Project Extra Item of Power House Extension |
Item: 02 (A02H) BFS with m-joint(1:4)-3% pudlu |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Brick |
300.000 |
no. |
3.80 |
1140.00 |
|
Sand - Local - Mymensingh |
5.000 |
cft |
13.00 |
65.00 |
|
Cement |
2.000 |
bag |
343.00 |
686.00 |
|
Pudloo |
3.000 |
kg |
70.00 |
210.00 |
|
|
Sub-Total(A1) |
2101.00
|
226.15
|
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
BFS with Morter joint |
100.000 |
sft |
1.50 |
150.00 |
|
|
Sub-Total(L1) |
150.00
|
16.15
|
|
|
|
Total(1) |
|
242.30 |
|
Add over head on Total(1)
|
3.0 % |
7.27 |
|
|
|
Total(2) |
|
249.57 |
|
Add Profit on Total(2) |
8.0 % |
19.97
|
|
|
|
Total(3) |
|
269.53 |
|
Add VAT on Unit Price |
4.5 % |
12.70 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
282.23
|
|
|
|
Say |
|
Item: 01 (A06F2) 125mm Fire Brick Work |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Fire Brick |
500.000 |
no. |
10.00 |
5000.00 |
|
Fire Brick Morter |
20.000 |
cft |
500.00 |
10000.00 |
|
|
Sub-Total(A1) |
15000.00
|
1614.60
|
L2.Labour-Tile/Sanitary |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Fire Brick Work |
100.000 |
sft |
15.00 |
1500.00 |
|
|
Sub-Total(L2) |
1500.00
|
161.46
|
|
|
|
Total(1) |
|
1776.06 |
|
Add over head on Total(1)
|
3.0 % |
53.28 |
|
|
|
Total(2) |
|
1829.34 |
|
Add Profit on Total(2) |
8.0 % |
146.35
|
|
|
|
Total(3) |
|
1975.69 |
|
Add VAT on Unit Price |
4.5 % |
93.10 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
2068.78
|
|
|
|
Say |
|
Item: 03 (A09N2) Supply of Plstocrete Plus |
|
Basis:1
no. |
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Plastocerte Plus |
1.000 |
kg |
160.00 |
160.00 |
|
|
Sub-Total(M1) |
160.00
|
160.00
|
|
|
|
Total(1) |
|
160.00 |
|
Add over head on Total(1)
|
3.0 % |
4.80 |
|
|
|
Total(2) |
|
164.80 |
|
Add Profit on Total(2) |
8.0 % |
13.18
|
|
|
|
Total(3) |
|
177.98 |
|
Add VAT on Unit Price |
4.5 % |
8.39 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
186.37
|
|
|
|
Say |
|
Item: 07 (A12B) Plaster 12mm thick (1:4) |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
7.500 |
cft |
13.00 |
97.50 |
|
Cement |
1.000 |
bag |
343.00 |
343.00 |
|
|
Sub-Total(A1) |
440.50
|
47.42
|
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Plaster Work |
100.000 |
sft |
3.00 |
300.00 |
|
|
Sub-Total(L1) |
300.00
|
32.29
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Scaffolding |
1.000 |
set |
100.00 |
100.00 |
|
|
Sub-Total(M1) |
100.00
|
10.76
|
|
|
|
Total(1) |
|
90.47 |
|
Add over head on Total(1)
|
3.0 % |
2.71 |
|
|
|
Total(2) |
|
93.19 |
|
Add Profit on Total(2) |
8.0 % |
7.45
|
|
|
|
Total(3) |
|
100.64 |
|
Add VAT on Unit Price |
4.5 % |
4.74 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
105.38
|
|
|
|
Say |
|
Item: 06 (A13E) Plastic paint |
|
Basis:100
sft |
A3.Material-Paint |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Plastron Sealer |
0.800 |
Ltr |
160.00 |
128.00 |
|
Plastic Emulsion |
1.330 |
Ltr |
170.00 |
226.10 |
|
Enamel paint |
0.610 |
Ltr |
170.00 |
103.70 |
|
Snowcel |
2.500 |
kg |
7.60 |
19.00 |
|
Thinner-T6/T7 |
0.800 |
Ltr |
46.00 |
36.80 |
|
Water Paper |
0.500 |
nos |
40.00 |
20.00 |
|
Chalk powder |
2.500 |
kg |
18.00 |
45.00 |
|
Mosaic stone |
0.100 |
no |
110.00 |
11.00 |
|
|
Sub-Total(A3) |
589.60
|
63.46
|
L6.Labour Paints |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Plastic Painting |
100.000 |
sft |
2.50 |
250.00 |
|
|
Sub-Total(L6) |
250.00
|
26.91
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Scaffolding |
1.000 |
set |
100.00 |
100.00 |
|
|
Sub-Total(M1) |
100.00
|
10.76
|
|
|
|
Total(1) |
|
101.14 |
|
Add over head on Total(1)
|
3.0 % |
3.03 |
|
|
|
Total(2) |
|
104.17 |
|
Add Profit on Total(2) |
8.0 % |
8.33
|
|
|
|
Total(3) |
|
112.51 |
|
Add VAT on Unit Price |
4.5 % |
5.30 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
117.81
|
|
|
|
Say |
|
Item: 05 (A13G) Epoxy paint to wall (New) |
|
Basis:100
sft |
A3.Material-Paint |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Epoxy Primer |
2.000 |
Ltr |
170.00 |
340.00 |
|
Epoxy Enamel |
3.080 |
Ltr |
387.00 |
1191.96 |
|
Thinner-T6/T7 |
1.600 |
Ltr |
46.00 |
73.60 |
|
Chalk powder |
1.330 |
kg |
18.00 |
23.94 |
|
Mosaic stone |
0.200 |
no |
110.00 |
22.00 |
|
Scrap |
1.000 |
L.s |
30.00 |
30.00 |
|
|
Sub-Total(A3) |
1681.50
|
181.00
|
L6.Labour Paints |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Epoxy Paint to wall |
100.000 |
sft |
10.00 |
1000.00 |
|
|
Sub-Total(L6) |
1000.00
|
107.64
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Scaffolding |
1.000 |
set |
100.00 |
100.00 |
|
|
Sub-Total(M1) |
100.00
|
10.76
|
|
|
|
Total(1) |
|
299.40 |
|
Add over head on Total(1)
|
3.0 % |
8.98 |
|
|
|
Total(2) |
|
308.38 |
|
Add Profit on Total(2) |
8.0 % |
24.67
|
|
|
|
Total(3) |
|
333.05 |
|
Add VAT on Unit Price |
4.5 % |
15.69 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
348.75
|
|
|
|
Say |
|
Item: 04 (B01C) uPVc pipe 50 dia |
|
Basis:100
rft |
B1.Plumbing/Sanitr Pipe |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
uPVc pipe 50 dia |
105.000 |
rft |
25.00 |
2625.00 |
|
uPVC Bend - 50mm dia |
16.000 |
no. |
47.00 |
752.00 |
|
|
Sub-Total(B1) |
3377.00
|
10.76
|
L4.Labour-Sanitary |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
uPVC pipe - 50mm |
100.000 |
rft |
15.00 |
1500.00 |
|
|
Sub-Total(L4) |
1500.00
|
10.76
|
|
|
|
Total(1) |
|
21.53 |
|
Add over head on Total(1)
|
3.0 % |
0.65 |
|
|
|
Total(2) |
|
22.17 |
|
Add Profit on Total(2) |
8.0 % |
1.77
|
|
|
|
Total(3) |
|
23.95 |
|
Add VAT on Unit Price |
4.5 % |
1.13 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
25.08
|
|
|
|
Say |
|