Project Prayer Room in between BIL & PTK |
Item: 01 (A09E1) Dismantling of CC |
|
Basis:1
sft |
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Ordinary Labour Supply |
0.030 |
nos. |
100.00 |
3.00 |
|
|
Sub-Total(L0) |
3.00
|
32.29
|
|
|
|
Total(1) |
|
32.29 |
|
Add over head on Total(1)
|
3.0 % |
0.97 |
|
|
|
Total(2) |
|
33.26 |
|
Add Profit on Total(2) |
8.0 % |
2.66
|
|
|
|
Total(3) |
|
35.92 |
|
Add VAT on Unit Price |
4.5 % |
1.69 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
37.61
|
|
|
|
Say |
|
Item: 02 (A01) Earth work in Excavation |
|
Basis:1000
cft |
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Earth Work in Excavation |
1000.000 |
cft |
1.80 |
1800.00 |
|
|
Sub-Total(L1) |
1800.00
|
63.57
|
|
|
|
Total(1) |
|
63.57 |
|
Add over head on Total(1)
|
3.0 % |
1.91 |
|
|
|
Total(2) |
|
65.47 |
|
Add Profit on Total(2) |
8.0 % |
5.24
|
|
|
|
Total(3) |
|
70.71 |
|
Add VAT on Unit Price |
4.5 % |
3.33 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
74.04
|
|
|
|
Say |
|
Item: 03 (A03C) CC (1:2:4) 75mm thick with NCF |
|
Basis:100
cft |
|
|
|
Total(1) |
|
0.00 |
|
Add over head on Total(1)
|
3.0 % |
1.91 |
|
|
|
Total(2) |
|
65.47 |
|
Add Profit on Total(2) |
8.0 % |
5.24
|
|
|
|
Total(3) |
|
70.71 |
|
Add VAT on Unit Price |
4.5 % |
3.33 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
74.04
|
|
|
|
Say |
|
Item: 04 (A05) Sand Filling |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Filling Sand |
130.000 |
cft |
8.50 |
1105.00 |
|
|
Sub-Total(A1) |
1105.00
|
390.23
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mini Roller Compaction |
100.000 |
cft |
1.00 |
100.00 |
|
Mini Dumper |
130.000 |
cft |
2.00 |
260.00 |
|
Payloader |
0.000 |
day |
8000.00 |
0.00 |
|
Dump Truck |
0.000 |
day |
8300.00 |
0.00 |
|
|
Sub-Total(E1) |
360.00
|
127.13
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Ordinary Labour Supply |
0.800 |
nos. |
100.00 |
80.00 |
|
|
Sub-Total(L0) |
80.00
|
28.25
|
|
|
|
Total(1) |
|
545.62 |
|
Add over head on Total(1)
|
3.0 % |
16.37 |
|
|
|
Total(2) |
|
561.99 |
|
Add Profit on Total(2) |
8.0 % |
44.96
|
|
|
|
Total(3) |
|
606.94 |
|
Add VAT on Unit Price |
4.5 % |
28.60 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
635.54
|
|
|
|
Say |
|
Item: 05 (A02E) Double Layer Polythene |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Polythene |
3.000 |
kg |
77.00 |
231.00 |
|
|
Sub-Total(A1) |
231.00
|
24.86
|
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Polythene laying |
200.000 |
sft |
0.20 |
40.00 |
|
|
Sub-Total(L1) |
40.00
|
4.31
|
|
|
|
Total(1) |
|
29.17 |
|
Add over head on Total(1)
|
3.0 % |
0.88 |
|
|
|
Total(2) |
|
30.05 |
|
Add Profit on Total(2) |
8.0 % |
2.40
|
|
|
|
Total(3) |
|
32.45 |
|
Add VAT on Unit Price |
4.5 % |
1.53 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
33.98
|
|
|
|
Say |
|
Item: 06 (A02B) Brick Flat Soling |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Filling Sand |
5.000 |
cft |
8.50 |
42.50 |
|
Brick |
300.000 |
no. |
3.80 |
1140.00 |
|
|
Sub-Total(A1) |
1182.50
|
127.28
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Ordinary Labour Supply |
0.100 |
nos. |
100.00 |
10.00 |
|
Head Mason Supply |
0.250 |
nos. |
200.00 |
50.00 |
|
|
Sub-Total(L0) |
60.00
|
6.46
|
|
|
|
Total(1) |
|
133.74 |
|
Add over head on Total(1)
|
3.0 % |
4.01 |
|
|
|
Total(2) |
|
137.75 |
|
Add Profit on Total(2) |
8.0 % |
11.02
|
|
|
|
Total(3) |
|
148.78 |
|
Add VAT on Unit Price |
4.5 % |
7.01 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
155.79
|
|
|
|
Say |
|
Item: 06A (A02G) BFS with existing brick |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Filling Sand |
5.000 |
cft |
8.50 |
42.50 |
|
|
Sub-Total(A1) |
42.50
|
4.57
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Ordinary Labour Supply |
0.400 |
nos. |
100.00 |
40.00 |
|
Head Mason Supply |
0.250 |
nos. |
200.00 |
50.00 |
|
|
Sub-Total(L0) |
90.00
|
9.69
|
|
|
|
Total(1) |
|
14.26 |
|
Add over head on Total(1)
|
3.0 % |
0.43 |
|
|
|
Total(2) |
|
14.69 |
|
Add Profit on Total(2) |
8.0 % |
1.18
|
|
|
|
Total(3) |
|
15.87 |
|
Add VAT on Unit Price |
4.5 % |
0.75 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
16.61
|
|
|
|
Say |
|
Item: 07 (A03G) 50mm DPC (1:1.5:3) |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
7.500 |
cft |
13.00 |
97.50 |
|
Cement |
4.000 |
bag |
343.00 |
1372.00 |
|
Stone-chips |
15.000 |
cft |
80.00 |
1200.00 |
|
Plastocrete super-Sika |
1.000 |
kg |
155.00 |
155.00 |
|
|
Sub-Total(A1) |
2824.50
|
304.03
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mixer m/c and vibrator |
16.700 |
cft |
2.00 |
33.40 |
|
|
Sub-Total(E1) |
33.40
|
3.60
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
D.P.C. |
100.000 |
sft |
3.00 |
300.00 |
|
|
Sub-Total(L0) |
300.00
|
32.29
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Wood shutter-3time |
1.110 |
cft |
350.00 |
388.50 |
|
|
Sub-Total(M1) |
388.50
|
41.82
|
|
|
|
Total(1) |
|
381.73 |
|
Add over head on Total(1)
|
3.0 % |
11.45 |
|
|
|
Total(2) |
|
393.19 |
|
Add Profit on Total(2) |
8.0 % |
31.45
|
|
|
|
Total(3) |
|
424.64 |
|
Add VAT on Unit Price |
4.5 % |
20.01 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
444.65
|
|
|
|
Say |
|
Item: 08 (A12I1) NCF |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Cement |
0.500 |
bag |
343.00 |
171.50 |
|
|
Sub-Total(A1) |
171.50
|
18.46
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Head Mason Supply |
0.500 |
nos. |
200.00 |
100.00 |
|
|
Sub-Total(L0) |
100.00
|
10.76
|
|
|
|
Total(1) |
|
29.22 |
|
Add over head on Total(1)
|
3.0 % |
0.88 |
|
|
|
Total(2) |
|
30.10 |
|
Add Profit on Total(2) |
8.0 % |
2.41
|
|
|
|
Total(3) |
|
32.51 |
|
Add VAT on Unit Price |
4.5 % |
1.53 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
34.04
|
|
|
|
Say |
|
Item: 09 (A06C) 250mm thick B-wall (1:5) - Supers |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Brick |
1200.000 |
no. |
3.80 |
4560.00 |
|
Sand - Local - Mymensingh |
40.000 |
cft |
13.00 |
520.00 |
|
Cement |
6.000 |
bag |
343.00 |
2058.00 |
|
|
Sub-Total(A1) |
7138.00
|
2520.78
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
B/w:15.5-27ft Scffld(Part |
100.000 |
cft |
6.00 |
600.00 |
|
|
Sub-Total(L0) |
600.00
|
211.89
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Scaffolding |
1.000 |
set |
100.00 |
100.00 |
|
|
Sub-Total(M1) |
100.00
|
35.32
|
|
|
|
Total(1) |
|
2767.99 |
|
Add over head on Total(1)
|
3.0 % |
83.04 |
|
|
|
Total(2) |
|
2851.03 |
|
Add Profit on Total(2) |
8.0 % |
228.08
|
|
|
|
Total(3) |
|
3079.11 |
|
Add VAT on Unit Price |
4.5 % |
145.09 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
3224.20
|
|
|
|
Say |
|
Item: 10 (A06F) 125 B/Wall (1:4) |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Brick |
500.000 |
no. |
3.80 |
1900.00 |
|
Sand - Local - Mymensingh |
17.000 |
cft |
13.00 |
221.00 |
|
Cement |
3.000 |
bag |
343.00 |
1029.00 |
|
|
Sub-Total(A1) |
3150.00
|
339.07
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
125mm thick Brick Work |
100.000 |
sft |
6.00 |
600.00 |
|
|
Sub-Total(L0) |
600.00
|
64.58
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Scaffolding |
0.000 |
set |
100.00 |
0.00 |
|
|
Sub-Total(M1) |
0.00
|
0.00
|
|
|
|
Total(1) |
|
403.65 |
|
Add over head on Total(1)
|
3.0 % |
12.11 |
|
|
|
Total(2) |
|
415.76 |
|
Add Profit on Total(2) |
8.0 % |
33.26
|
|
|
|
Total(3) |
|
449.02 |
|
Add VAT on Unit Price |
4.5 % |
21.16 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
470.18
|
|
|
|
Say |
|
Item: 11 (A12C) Plaster 12mm thick (1:6)- Superst |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
11.250 |
cft |
13.00 |
146.25 |
|
Cement |
1.000 |
bag |
343.00 |
343.00 |
|
|
Sub-Total(A1) |
489.25
|
52.66
|
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Plaster Work |
100.000 |
sft |
3.00 |
300.00 |
|
|
Sub-Total(L1) |
300.00
|
32.29
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Scaffolding |
1.000 |
set |
100.00 |
100.00 |
|
|
Sub-Total(M1) |
100.00
|
10.76
|
|
|
|
Total(1) |
|
95.72 |
|
Add over head on Total(1)
|
3.0 % |
2.87 |
|
|
|
Total(2) |
|
98.59 |
|
Add Profit on Total(2) |
8.0 % |
7.89
|
|
|
|
Total(3) |
|
106.48 |
|
Add VAT on Unit Price |
4.5 % |
5.02 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
111.49
|
|
|
|
Say |
|
Item: 12 (A08) RCC (1:2:4) in Floor on Grade |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
15.000 |
cft |
13.00 |
195.00 |
|
Cement |
18.000 |
bag |
343.00 |
6174.00 |
|
Sand - Sylhet |
30.000 |
cft |
24.00 |
720.00 |
|
Brick-chips |
90.000 |
cft |
40.00 |
3600.00 |
|
|
Sub-Total(A1) |
10689.00
|
3774.82
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Formwork upto 10ft from P |
50.000 |
sft |
8.00 |
400.00 |
|
RCC Casting. |
100.000 |
cft |
8.00 |
800.00 |
|
|
Sub-Total(L0) |
1200.00
|
423.78
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Forms |
50.000 |
sft |
5.00 |
250.00 |
|
|
Sub-Total(M1) |
250.00
|
88.29
|
|
|
|
Total(1) |
|
4286.89 |
|
Add over head on Total(1)
|
3.0 % |
128.61 |
|
|
|
Total(2) |
|
4415.49 |
|
Add Profit on Total(2) |
8.0 % |
353.24
|
|
|
|
Total(3) |
|
4768.73 |
|
Add VAT on Unit Price |
4.5 % |
224.70 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
4993.44
|
|
|
|
Say |
|
Item: 13 (A10A) Re-bar Grade 60 |
|
Basis:1000
kg. |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
GI Wire |
10.000 |
kg |
90.00 |
900.00 |
|
Re-bar G60 |
1050.000 |
kg |
40.20 |
42210.00 |
|
|
Sub-Total(A1) |
43110.00
|
88.29
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Re-bar Work |
1000.000 |
kg |
1.65 |
1650.00 |
|
Local carrying Rod |
0.000 |
kg |
0.25 |
0.00 |
|
|
Sub-Total(L0) |
1650.00
|
88.29
|
|
|
|
Total(1) |
|
176.58 |
|
Add over head on Total(1)
|
3.0 % |
5.30 |
|
|
|
Total(2) |
|
181.87 |
|
Add Profit on Total(2) |
8.0 % |
14.55
|
|
|
|
Total(3) |
|
196.42 |
|
Add VAT on Unit Price |
4.5 % |
9.26 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
205.68
|
|
|
|
Say |
|
Item: 14 (A13F) Weather coat paint |
|
Basis:100
sft |
A3.Material-Paint |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Plastron Sealer |
0.500 |
Ltr |
160.00 |
80.00 |
|
Enamel paint |
0.250 |
Ltr |
170.00 |
42.50 |
|
Snowcel |
2.500 |
kg |
7.60 |
19.00 |
|
Thinner-T6/T7 |
0.500 |
Ltr |
46.00 |
23.00 |
|
Weather Coat (ColorBank) |
1.420 |
Ltr |
227.85 |
323.55 |
|
|
Sub-Total(A3) |
488.05
|
52.53
|
L6.Labour Paints |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Weather coat painting |
100.000 |
sft |
4.00 |
400.00 |
|
|
Sub-Total(L6) |
400.00
|
43.06
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Scaffolding |
1.000 |
set |
100.00 |
100.00 |
|
|
Sub-Total(M1) |
100.00
|
10.76
|
|
|
|
Total(1) |
|
106.35 |
|
Add over head on Total(1)
|
3.0 % |
3.19 |
|
|
|
Total(2) |
|
109.54 |
|
Add Profit on Total(2) |
8.0 % |
8.76
|
|
|
|
Total(3) |
|
118.31 |
|
Add VAT on Unit Price |
4.5 % |
5.57 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
123.88
|
|
|
|
Say |
|
Item: 15 (A13E) Plastic paint |
|
Basis:100
sft |
A3.Material-Paint |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Plastron Sealer |
0.800 |
Ltr |
160.00 |
128.00 |
|
Plastic Emulsion |
1.330 |
Ltr |
170.00 |
226.10 |
|
Enamel paint |
0.610 |
Ltr |
170.00 |
103.70 |
|
Snowcel |
2.500 |
kg |
7.60 |
19.00 |
|
Thinner-T6/T7 |
0.800 |
Ltr |
46.00 |
36.80 |
|
Water Paper |
0.500 |
nos |
40.00 |
20.00 |
|
Chalk powder |
2.500 |
kg |
18.00 |
45.00 |
|
Mosaic stone |
0.100 |
no |
110.00 |
11.00 |
|
|
Sub-Total(A3) |
589.60
|
63.46
|
L6.Labour Paints |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Plastic Painting |
100.000 |
sft |
2.50 |
250.00 |
|
|
Sub-Total(L6) |
250.00
|
26.91
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Scaffolding |
1.000 |
set |
100.00 |
100.00 |
|
|
Sub-Total(M1) |
100.00
|
10.76
|
|
|
|
Total(1) |
|
101.14 |
|
Add over head on Total(1)
|
3.0 % |
3.03 |
|
|
|
Total(2) |
|
104.17 |
|
Add Profit on Total(2) |
8.0 % |
8.33
|
|
|
|
Total(3) |
|
112.51 |
|
Add VAT on Unit Price |
4.5 % |
5.30 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
117.81
|
|
|
|
Say |
|
Item: 16 (A14E) Hard Board Ceiling |
|
Basis:1
sft |
S1.Sub-contractor-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Hard board Ceiling |
1.000 |
sft |
30.00 |
30.00 |
|
|
Sub-Total(S1) |
30.00
|
322.92
|
|
|
|
Total(1) |
|
322.92 |
|
Add over head on Total(1)
|
3.0 % |
9.69 |
|
|
|
Total(2) |
|
332.61 |
|
Add Profit on Total(2) |
8.0 % |
26.61
|
|
|
|
Total(3) |
|
359.22 |
|
Add VAT on Unit Price |
4.5 % |
16.93 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
376.14
|
|
|
|
Say |
|
Item: 17 (C01) MS Angle Purlin |
|
Basis:1000
kg. |
C1.Steel Structures |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
MS angle |
1050.000 |
kg |
38.00 |
39900.00 |
|
|
Sub-Total(C1) |
39900.00
|
322.92
|
L5.Labour-MS Work |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Making Purlin,rafter, box |
1000.000 |
kg |
6.50 |
6500.00 |
|
|
Sub-Total(L5) |
6500.00
|
322.92
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Welding Electrode VM 8-no |
2.000 |
pack |
520.00 |
1040.00 |
|
|
Sub-Total(M1) |
1040.00
|
322.92
|
|
|
|
Total(1) |
|
968.76 |
|
Add over head on Total(1)
|
3.0 % |
29.06 |
|
|
|
Total(2) |
|
997.82 |
|
Add Profit on Total(2) |
8.0 % |
79.83
|
|
|
|
Total(3) |
|
1077.65 |
|
Add VAT on Unit Price |
4.5 % |
50.78 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
1128.43
|
|
|
|
Say |
|
Item: 18 (C14) CI sheet roofing (excl.angle) |
|
Basis:100
sft |
C1.Steel Structures |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
J-Hook |
65.000 |
no |
2.50 |
162.50 |
|
CI Sheet 0.45mm |
0.700 |
Bun |
3000.00 |
2100.00 |
|
|
Sub-Total(C1) |
2262.50
|
243.54
|
S2.Alum,SS/MS,FalseCeil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
CI Sheet roofing |
100.000 |
sft |
2.75 |
275.00 |
|
|
Sub-Total(S2) |
275.00
|
29.60
|
|
|
|
Total(1) |
|
273.14 |
|
Add over head on Total(1)
|
3.0 % |
8.19 |
|
|
|
Total(2) |
|
281.33 |
|
Add Profit on Total(2) |
8.0 % |
22.51
|
|
|
|
Total(3) |
|
303.84 |
|
Add VAT on Unit Price |
4.5 % |
14.32 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
318.15
|
|
|
|
Say |
|
Item: 19 (B15D) Bib cock N-54 |
|
Basis:1
no. |
B1.Plumbing/Sanitr Pipe |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Bib cock |
1.000 |
no |
380.00 |
380.00 |
|
|
Sub-Total(B1) |
380.00
|
380.00
|
L4.Labour-Sanitary |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Bib Cock fitting |
1.000 |
no. |
50.00 |
50.00 |
|
|
Sub-Total(L4) |
50.00
|
50.00
|
|
|
|
Total(1) |
|
430.00 |
|
Add over head on Total(1)
|
3.0 % |
12.90 |
|
|
|
Total(2) |
|
442.90 |
|
Add Profit on Total(2) |
8.0 % |
35.43
|
|
|
|
Total(3) |
|
478.33 |
|
Add VAT on Unit Price |
4.5 % |
22.54 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
500.87
|
|
|
|
Say |
|
Item: 20A (B15A3) 25mm dia GI Pipe |
|
Basis:100
rft |
B1.Plumbing/Sanitr Pipe |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
GI Pipe - 25mm dia |
105.000 |
rft |
50.00 |
5250.00 |
|
Tread Tape |
6.000 |
Dezn |
120.00 |
720.00 |
|
25mm G-Valve |
1.000 |
No |
230.00 |
230.00 |
|
25mm Union |
1.000 |
No |
50.00 |
50.00 |
|
25mm El-bow |
25.000 |
No |
25.00 |
625.00 |
|
|
Sub-Total(B1) |
6875.00
|
50.00
|
B2.Sanitary fittings |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
GI Fittings - 25mm dia |
100.000 |
rft |
5.00 |
500.00 |
|
|
Sub-Total(B2) |
500.00
|
50.00
|
L4.Labour-Sanitary |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
GI Pipe fiting - 25mm dia |
1.000 |
rft |
11.00 |
11.00 |
|
1" dia G.I gate Valve |
1.000 |
No |
35.00 |
35.00 |
|
|
Sub-Total(L4) |
46.00
|
50.00
|
|
|
|
Total(1) |
|
150.00 |
|
Add over head on Total(1)
|
3.0 % |
4.50 |
|
|
|
Total(2) |
|
154.50 |
|
Add Profit on Total(2) |
8.0 % |
12.36
|
|
|
|
Total(3) |
|
166.86 |
|
Add VAT on Unit Price |
4.5 % |
7.86 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
174.72
|
|
|
|
Say |
|
Item: 20B (B15A) 12mm dia G.I pipe |
|
Basis:160
rft |
B1.Plumbing/Sanitr Pipe |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
12mm G.I pipe |
168.000 |
rft |
30.00 |
5040.00 |
|
Tread Tape |
9.000 |
Dezn |
120.00 |
1080.00 |
|
12mm G-Valve |
4.000 |
No |
160.00 |
640.00 |
|
12mm Tee |
100.000 |
No |
12.00 |
1200.00 |
|
12mm Union |
10.000 |
No |
10.00 |
100.00 |
|
|
Sub-Total(B1) |
8060.00
|
50.00
|
L4.Labour-Sanitary |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
GI Pipe fitting - 12mmdia |
160.000 |
rft |
9.00 |
1440.00 |
|
|
Sub-Total(L4) |
1440.00
|
50.00
|
|
|
|
Total(1) |
|
100.00 |
|
Add over head on Total(1)
|
3.0 % |
3.00 |
|
|
|
Total(2) |
|
103.00 |
|
Add Profit on Total(2) |
8.0 % |
8.24
|
|
|
|
Total(3) |
|
111.24 |
|
Add VAT on Unit Price |
4.5 % |
5.24 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
116.48
|
|
|
|
Say |
|
Item: 21 (B01A) uPVC Pipe - 150mm dia |
|
Basis:319
rft |
B1.Plumbing/Sanitr Pipe |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
uPVC Pipe 150 dia |
328.280 |
rft |
115.00 |
37752.20 |
|
uPVC Bend 150mm dia |
3.000 |
no. |
560.00 |
1680.00 |
|
uPVC Tee - 150mm dia |
21.000 |
no |
950.00 |
19950.00 |
|
uPVC End Cap -150 dia |
2.000 |
no |
920.00 |
1840.00 |
|
Clamp |
73.000 |
no |
35.00 |
2555.00 |
|
Standing Urinal |
1.000 |
no |
150.00 |
150.00 |
|
Hole making (150 dia) |
21.000 |
no |
350.00 |
7350.00 |
|
S-cement tube |
5.000 |
no |
190.00 |
950.00 |
|
Solvent cement -500 ml |
2.000 |
pot |
490.00 |
980.00 |
|
|
Sub-Total(B1) |
73207.20
|
50.00
|
L4.Labour-Sanitary |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
uPVC Pipe Fitting -150mm |
318.720 |
rft |
20.00 |
6374.40 |
|
|
Sub-Total(L4) |
6374.40
|
50.00
|
|
|
|
Total(1) |
|
100.00 |
|
Add over head on Total(1)
|
3.0 % |
3.00 |
|
|
|
Total(2) |
|
103.00 |
|
Add Profit on Total(2) |
8.0 % |
8.24
|
|
|
|
Total(3) |
|
111.24 |
|
Add VAT on Unit Price |
4.5 % |
5.24 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
116.48
|
|
|
|
Say |
|
Item: 22 (A11R0) MS Door Shutter Angle Frame |
|
Basis:52
sft |
S2.Alum,SS/MS,FalseCeil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
MS Swing Door i/c C.Sheet |
51.600 |
sft |
260.00 |
13416.00 |
|
|
Sub-Total(S2) |
13416.00
|
2798.64
|
|
|
|
Total(1) |
|
2798.64 |
|
Add over head on Total(1)
|
3.0 % |
83.96 |
|
|
|
Total(2) |
|
2882.60 |
|
Add Profit on Total(2) |
8.0 % |
230.61
|
|
|
|
Total(3) |
|
3113.21 |
|
Add VAT on Unit Price |
4.5 % |
146.70 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
3259.90
|
|
|
|
Say |
|
Item: 22A (A11R) MS Door |
|
Basis:23
sft |
C2.MS/SS Work i/c matr |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Hollow Metal Door |
22.600 |
sft |
350.00 |
7910.00 |
|
Mortise Door Lock |
1.000 |
no. |
380.00 |
380.00 |
|
|
Sub-Total(C2) |
8290.00
|
3948.39
|
|
|
|
Total(1) |
|
3948.39 |
|
Add over head on Total(1)
|
3.0 % |
118.45 |
|
|
|
Total(2) |
|
4066.84 |
|
Add Profit on Total(2) |
8.0 % |
325.35
|
|
|
|
Total(3) |
|
4392.19 |
|
Add VAT on Unit Price |
4.5 % |
206.96 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
4599.15
|
|
|
|
Say |
|
Item: 23 (A11C1) Alum(PC) Sliding/Fiexd Window Ref |
|
Basis:1
sft |
S2.Alum,SS/MS,FalseCeil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Al Win F/Sliding W- R-gls |
1.000 |
sft |
250.00 |
250.00 |
|
|
Sub-Total(S2) |
250.00
|
2691.00
|
|
|
|
Total(1) |
|
2691.00 |
|
Add over head on Total(1)
|
3.0 % |
80.73 |
|
|
|
Total(2) |
|
2771.73 |
|
Add Profit on Total(2) |
8.0 % |
221.74
|
|
|
|
Total(3) |
|
2993.47 |
|
Add VAT on Unit Price |
4.5 % |
141.05 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
3134.52
|
|
|
|
Say |
|
Item: 24A (A11G) Alum(PC) swing door Plastic-Glass |
|
Basis:1
sft |
S2.Alum,SS/MS,FalseCeil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Alum.Swing doorGlass-Plas |
1.000 |
sft |
470.00 |
470.00 |
|
|
Sub-Total(S2) |
470.00
|
5059.08
|
|
|
|
Total(1) |
|
5059.08 |
|
Add over head on Total(1)
|
3.0 % |
151.77 |
|
|
|
Total(2) |
|
5210.85 |
|
Add Profit on Total(2) |
8.0 % |
416.87
|
|
|
|
Total(3) |
|
5627.72 |
|
Add VAT on Unit Price |
4.5 % |
265.18 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
5892.90
|
|
|
|
Say |
|
Item: 24B (A11H) Aluminium Louver |
|
Basis:1
sft |
S2.Alum,SS/MS,FalseCeil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Aluminium Louver |
1.000 |
sft |
310.00 |
310.00 |
|
|
Sub-Total(S2) |
310.00
|
3336.84
|
|
|
|
Total(1) |
|
3336.84 |
|
Add over head on Total(1)
|
3.0 % |
100.11 |
|
|
|
Total(2) |
|
3436.95 |
|
Add Profit on Total(2) |
8.0 % |
274.96
|
|
|
|
Total(3) |
|
3711.90 |
|
Add VAT on Unit Price |
4.5 % |
174.91 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
3886.81
|
|
|
|
Say |
|
Item: 24C (G01B) Groove Cutting - 40x32 |
|
Basis:1
rft |
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Head Mason Supply |
0.080 |
nos. |
200.00 |
16.00 |
|
|
Sub-Total(L0) |
16.00
|
3336.84
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Diamond Cutiing Disc -100 |
0.001 |
no |
600.00 |
0.60 |
|
Cheisel - Hammer |
0.150 |
no |
55.00 |
8.25 |
|
|
Sub-Total(M1) |
8.85
|
3336.84
|
|
|
|
Total(1) |
|
6673.68 |
|
Add over head on Total(1)
|
3.0 % |
200.21 |
|
|
|
Total(2) |
|
6873.89 |
|
Add Profit on Total(2) |
8.0 % |
549.91
|
|
|
|
Total(3) |
|
7423.80 |
|
Add VAT on Unit Price |
4.5 % |
349.81 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
7773.61
|
|
|
|
Say |
|
Item: 24D (B15N) Cowel 100mm dia |
|
Basis:1
no. |
B1.Plumbing/Sanitr Pipe |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Cowel 100mm dia |
1.000 |
no. |
50.00 |
50.00 |
|
|
Sub-Total(B1) |
50.00
|
50.00
|
L4.Labour-Sanitary |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Cowel Fitting |
1.000 |
no. |
25.00 |
25.00 |
|
|
Sub-Total(L4) |
25.00
|
25.00
|
|
|
|
Total(1) |
|
75.00 |
|
Add over head on Total(1)
|
3.0 % |
2.25 |
|
|
|
Total(2) |
|
77.25 |
|
Add Profit on Total(2) |
8.0 % |
6.18
|
|
|
|
Total(3) |
|
83.43 |
|
Add VAT on Unit Price |
4.5 % |
3.93 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
87.36
|
|
|
|
Say |
|