolding
0.000
set
100.00
0.00
Sub-Total(M1)
0.00
0.00
Total(1)
403.65
Add over head on Total(1)
3.0 %
12.11
Total(2)
415.76
Add Profit on Total(2)
8.0 %
33.26
Total(3)
449.02
Add VAT on Unit Price
4.5 %
21.16
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
470.18
Say
470
per M2
Item: 06 (A08K) RCC Lintel (1:2:4) with 1% rod
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
15.000
cft
13.00
195.00
Cement
18.000
bag
343.00
6174.00
Sand - Sylhet
30.000
cft
24.00
720.00
Stone-chips
90.000
cft
80.00
7200.00
Re-bar G60
222.730
kg
40.20
8953.75
Wood - Mango
13.000
cft
250.00
3250.00
Sub-Total(A1)
26492.75
9355.91
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
RCC Work
100.000
cft
6.00
600.00
Form work
476.000
sft
8.00
3808.00
Sub-Total(L1)
4408.00
1556.69
Total(1)
10912.60
Add over head on Total(1)
3.0 %
327.38
Total(2)
11239.98
Add Profit on Total(2)
8.0 %
899.20
Total(3)
12139.17
Add VAT on Unit Price
4.5 %
572.00
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
12711.18
Say
12711
per M3
Item: 01 (A09F) Dismantling - 250mm Brick Wall
Basis:1 cft
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Dismatle - B/W
1.000
cft
3.50
3.50
Sub-Total(L1)
3.50
123.60
Total(1)
123.60
Add over head on Total(1)
3.0 %
3.71
Total(2)
127.31
Add Profit on Total(2)
8.0 %
10.18
Total(3)
137.50
Add VAT on Unit Price
4.5 %
6.48
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
143.97
Say
144
per M2
Item: 15E (A09G1) Dismantle, Refixing Door
Basis:1 sft
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
0.050
nos.
100.00
5.00
Head Mason Supply
0.050
nos.
200.00
10.00
Sub-Total(L0)
15.00
161.46
Total(1)
161.46
Add over head on Total(1)
3.0 %
4.84
Total(2)
166.30
Add Profit on Total(2)
8.0 %
13.30
Total(3)
179.61
Add VAT on Unit Price
4.5 %
8.46
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
188.07
Say
188
per M2
Item: 15F (A09G2) Dismatle Window
Basis:1 sft
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
0.050
nos.
100.00
5.00
Sub-Total(L0)
5.00
53.82
Total(1)
53.82
Add over head on Total(1)
3.0 %
1.61
Total(2)
55.43
Add Profit on Total(2)
8.0 %
4.43
Total(3)
59.87
Add VAT on Unit Price
4.5 %
2.82
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
62.69
Say
63
per M2
Item: 14 (A11B) Aluminium fixed window
Basis:1 sft
S2.Alum,SS/MS,FalseCeil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Aluminum Fixed Window
1.000
sft
170.00
170.00
Sub-Total(S2)
170.00
1829.88
Total(1)
1829.88
Add over head on Total(1)
3.0 %
54.90
Total(2)
1884.78
Add Profit on Total(2)
8.0 %
150.78
Total(3)
2035.56
Add VAT on Unit Price
4.5 %
95.92
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
2131.47
Say
2131
per M2
Item: 13A (A11I) Alum(PC)-Swing door Louvr-glass
Basis:1 sft
S2.Alum,SS/MS,FalseCeil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
AlPC) SwingDoorLouvr-Glas
1.000
sft
439.00
439.00
Sub-Total(S2)
439.00
4725.40
Total(1)
4725.40
Add over head on Total(1)
3.0 %
141.76
Total(2)
4867.16
Add Profit on Total(2)
8.0 %
389.37
Total(3)
5256.53
Add VAT on Unit Price
4.5 %
247.69
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
5504.22
Say
5504
per M2
Item: 07 (A12A) Plaster(1:5) 20mm thick
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
8.250
cft
13.00
107.25
Cement
1.100
bag
343.00
377.30
Sub-Total(A1)
484.55
52.16
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
OutPlaster 30.5ft
100.000
sft
4.50
450.00
Sub-Total(L0)
450.00
48.44
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Scaffolding
1.500
set
100.00
150.00
Sub-Total(M1)
150.00
16.15
Total(1)
116.74
Add over head on Total(1)
3.0 %
3.50
Total(2)
120.24
Add Profit on Total(2)
8.0 %
9.62
Total(3)
129.86
Add VAT on Unit Price
4.5 %
6.12
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
135.98
Say
136
per M2
Item: 09 (A13B) Epoxy paint to floor
Basis:100 sft
A3.Material-Paint
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Epoxy Primer
2.000
Ltr
170.00
340.00
Epoxy Enamel
3.080
Ltr
387.00
1191.96
Thinner-T6/T7
1.600
Ltr
46.00
73.60
Chalk powder
1.330
kg
18.00
23.94
Mosaic stone
0.200
no
110.00
22.00
Scrap
1.000
L.s
30.00
30.00
Sub-Total(A3)
1681.50
181.00
L6.Labour Paints
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Epoxy Paint-Floor
100.000
sft
7.00
700.00
Sub-Total(L6)
700.00
75.35
Total(1)
256.34
Add over head on Total(1)
3.0 %
7.69
Total(2)
264.03
Add Profit on Total(2)
8.0 %
21.12
Total(3)
285.16
Add VAT on Unit Price
4.5 %
13.44
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
298.59
Say
299
per M2
Item: 10 (A13C2) Ind-Enamel paint Inside
Basis:2481 sft
A3.Material-Paint
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ind. Enamel paint
40.000
Ltr
210.00
8400.00
Thinner-T6/T7
16.000
Ltr
46.00
736.00
Jensoline primer
8.000
Ltr
265.00
2120.00
Water Paper
6.000
nos
40.00
240.00
Chalk powder
5.000
kg
18.00
90.00
4" Brush
6.000
no
100.00
600.00
Iron paper
3.000
no
80.00
240.00
Carrying
1.000
L.s
300.00
300.00
Sub-Total(A3)
12726.00
55.22
L6.Labour Paints
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Industrial Enamel paint
2480.780
sft
4.00
9923.12
Sub-Total(L6)
9923.12
43.06
Total(1)
98.27
Add over head on Total(1)
3.0 %
2.95
Total(2)
101.22
Add Profit on Total(2)
8.0 %
8.10
Total(3)
109.32
Add VAT on Unit Price
4.5 %
5.15
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
114.47
Say
114
per M2
Item: 08A (A13E) Plastic paint
Basis:100 sft
A3.Material-Paint
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Plastron Sealer
0.800
Ltr
160.00
128.00
Plastic Emulsion
1.330
Ltr
170.00
226.10
Enamel paint
0.610
Ltr
170.00
103.70
Snowcel
2.500
kg
7.60
19.00
Thinner-T6/T7
0.800
Ltr
46.00
36.80
Water Paper
0.500
nos
40.00
20.00
Chalk powder
2.500
kg
18.00
45.00
Mosaic stone
0.100
no
110.00
11.00
Sub-Total(A3)
589.60
63.46
L6.Labour Paints
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Plastic Painting
100.000
sft
2.50
250.00
Sub-Total(L6)
250.00
26.91
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Scaffolding
1.000
set
100.00
100.00
Sub-Total(M1)
100.00
10.76
Total(1)
101.14
Add over head on Total(1)
3.0 %
3.03
Total(2)
104.17
Add Profit on Total(2)
8.0 %
8.33
Total(3)
112.51
Add VAT on Unit Price
4.5 %
5.30
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
117.81
Say
118
per M2
Item: 08B (A13E1) Plastic paint to existing wall
Basis:100 sft
A3.Material-Paint
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Plastic Emulsion
0.655
Ltr
170.00
111.35
Enamel paint
0.300
Ltr
170.00
51.00
Snowcel
1.000
kg
7.60
7.60
Thinner-T6/T7
0.400
Ltr
46.00
18.40
Water Paper
0.200
nos
40.00
8.00
Sub-Total(A3)
196.35
21.14
L6.Labour Paints
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Plastic Paint (1-coat)
100.000
sft
1.25
125.00
Sub-Total(L6)
125.00
13.46
Total(1)
34.59
Add over head on Total(1)
3.0 %
1.04
Total(2)
35.63
Add Profit on Total(2)
8.0 %
2.85
Total(3)
38.48
Add VAT on Unit Price
4.5 %
1.81
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
40.29
Say
40
per M2
Item: 15G (A13F) Weather coat paint
Basis:100 sft
A3.Material-Paint
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Plastron Sealer
0.500
Ltr
160.00
80.00
Enamel paint
0.250
Ltr
170.00
42.50
Snowcel
2.500
kg
7.60
19.00
Thinner-T6/T7
0.500
Ltr
46.00
23.00
Weather Coat (ColorBank)
1.420
Ltr
227.85
323.55
Sub-Total(A3)
488.05
52.53
L6.Labour Paints
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Weather coat painting
100.000
sft
4.00
400.00
Sub-Total(L6)
400.00
43.06
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Scaffolding
1.000
set
100.00
100.00
Sub-Total(M1)
100.00
10.76
Total(1)
106.35
Add over head on Total(1)
3.0 %
3.19
Total(2)
109.54
Add Profit on Total(2)
8.0 %
8.76
Total(3)
118.31
Add VAT on Unit Price
4.5 %
5.57
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
123.88
Say
124
per M2
Item: 11 (C20) Chain Link Wire Fencing (12 BWG)
Basis:1 sft
S2.Alum,SS/MS,FalseCeil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
GI Fenc i/c MS Pipe-1~1.5
1.000
sft
70.00
70.00
Sub-Total(S2)
70.00
753.48
Total(1)
753.48
Add over head on Total(1)
3.0 %
22.60
Total(2)
776.08
Add Profit on Total(2)
8.0 %
62.09
Total(3)
838.17
Add VAT on Unit Price
4.5 %
39.49
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
877.67
Say
878
per M2
Item: 15A (C23) MS Chequr Plate
Basis:1 sft
C1.Steel Structures
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS Checker Plate
1.000
sft
100.00
100.00
Sub-Total(C1)
100.00
1076.40
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Carpenter Helper
0.100
nos.
150.00
15.00
Sub-Total(L0)
15.00
161.46
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Welding Electrode VM 8-no
0.050
pack
520.00
26.00
Sub-Total(M1)
26.00
279.86
Total(1)
1517.72
Add over head on Total(1)
3.0 %
45.53
Total(2)
1563.26
Add Profit on Total(2)
8.0 %
125.06
Total(3)
1688.32
Add VAT on Unit Price
4.5 %
79.55
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
1767.87
Say
1768
per M2
Item: 15B (C23A) MS Chequre Plate Re-arrngement
Basis:1 sft
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Carpenter Helper
0.040
nos.
150.00
6.00
Sub-Total(L0)
6.00
64.58
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Welding Electrode VM 8-no
0.001
pack
520.00
0.52
Sub-Total(M1)
0.52
5.60
Total(1)
70.18
Add over head on Total(1)
3.0 %
2.11
Total(2)
72.29
Add Profit on Total(2)
8.0 %
5.78
Total(3)
78.07
Add VAT on Unit Price
4.5 %
3.68
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
81.75
Say
82
per M2
Item: 15D (C24) MS Louver
Basis:1 sft
S2.Alum,SS/MS,FalseCeil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS Louver in Steel Door
1.000
sft
180.00
180.00
Sub-Total(S2)
180.00
1937.52
Total(1)
1937.52
Add over head on Total(1)
3.0 %
58.13
Total(2)
1995.65
Add Profit on Total(2)
8.0 %
159.65
Total(3)
2155.30
Add VAT on Unit Price
4.5 %
101.56
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
2256.86
Say
2257
per M2