Project Contracors Site Office |
Item: 01 (A01) Earth work in Excavation |
|
Basis:1000
cft |
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Earth Work in Excavation |
1000.000 |
cft |
1.80 |
1800.00 |
|
|
Sub-Total(L1) |
1800.00
|
63.57
|
|
|
|
Total(1) |
|
63.57 |
|
Add over head on Total(1)
|
3.0 % |
1.91 |
|
|
|
Total(2) |
|
65.47 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
65.47 |
|
Add VAT on Unit Price |
4.5 % |
3.09 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
68.56
|
|
|
|
Say |
|
Item: 02 (A05) Sand Filling |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Filling Sand |
130.000 |
cft |
8.50 |
1105.00 |
|
|
Sub-Total(A1) |
1105.00
|
390.23
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mini Roller Compaction |
100.000 |
cft |
1.00 |
100.00 |
|
Mini Dumper |
130.000 |
cft |
2.00 |
260.00 |
|
Payloader |
0.000 |
day |
8000.00 |
0.00 |
|
Dump Truck |
0.000 |
day |
8300.00 |
0.00 |
|
|
Sub-Total(E1) |
360.00
|
127.13
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Ordinary Labour Supply |
0.800 |
nos. |
100.00 |
80.00 |
|
|
Sub-Total(L0) |
80.00
|
28.25
|
|
|
|
Total(1) |
|
545.62 |
|
Add over head on Total(1)
|
3.0 % |
16.37 |
|
|
|
Total(2) |
|
561.99 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
561.99 |
|
Add VAT on Unit Price |
4.5 % |
26.48 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
588.47
|
|
|
|
Say |
|
Item: 03 (A05G1) Earth Filling |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Filling Earth |
130.000 |
cft |
6.60 |
858.00 |
|
|
Sub-Total(A1) |
858.00
|
303.00
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mini Roller Compaction |
100.000 |
cft |
1.00 |
100.00 |
|
|
Sub-Total(E1) |
100.00
|
35.32
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Ordinary Labour Supply |
1.000 |
nos. |
100.00 |
100.00 |
|
|
Sub-Total(L0) |
100.00
|
35.32
|
|
|
|
Total(1) |
|
373.63 |
|
Add over head on Total(1)
|
3.0 % |
11.21 |
|
|
|
Total(2) |
|
384.84 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
384.84 |
|
Add VAT on Unit Price |
4.5 % |
18.13 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
402.98
|
|
|
|
Say |
|
Item: 04A (A02B) Brick Flat Soling |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Filling Sand |
5.000 |
cft |
8.50 |
42.50 |
|
Brick |
300.000 |
no. |
3.80 |
1140.00 |
|
|
Sub-Total(A1) |
1182.50
|
127.28
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Ordinary Labour Supply |
0.100 |
nos. |
100.00 |
10.00 |
|
Head Mason Supply |
0.250 |
nos. |
200.00 |
50.00 |
|
|
Sub-Total(L0) |
60.00
|
6.46
|
|
|
|
Total(1) |
|
133.74 |
|
Add over head on Total(1)
|
3.0 % |
4.01 |
|
|
|
Total(2) |
|
137.75 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
137.75 |
|
Add VAT on Unit Price |
4.5 % |
6.49 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
144.25
|
|
|
|
Say |
|
Item: 04B (A03N) 100mm Brick bonded Concrete(1:2:4 |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Brick |
150.000 |
no. |
3.80 |
570.00 |
|
Sand - Local - Mymensingh |
6.750 |
cft |
13.00 |
87.75 |
|
Cement |
3.200 |
bag |
343.00 |
1097.60 |
|
Brick-chips |
13.500 |
cft |
40.00 |
540.00 |
|
|
Sub-Total(A1) |
2295.35
|
247.07
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Ordinary Labour Supply |
1.000 |
nos. |
100.00 |
100.00 |
|
Head Mason Supply |
1.000 |
nos. |
200.00 |
200.00 |
|
|
Sub-Total(L0) |
300.00
|
32.29
|
|
|
|
Total(1) |
|
279.36 |
|
Add over head on Total(1)
|
3.0 % |
8.38 |
|
|
|
Total(2) |
|
287.74 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
287.74 |
|
Add VAT on Unit Price |
4.5 % |
13.56 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
301.30
|
|
|
|
Say |
|
Item: 04C (A03O) HBB |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Filling Sand |
8.000 |
cft |
8.50 |
68.00 |
|
Brick |
500.000 |
no. |
3.80 |
1900.00 |
|
|
Sub-Total(A1) |
1968.00
|
211.84
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Ordinary Labour Supply |
0.200 |
nos. |
100.00 |
20.00 |
|
Head Mason Supply |
0.500 |
nos. |
200.00 |
100.00 |
|
|
Sub-Total(L0) |
120.00
|
12.92
|
|
|
|
Total(1) |
|
224.75 |
|
Add over head on Total(1)
|
3.0 % |
6.74 |
|
|
|
Total(2) |
|
231.49 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
231.49 |
|
Add VAT on Unit Price |
4.5 % |
10.91 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
242.40
|
|
|
|
Say |
|
Item: 05 (A02F) Single layer polythene |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Polythene |
1.500 |
kg |
77.00 |
115.50 |
|
|
Sub-Total(A1) |
115.50
|
12.43
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Ordinary Labour Supply |
0.020 |
nos. |
100.00 |
2.00 |
|
|
Sub-Total(L0) |
2.00
|
0.22
|
|
|
|
Total(1) |
|
12.65 |
|
Add over head on Total(1)
|
3.0 % |
0.38 |
|
|
|
Total(2) |
|
13.03 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
13.03 |
|
Add VAT on Unit Price |
4.5 % |
0.61 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
13.64
|
|
|
|
Say |
|
Item: 06 (A06C) 250mm thick B-wall (1:5) - Supers |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Brick |
1200.000 |
no. |
3.80 |
4560.00 |
|
Sand - Local - Mymensingh |
40.000 |
cft |
13.00 |
520.00 |
|
Cement |
6.000 |
bag |
343.00 |
2058.00 |
|
|
Sub-Total(A1) |
7138.00
|
2520.78
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
B/w:15.5-27ft Scffld(Part |
100.000 |
cft |
6.00 |
600.00 |
|
|
Sub-Total(L0) |
600.00
|
211.89
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Scaffolding |
1.000 |
set |
100.00 |
100.00 |
|
|
Sub-Total(M1) |
100.00
|
35.32
|
|
|
|
Total(1) |
|
2767.99 |
|
Add over head on Total(1)
|
3.0 % |
83.04 |
|
|
|
Total(2) |
|
2851.03 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
2851.03 |
|
Add VAT on Unit Price |
4.5 % |
134.34 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
2985.37
|
|
|
|
Say |
|
Item: 08 (A06F) 125 B/Wall (1:4) |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Brick |
500.000 |
no. |
3.80 |
1900.00 |
|
Sand - Local - Mymensingh |
17.000 |
cft |
13.00 |
221.00 |
|
Cement |
3.000 |
bag |
343.00 |
1029.00 |
|
|
Sub-Total(A1) |
3150.00
|
339.07
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
125mm thick Brick Work |
100.000 |
sft |
6.00 |
600.00 |
|
|
Sub-Total(L0) |
600.00
|
64.58
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Scaffolding |
0.000 |
set |
100.00 |
0.00 |
|
|
Sub-Total(M1) |
0.00
|
0.00
|
|
|
|
Total(1) |
|
403.65 |
|
Add over head on Total(1)
|
3.0 % |
12.11 |
|
|
|
Total(2) |
|
415.76 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
415.76 |
|
Add VAT on Unit Price |
4.5 % |
19.59 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
435.35
|
|
|
|
Say |
|
Item: 09 (A03E1) 62.5mm CC(1:2:4) |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
9.450 |
cft |
13.00 |
122.85 |
|
Cement |
3.780 |
bag |
343.00 |
1296.54 |
|
Brick-chips |
18.900 |
cft |
40.00 |
756.00 |
|
|
Sub-Total(A1) |
2175.39
|
234.16
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Ordinary Labour Supply |
1.000 |
nos. |
100.00 |
100.00 |
|
Head Mason Supply |
0.500 |
nos. |
200.00 |
100.00 |
|
|
Sub-Total(L0) |
200.00
|
21.53
|
|
|
|
Total(1) |
|
255.69 |
|
Add over head on Total(1)
|
3.0 % |
7.67 |
|
|
|
Total(2) |
|
263.36 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
263.36 |
|
Add VAT on Unit Price |
4.5 % |
12.41 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
275.77
|
|
|
|
Say |
|
Item: 10 (A12C) Plaster 12mm thick (1:6)- Superst |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
11.250 |
cft |
13.00 |
146.25 |
|
Cement |
1.000 |
bag |
343.00 |
343.00 |
|
|
Sub-Total(A1) |
489.25
|
52.66
|
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Plaster Work |
100.000 |
sft |
3.00 |
300.00 |
|
|
Sub-Total(L1) |
300.00
|
32.29
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Scaffolding |
1.000 |
set |
100.00 |
100.00 |
|
|
Sub-Total(M1) |
100.00
|
10.76
|
|
|
|
Total(1) |
|
95.72 |
|
Add over head on Total(1)
|
3.0 % |
2.87 |
|
|
|
Total(2) |
|
98.59 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
98.59 |
|
Add VAT on Unit Price |
4.5 % |
4.65 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
103.24
|
|
|
|
Say |
|
Item: 11A (A08YC) Lintel Sunshade (1:2:4) |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
22.500 |
cft |
13.00 |
292.50 |
|
Cement |
18.000 |
bag |
343.00 |
6174.00 |
|
Sand - Sylhet |
22.500 |
cft |
24.00 |
540.00 |
|
Stone-chips |
90.000 |
cft |
80.00 |
7200.00 |
|
|
Sub-Total(A1) |
14206.50
|
5017.03
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mixer m/c and vibrator |
100.000 |
cft |
2.00 |
200.00 |
|
|
Sub-Total(E1) |
200.00
|
70.63
|
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
RCC Work |
100.000 |
cft |
6.00 |
600.00 |
|
Form work |
490.190 |
sft |
8.00 |
3921.52 |
|
|
Sub-Total(L1) |
4521.52
|
1596.77
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Scaffolding |
1.000 |
set |
100.00 |
100.00 |
|
|
Sub-Total(M1) |
100.00
|
35.32
|
|
|
|
Total(1) |
|
6719.75 |
|
Add over head on Total(1)
|
3.0 % |
201.59 |
|
|
|
Total(2) |
|
6921.34 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
6921.34 |
|
Add VAT on Unit Price |
4.5 % |
326.14 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
7247.47
|
|
|
|
Say |
|
Item: 11B (A09L) Rcc Darin-Gutter (1:1.5:3) |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
14.333 |
cft |
13.00 |
186.33 |
|
Cement |
22.000 |
bag |
343.00 |
7546.00 |
|
Sand - Sylhet |
28.667 |
cft |
24.00 |
688.01 |
|
Stone-chips |
86.000 |
cft |
80.00 |
6880.00 |
|
|
Sub-Total(A1) |
15300.34
|
5403.31
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mixer m/c and vibrator |
100.000 |
cft |
2.00 |
200.00 |
|
|
Sub-Total(E1) |
200.00
|
70.63
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
RCC Casting-Superstructur |
100.000 |
sft |
10.00 |
1000.00 |
|
|
Sub-Total(L0) |
1000.00
|
353.15
|
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Form work S-structure |
606.060 |
sft |
8.00 |
4848.48 |
|
|
Sub-Total(L1) |
4848.48
|
1712.24
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Scaffolding |
8.000 |
set |
100.00 |
800.00 |
|
Steel pipe with B-plate |
40.000 |
no |
11.00 |
440.00 |
|
Steel form,S-structure |
606.060 |
sft |
10.00 |
6060.60 |
|
|
Sub-Total(M1) |
7300.60
|
2578.21
|
|
|
|
Total(1) |
|
10117.54 |
|
Add over head on Total(1)
|
3.0 % |
303.53 |
|
|
|
Total(2) |
|
10421.07 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
10421.07 |
|
Add VAT on Unit Price |
4.5 % |
491.05 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
10912.11
|
|
|
|
Say |
|
Item: 12 (C14) CI sheet roofing (excl.angle) |
|
Basis:100
sft |
C1.Steel Structures |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
J-Hook |
65.000 |
no |
2.50 |
162.50 |
|
CI Sheet 0.45mm |
0.700 |
Bun |
3000.00 |
2100.00 |
|
|
Sub-Total(C1) |
2262.50
|
243.54
|
S2.Alum,SS/MS,FalseCeil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
CI Sheet roofing |
100.000 |
sft |
2.75 |
275.00 |
|
|
Sub-Total(S2) |
275.00
|
29.60
|
|
|
|
Total(1) |
|
273.14 |
|
Add over head on Total(1)
|
3.0 % |
8.19 |
|
|
|
Total(2) |
|
281.33 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
281.33 |
|
Add VAT on Unit Price |
4.5 % |
13.26 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
294.59
|
|
|
|
Say |
|
Item: 14 (A13E) Plastic paint |
|
Basis:100
sft |
A3.Material-Paint |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Plastron Sealer |
0.800 |
Ltr |
160.00 |
128.00 |
|
Plastic Emulsion |
1.330 |
Ltr |
170.00 |
226.10 |
|
Enamel paint |
0.610 |
Ltr |
170.00 |
103.70 |
|
Snowcel |
2.500 |
kg |
7.60 |
19.00 |
|
Thinner-T6/T7 |
0.800 |
Ltr |
46.00 |
36.80 |
|
Water Paper |
0.500 |
nos |
40.00 |
20.00 |
|
Chalk powder |
2.500 |
kg |
18.00 |
45.00 |
|
Mosaic stone |
0.100 |
no |
110.00 |
11.00 |
|
|
Sub-Total(A3) |
589.60
|
63.46
|
L6.Labour Paints |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Plastic Painting |
100.000 |
sft |
2.50 |
250.00 |
|
|
Sub-Total(L6) |
250.00
|
26.91
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Scaffolding |
1.000 |
set |
100.00 |
100.00 |
|
|
Sub-Total(M1) |
100.00
|
10.76
|
|
|
|
Total(1) |
|
101.14 |
|
Add over head on Total(1)
|
3.0 % |
3.03 |
|
|
|
Total(2) |
|
104.17 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
104.17 |
|
Add VAT on Unit Price |
4.5 % |
4.91 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
109.08
|
|
|
|
Say |
|
Item: 15 (A13F) Weather coat paint |
|
Basis:100
sft |
A3.Material-Paint |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Plastron Sealer |
0.500 |
Ltr |
160.00 |
80.00 |
|
Enamel paint |
0.250 |
Ltr |
170.00 |
42.50 |
|
Snowcel |
2.500 |
kg |
7.60 |
19.00 |
|
Thinner-T6/T7 |
0.500 |
Ltr |
46.00 |
23.00 |
|
Weather Coat (ColorBank) |
1.420 |
Ltr |
227.85 |
323.55 |
|
|
Sub-Total(A3) |
488.05
|
52.53
|
L6.Labour Paints |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Weather coat painting |
100.000 |
sft |
4.00 |
400.00 |
|
|
Sub-Total(L6) |
400.00
|
43.06
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Scaffolding |
1.000 |
set |
100.00 |
100.00 |
|
|
Sub-Total(M1) |
100.00
|
10.76
|
|
|
|
Total(1) |
|
106.35 |
|
Add over head on Total(1)
|
3.0 % |
3.19 |
|
|
|
Total(2) |
|
109.54 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
109.54 |
|
Add VAT on Unit Price |
4.5 % |
5.16 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
114.71
|
|
|
|
Say |
|
Item: 16 (A12I1) NCF |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Cement |
0.500 |
bag |
343.00 |
171.50 |
|
|
Sub-Total(A1) |
171.50
|
18.46
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Head Mason Supply |
0.500 |
nos. |
200.00 |
100.00 |
|
|
Sub-Total(L0) |
100.00
|
10.76
|
|
|
|
Total(1) |
|
29.22 |
|
Add over head on Total(1)
|
3.0 % |
0.88 |
|
|
|
Total(2) |
|
30.10 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
30.10 |
|
Add VAT on Unit Price |
4.5 % |
1.42 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
31.52
|
|
|
|
Say |
|
Item: 17 (A14D) T-Ceiling excluding Board |
|
Basis:1
sft |
S2.Alum,SS/MS,FalseCeil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
False Ceiling exclud Boar |
1.000 |
sft |
25.00 |
25.00 |
|
|
Sub-Total(S2) |
25.00
|
269.10
|
|
|
|
Total(1) |
|
269.10 |
|
Add over head on Total(1)
|
3.0 % |
8.07 |
|
|
|
Total(2) |
|
277.17 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
277.17 |
|
Add VAT on Unit Price |
4.5 % |
13.06 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
290.23
|
|
|
|
Say |
|
Item: 18 (A11R1) Flush Door |
|
Basis:1
no. |
S1.Sub-contractor-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Flush Door i/c Glass |
1.000 |
no. |
4500.00 |
4500.00 |
|
|
Sub-Total(S1) |
4500.00
|
4500.00
|
|
|
|
Total(1) |
|
4500.00 |
|
Add over head on Total(1)
|
3.0 % |
135.00 |
|
|
|
Total(2) |
|
4635.00 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
4635.00 |
|
Add VAT on Unit Price |
4.5 % |
218.40 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
4853.40
|
|
|
|
Say |
|
Item: 19A (A11S) PVC Door i/c Lock(750) |
|
Basis:1
no. |
S2.Alum,SS/MS,FalseCeil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
PVC Door |
1.000 |
no. |
3000.00 |
3000.00 |
|
|
Sub-Total(S2) |
3000.00
|
3000.00
|
|
|
|
Total(1) |
|
3000.00 |
|
Add over head on Total(1)
|
3.0 % |
90.00 |
|
|
|
Total(2) |
|
3090.00 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
3090.00 |
|
Add VAT on Unit Price |
4.5 % |
145.60 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
3235.60
|
|
|
|
Say |
|
Item: 19B (A11S1) PVC Door i/c Lock(875) |
|
Basis:1
no. |
S1.Sub-contractor-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Plastic Door (875) |
1.000 |
no. |
3500.00 |
3500.00 |
|
|
Sub-Total(S1) |
3500.00
|
3500.00
|
|
|
|
Total(1) |
|
3500.00 |
|
Add over head on Total(1)
|
3.0 % |
105.00 |
|
|
|
Total(2) |
|
3605.00 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
3605.00 |
|
Add VAT on Unit Price |
4.5 % |
169.87 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
3774.87
|
|
|
|
Say |
|
Item: 20 (A11R) MS Door |
|
Basis:23
sft |
C2.MS/SS Work i/c matr |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Hollow Metal Door |
22.600 |
sft |
350.00 |
7910.00 |
|
Mortise Door Lock |
1.000 |
no. |
380.00 |
380.00 |
|
|
Sub-Total(C2) |
8290.00
|
3948.39
|
|
|
|
Total(1) |
|
3948.39 |
|
Add over head on Total(1)
|
3.0 % |
118.45 |
|
|
|
Total(2) |
|
4066.84 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
4066.84 |
|
Add VAT on Unit Price |
4.5 % |
191.63 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
4258.47
|
|
|
|
Say |
|
Item: 21A (A11R2) Door Closure |
|
Basis:1
no. |
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Carpenter Supply |
1.000 |
nos. |
120.00 |
120.00 |
|
|
Sub-Total(L0) |
120.00
|
120.00
|
S1.Sub-contractor-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Door Closure |
1.000 |
no. |
1000.00 |
1000.00 |
|
|
Sub-Total(S1) |
1000.00
|
1000.00
|
|
|
|
Total(1) |
|
1120.00 |
|
Add over head on Total(1)
|
3.0 % |
33.60 |
|
|
|
Total(2) |
|
1153.60 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
1153.60 |
|
Add VAT on Unit Price |
4.5 % |
54.36 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
1207.96
|
|
|
|
Say |
|
Item: 22B (F006) 225mm dia Rcc pipe (Capital-RC) |
|
Basis:1
rft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Brick |
3.000 |
no. |
3.80 |
11.40 |
|
Sand - Local - Mymensingh |
0.350 |
cft |
13.00 |
4.55 |
|
Polythene |
0.065 |
kg |
77.00 |
5.01 |
|
Cement |
0.200 |
bag |
343.00 |
68.60 |
|
Brick-chips |
0.700 |
cft |
40.00 |
28.00 |
|
|
Sub-Total(A1) |
117.56
|
1000.00
|
B1.Plumbing/Sanitr Pipe |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
RCC Pipe 9" dia |
1.050 |
rft |
108.00 |
113.40 |
|
|
Sub-Total(B1) |
113.40
|
1000.00
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mixer m/c and vibrator |
1.200 |
cft |
2.00 |
2.40 |
|
|
Sub-Total(E1) |
2.40
|
1000.00
|
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Earth Work in Excavation |
2.380 |
cft |
1.80 |
4.28 |
|
Brck flat soling |
1.000 |
sft |
0.60 |
0.60 |
|
CC Work |
1.200 |
cft |
5.00 |
6.00 |
|
225mm dia RCC pipe |
1.000 |
rft |
25.00 |
25.00 |
|
|
Sub-Total(L1) |
35.88
|
1000.00
|
|
|
|
Total(1) |
|
4000.00 |
|
Add over head on Total(1)
|
3.0 % |
120.00 |
|
|
|
Total(2) |
|
4120.00 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
4120.00 |
|
Add VAT on Unit Price |
4.5 % |
194.14 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
4314.14
|
|
|
|
Say |
|
Item: 23 (B01B1) uPVC Pipe pipe fitting -100mm |
|
Basis:1
rft |
L4.Labour-Sanitary |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
uPVC Pipe fitting-100 mm |
1.000 |
rft |
15.00 |
15.00 |
|
|
Sub-Total(L4) |
15.00
|
1000.00
|
|
|
|
Total(1) |
|
1000.00 |
|
Add over head on Total(1)
|
3.0 % |
30.00 |
|
|
|
Total(2) |
|
1030.00 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
1030.00 |
|
Add VAT on Unit Price |
4.5 % |
48.53 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
1078.53
|
|
|
|
Say |
|
Item: 24A (B15) 20mm dia G.I pipe |
|
Basis:160
rft |
B1.Plumbing/Sanitr Pipe |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
20mm G.I pipe |
168.000 |
rft |
40.00 |
6720.00 |
|
Tread Tape |
9.000 |
Dezn |
120.00 |
1080.00 |
|
20mm G-Valve |
4.000 |
No |
235.00 |
940.00 |
|
20mm Tee |
40.000 |
No |
25.00 |
1000.00 |
|
20mm Union |
4.000 |
No |
35.00 |
140.00 |
|
|
Sub-Total(B1) |
9880.00
|
1000.00
|
L4.Labour-Sanitary |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
GI Pipe fitting - 20mm di |
160.000 |
rft |
10.00 |
1600.00 |
|
GI Gate Valve fitting 20 |
4.000 |
No |
30.00 |
120.00 |
|
|
Sub-Total(L4) |
1720.00
|
1000.00
|
|
|
|
Total(1) |
|
2000.00 |
|
Add over head on Total(1)
|
3.0 % |
60.00 |
|
|
|
Total(2) |
|
2060.00 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
2060.00 |
|
Add VAT on Unit Price |
4.5 % |
97.07 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
2157.07
|
|
|
|
Say |
|
Item: 24B (B15A) 12mm dia G.I pipe |
|
Basis:160
rft |
B1.Plumbing/Sanitr Pipe |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
12mm G.I pipe |
168.000 |
rft |
30.00 |
5040.00 |
|
Tread Tape |
9.000 |
Dezn |
120.00 |
1080.00 |
|
12mm G-Valve |
4.000 |
No |
160.00 |
640.00 |
|
12mm Tee |
100.000 |
No |
12.00 |
1200.00 |
|
12mm Union |
10.000 |
No |
10.00 |
100.00 |
|
|
Sub-Total(B1) |
8060.00
|
1000.00
|
L4.Labour-Sanitary |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
GI Pipe fitting - 12mmdia |
160.000 |
rft |
9.00 |
1440.00 |
|
|
Sub-Total(L4) |
1440.00
|
1000.00
|
|
|
|
Total(1) |
|
2000.00 |
|
Add over head on Total(1)
|
3.0 % |
60.00 |
|
|
|
Total(2) |
|
2060.00 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
2060.00 |
|
Add VAT on Unit Price |
4.5 % |
97.07 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
2157.07
|
|
|
|
Say |
|
Item: 24C (B15A3) 25mm dia GI Pipe |
|
Basis:100
rft |
B1.Plumbing/Sanitr Pipe |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
GI Pipe - 25mm dia |
105.000 |
rft |
50.00 |
5250.00 |
|
Tread Tape |
6.000 |
Dezn |
120.00 |
720.00 |
|
25mm G-Valve |
1.000 |
No |
230.00 |
230.00 |
|
25mm Union |
1.000 |
No |
50.00 |
50.00 |
|
25mm El-bow |
25.000 |
No |
25.00 |
625.00 |
|
|
Sub-Total(B1) |
6875.00
|
1000.00
|
B2.Sanitary fittings |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
GI Fittings - 25mm dia |
100.000 |
rft |
5.00 |
500.00 |
|
|
Sub-Total(B2) |
500.00
|
1000.00
|
L4.Labour-Sanitary |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
GI Pipe fiting - 25mm dia |
1.000 |
rft |
11.00 |
11.00 |
|
1" dia G.I gate Valve |
1.000 |
No |
35.00 |
35.00 |
|
|
Sub-Total(L4) |
46.00
|
1000.00
|
|
|
|
Total(1) |
|
3000.00 |
|
Add over head on Total(1)
|
3.0 % |
90.00 |
|
|
|
Total(2) |
|
3090.00 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
3090.00 |
|
Add VAT on Unit Price |
4.5 % |
145.60 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
3235.60
|
|
|
|
Say |
|
Item: 24D (B01C1) uPVC Pipe 38mm dia |
|
Basis:75
rft |
B1.Plumbing/Sanitr Pipe |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
uPVC Bend - 50mm dia |
20.000 |
no. |
47.00 |
940.00 |
|
uPVC Pipe - 40mm dia |
78.750 |
rft |
16.25 |
1279.69 |
|
|
Sub-Total(B1) |
2219.69
|
1000.00
|
L4.Labour-Sanitary |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
uPVC Pipe fitting 37mm di |
75.000 |
rft |
5.00 |
375.00 |
|
|
Sub-Total(L4) |
375.00
|
1000.00
|
|
|
|
Total(1) |
|
2000.00 |
|
Add over head on Total(1)
|
3.0 % |
60.00 |
|
|
|
Total(2) |
|
2060.00 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
2060.00 |
|
Add VAT on Unit Price |
4.5 % |
97.07 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
2157.07
|
|
|
|
Say |
|
Item: 24E (B01B) uPVC Pipe 100 dia |
|
Basis:300
rft |
B1.Plumbing/Sanitr Pipe |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
uPVC Pipe 100mm dia |
315.000 |
rft |
58.00 |
18270.00 |
|
Solvent cement -500 ml |
8.000 |
pot |
490.00 |
3920.00 |
|
uPVC Plainn Tee-100mm Dia |
16.000 |
no. |
278.00 |
4448.00 |
|
uPVC Long Trap - 100mm Di |
6.000 |
no. |
370.00 |
2220.00 |
|
uPVC Door Bend - 100mm di |
24.000 |
no. |
290.00 |
6960.00 |
|
uPVC Bend 45D -100mm dia |
6.000 |
no. |
175.00 |
1050.00 |
|
|
Sub-Total(B1) |
36868.00
|
1000.00
|
L4.Labour-Sanitary |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
uPVC Pipe fitting-100 mm |
300.000 |
rft |
15.00 |
4500.00 |
|
|
Sub-Total(L4) |
4500.00
|
1000.00
|
|
|
|
Total(1) |
|
2000.00 |
|
Add over head on Total(1)
|
3.0 % |
60.00 |
|
|
|
Total(2) |
|
2060.00 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
2060.00 |
|
Add VAT on Unit Price |
4.5 % |
97.07 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
2157.07
|
|
|
|
Say |
|
Item: 24F (A11H1) Alum. Louver - DB Box |
|
Basis:1
sft |
S2.Alum,SS/MS,FalseCeil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Alum.Louver-DB Box |
1.000 |
sft |
375.00 |
375.00 |
|
|
Sub-Total(S2) |
375.00
|
4036.50
|
|
|
|
Total(1) |
|
4036.50 |
|
Add over head on Total(1)
|
3.0 % |
121.10 |
|
|
|
Total(2) |
|
4157.60 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
4157.60 |
|
Add VAT on Unit Price |
4.5 % |
195.91 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
4353.50
|
|
|
|
Say |
|
Item: 24G (A13M) Rubber Paint |
|
Basis:100
sft |
A3.Material-Paint |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Rubber Paint |
3.000 |
Ltr |
210.00 |
630.00 |
|
|
Sub-Total(A3) |
630.00
|
67.81
|
L6.Labour Paints |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Rubber Painting |
100.000 |
sft |
4.00 |
400.00 |
|
|
Sub-Total(L6) |
400.00
|
43.06
|
|
|
|
Total(1) |
|
110.87 |
|
Add over head on Total(1)
|
3.0 % |
3.33 |
|
|
|
Total(2) |
|
114.20 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
114.20 |
|
Add VAT on Unit Price |
4.5 % |
5.38 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
119.58
|
|
|
|
Say |
|
Item: 24H (A03P) Brick on Edging |
|
Basis:100
rft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Filling Sand |
5.000 |
cft |
8.50 |
42.50 |
|
Brick |
270.000 |
no. |
3.80 |
1026.00 |
|
|
Sub-Total(A1) |
1068.50
|
43.06
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Ordinary Labour Supply |
0.400 |
nos. |
100.00 |
40.00 |
|
Head Mason Supply |
0.300 |
nos. |
200.00 |
60.00 |
|
|
Sub-Total(L0) |
100.00
|
43.06
|
|
|
|
Total(1) |
|
86.11 |
|
Add over head on Total(1)
|
3.0 % |
2.58 |
|
|
|
Total(2) |
|
88.70 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
88.70 |
|
Add VAT on Unit Price |
4.5 % |
4.18 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
92.87
|
|
|
|
Say |
|
Item: 25 (B15B) CP angle stop cock N-64 |
|
Basis:1
no. |
B1.Plumbing/Sanitr Pipe |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Angle stop cock |
1.000 |
no |
350.00 |
350.00 |
|
|
Sub-Total(B1) |
350.00
|
350.00
|
L4.Labour-Sanitary |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Stop cock fitting |
1.000 |
no |
50.00 |
50.00 |
|
|
Sub-Total(L4) |
50.00
|
50.00
|
|
|
|
Total(1) |
|
400.00 |
|
Add over head on Total(1)
|
3.0 % |
12.00 |
|
|
|
Total(2) |
|
412.00 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
412.00 |
|
Add VAT on Unit Price |
4.5 % |
19.41 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
431.41
|
|
|
|
Say |
|
Item: 26 (B15C) CP Piller cock N-42 |
|
Basis:1
no. |
B1.Plumbing/Sanitr Pipe |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Piller cock |
1.000 |
no |
410.00 |
410.00 |
|
|
Sub-Total(B1) |
410.00
|
410.00
|
L4.Labour-Sanitary |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Piller cock1 |
1.000 |
no |
50.00 |
50.00 |
|
|
Sub-Total(L4) |
50.00
|
50.00
|
|
|
|
Total(1) |
|
460.00 |
|
Add over head on Total(1)
|
3.0 % |
13.80 |
|
|
|
Total(2) |
|
473.80 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
473.80 |
|
Add VAT on Unit Price |
4.5 % |
22.33 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
496.13
|
|
|
|
Say |
|
Item: 27 (B15D) Bib cock N-54 |
|
Basis:1
no. |
B1.Plumbing/Sanitr Pipe |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Bib cock |
1.000 |
no |
380.00 |
380.00 |
|
|
Sub-Total(B1) |
380.00
|
380.00
|
L4.Labour-Sanitary |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Bib Cock fitting |
1.000 |
no. |
50.00 |
50.00 |
|
|
Sub-Total(L4) |
50.00
|
50.00
|
|
|
|
Total(1) |
|
430.00 |
|
Add over head on Total(1)
|
3.0 % |
12.90 |
|
|
|
Total(2) |
|
442.90 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
442.90 |
|
Add VAT on Unit Price |
4.5 % |
20.87 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
463.77
|
|
|
|
Say |
|
Item: 28 (B15D1) Combined Bib Cock |
|
Basis:1
no. |
B1.Plumbing/Sanitr Pipe |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Cobined Bib cock |
1.000 |
no. |
425.00 |
425.00 |
|
|
Sub-Total(B1) |
425.00
|
425.00
|
L4.Labour-Sanitary |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Combined Bib Cock fitting |
1.000 |
no. |
55.00 |
55.00 |
|
|
Sub-Total(L4) |
55.00
|
55.00
|
|
|
|
Total(1) |
|
480.00 |
|
Add over head on Total(1)
|
3.0 % |
14.40 |
|
|
|
Total(2) |
|
494.40 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
494.40 |
|
Add VAT on Unit Price |
4.5 % |
23.30 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
517.70
|
|
|
|
Say |
|
Item: 29 (B15E) Wshing H-Basin BISF SuperVt |
|
Basis:1
no. |
B1.Plumbing/Sanitr Pipe |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Washing h-basin with fitt |
1.000 |
no |
2150.00 |
2150.00 |
|
CP Bashin wast |
1.000 |
No |
95.00 |
95.00 |
|
Connection pipe |
1.000 |
No |
80.00 |
80.00 |
|
|
Sub-Total(B1) |
2325.00
|
2325.00
|
L4.Labour-Sanitary |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Basin fitting |
1.000 |
no. |
150.00 |
150.00 |
|
|
Sub-Total(L4) |
150.00
|
150.00
|
|
|
|
Total(1) |
|
2475.00 |
|
Add over head on Total(1)
|
3.0 % |
74.25 |
|
|
|
Total(2) |
|
2549.25 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
2549.25 |
|
Add VAT on Unit Price |
4.5 % |
120.12 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
2669.37
|
|
|
|
Say |
|
Item: 30 (B15F1) Commode - BISF |
|
Basis:1
no. |
B1.Plumbing/Sanitr Pipe |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Connecting pipe |
1.000 |
no |
150.00 |
150.00 |
|
Commode BISF |
1.000 |
no. |
3500.00 |
3500.00 |
|
|
Sub-Total(B1) |
3650.00
|
3650.00
|
L4.Labour-Sanitary |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Commode fitting |
1.000 |
no. |
200.00 |
200.00 |
|
|
Sub-Total(L4) |
200.00
|
200.00
|
|
|
|
Total(1) |
|
3850.00 |
|
Add over head on Total(1)
|
3.0 % |
115.50 |
|
|
|
Total(2) |
|
3965.50 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
3965.50 |
|
Add VAT on Unit Price |
4.5 % |
186.86 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
4152.36
|
|
|
|
Say |
|
Item: 31 (B15F) L-pan BISF Standerd |
|
Basis:1
no. |
B1.Plumbing/Sanitr Pipe |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Long pan BISF with fittin |
1.000 |
no |
850.00 |
850.00 |
|
C.I Cistern |
1.000 |
no |
1050.00 |
1050.00 |
|
Connecting pipe |
1.000 |
no |
150.00 |
150.00 |
|
|
Sub-Total(B1) |
2050.00
|
2050.00
|
L4.Labour-Sanitary |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Long Pan fitting |
1.000 |
no. |
250.00 |
250.00 |
|
Cistern fitting |
1.000 |
no |
100.00 |
100.00 |
|
CI Trap fitting |
1.000 |
no |
100.00 |
100.00 |
|
|
Sub-Total(L4) |
450.00
|
450.00
|
|
|
|
Total(1) |
|
2500.00 |
|
Add over head on Total(1)
|
3.0 % |
75.00 |
|
|
|
Total(2) |
|
2575.00 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
2575.00 |
|
Add VAT on Unit Price |
4.5 % |
121.34 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
2696.34
|
|
|
|
Say |
|
Item: 32 (B15G1) Mirror 460x305x5 |
|
Basis:1
no. |
B1.Plumbing/Sanitr Pipe |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mirror - 460x305x5 |
1.000 |
no. |
200.00 |
200.00 |
|
|
Sub-Total(B1) |
200.00
|
200.00
|
L4.Labour-Sanitary |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mirror Fitting-450x300 |
1.000 |
no. |
50.00 |
50.00 |
|
|
Sub-Total(L4) |
50.00
|
50.00
|
|
|
|
Total(1) |
|
250.00 |
|
Add over head on Total(1)
|
3.0 % |
7.50 |
|
|
|
Total(2) |
|
257.50 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
257.50 |
|
Add VAT on Unit Price |
4.5 % |
12.13 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
269.63
|
|
|
|
Say |
|
Item: 33 (B15L) CP Towel Rail |
|
Basis:1
no. |
B1.Plumbing/Sanitr Pipe |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
CP Towel Rail |
1.000 |
no. |
250.00 |
250.00 |
|
|
Sub-Total(B1) |
250.00
|
250.00
|
L4.Labour-Sanitary |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Towel Rail Fitting |
1.000 |
no. |
25.00 |
25.00 |
|
|
Sub-Total(L4) |
25.00
|
25.00
|
|
|
|
Total(1) |
|
275.00 |
|
Add over head on Total(1)
|
3.0 % |
8.25 |
|
|
|
Total(2) |
|
283.25 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
283.25 |
|
Add VAT on Unit Price |
4.5 % |
13.35 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
296.60
|
|
|
|
Say |
|
Item: 34 (B15I) Soap Case N-113 |
|
Basis:1
no. |
B1.Plumbing/Sanitr Pipe |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Soap Case |
1.000 |
no |
500.00 |
500.00 |
|
|
Sub-Total(B1) |
500.00
|
500.00
|
L4.Labour-Sanitary |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Soap Tray fitting |
1.000 |
no. |
50.00 |
50.00 |
|
|
Sub-Total(L4) |
50.00
|
50.00
|
|
|
|
Total(1) |
|
550.00 |
|
Add over head on Total(1)
|
3.0 % |
16.50 |
|
|
|
Total(2) |
|
566.50 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
566.50 |
|
Add VAT on Unit Price |
4.5 % |
26.69 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
593.19
|
|
|
|
Say |
|
Item: 35 (B15J) Toilet paper holder |
|
Basis:1
no. |
B1.Plumbing/Sanitr Pipe |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
T-Paper Holder |
1.000 |
no |
350.00 |
350.00 |
|
|
Sub-Total(B1) |
350.00
|
350.00
|
L4.Labour-Sanitary |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Paper holder fitting |
1.000 |
no. |
50.00 |
50.00 |
|
|
Sub-Total(L4) |
50.00
|
50.00
|
|
|
|
Total(1) |
|
400.00 |
|
Add over head on Total(1)
|
3.0 % |
12.00 |
|
|
|
Total(2) |
|
412.00 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
412.00 |
|
Add VAT on Unit Price |
4.5 % |
19.41 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
431.41
|
|
|
|
Say |
|
Item: 36 (B15K) C.I Gratting 100 dia |
|
Basis:1
no. |
B1.Plumbing/Sanitr Pipe |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
100mm dia CI gratting |
1.000 |
no |
150.00 |
150.00 |
|
|
Sub-Total(B1) |
150.00
|
150.00
|
L4.Labour-Sanitary |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
CP Gratting fitting |
1.000 |
no |
45.00 |
45.00 |
|
|
Sub-Total(L4) |
45.00
|
45.00
|
|
|
|
Total(1) |
|
195.00 |
|
Add over head on Total(1)
|
3.0 % |
5.85 |
|
|
|
Total(2) |
|
200.85 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
200.85 |
|
Add VAT on Unit Price |
4.5 % |
9.46 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
210.31
|
|
|
|
Say |
|
Item: 37 (B03) SS Sink-single |
|
Basis:1
no. |
B1.Plumbing/Sanitr Pipe |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
SS Sink |
1.000 |
no. |
2000.00 |
2000.00 |
|
CP Bashin wast |
1.000 |
No |
95.00 |
95.00 |
|
|
Sub-Total(B1) |
2095.00
|
2095.00
|
L4.Labour-Sanitary |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sink fitting |
1.000 |
no. |
125.00 |
125.00 |
|
|
Sub-Total(L4) |
125.00
|
125.00
|
|
|
|
Total(1) |
|
2220.00 |
|
Add over head on Total(1)
|
3.0 % |
66.60 |
|
|
|
Total(2) |
|
2286.60 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
2286.60 |
|
Add VAT on Unit Price |
4.5 % |
107.75 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
2394.35
|
|
|
|
Say |
|
Item: 38A (A22A) Ins. pit A type 500x500-in-in |
|
Basis:1
no. |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Brick |
21.000 |
no. |
3.80 |
79.80 |
|
Sand - Local - Mymensingh |
2.520 |
cft |
13.00 |
32.76 |
|
Polythene |
0.120 |
kg |
77.00 |
9.24 |
|
Cement |
3.160 |
bag |
343.00 |
1083.88 |
|
Sand - Sylhet |
4.000 |
cft |
24.00 |
96.00 |
|
Stone-chips |
11.930 |
cft |
80.00 |
954.40 |
|
Re-bar - G40 |
31.940 |
kg |
38.50 |
1229.69 |
|
GI Wire |
0.220 |
kg |
90.00 |
19.80 |
|
|
Sub-Total(A1) |
3505.57
|
3505.57
|
B1.Plumbing/Sanitr Pipe |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
CI Cover 300 mm dia |
1.000 |
no. |
750.00 |
750.00 |
|
|
Sub-Total(B1) |
750.00
|
750.00
|
C1.Steel Structures |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Galvanized Angle 38x38 |
1.720 |
rft |
125.00 |
215.00 |
|
MS Grating 200x75 |
1.000 |
no. |
100.00 |
100.00 |
|
|
Sub-Total(C1) |
315.00
|
315.00
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Re-bar Work |
30.420 |
kg |
1.65 |
50.19 |
|
Formwork upto 10ft from P |
35.830 |
sft |
8.00 |
286.64 |
|
Dismentling F/W/Mar tile |
10.760 |
sft |
10.00 |
107.60 |
|
Neat Cement Finishing |
10.760 |
sft |
1.00 |
10.76 |
|
RCC Casting. |
13.660 |
cft |
8.00 |
109.28 |
|
|
Sub-Total(L0) |
564.47
|
564.47
|
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Earth Work in Excavation |
55.440 |
cft |
1.80 |
99.79 |
|
Filling |
28.300 |
cft |
1.00 |
28.30 |
|
Brck flat soling |
6.880 |
sft |
0.60 |
4.13 |
|
Patent stone with NCF |
2.690 |
sft |
3.00 |
8.07 |
|
|
Sub-Total(L1) |
140.29
|
140.29
|
L4.Labour-Sanitary |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Manhole Cover fixing |
1.000 |
no. |
300.00 |
300.00 |
|
|
Sub-Total(L4) |
300.00
|
300.00
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Forms |
35.830 |
sft |
5.00 |
179.15 |
|
|
Sub-Total(M1) |
179.15
|
179.15
|
|
|
|
Total(1) |
|
5754.48 |
|
Add over head on Total(1)
|
3.0 % |
172.63 |
|
|
|
Total(2) |
|
5927.12 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
5927.12 |
|
Add VAT on Unit Price |
4.5 % |
279.29 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
6206.41
|
|
|
|
Say |
|
Item: 39A (C01A) MS Angle Truss |
|
Basis:1000
kg. |
C1.Steel Structures |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
MS angle |
1050.000 |
kg |
38.00 |
39900.00 |
|
|
Sub-Total(C1) |
39900.00
|
179.15
|
L5.Labour-MS Work |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Truss making |
1000.000 |
kg |
8.00 |
8000.00 |
|
|
Sub-Total(L5) |
8000.00
|
179.15
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Welding Electrode VM 8-no |
2.000 |
pack |
520.00 |
1040.00 |
|
|
Sub-Total(M1) |
1040.00
|
179.15
|
|
|
|
Total(1) |
|
537.45 |
|
Add over head on Total(1)
|
3.0 % |
16.12 |
|
|
|
Total(2) |
|
553.57 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
553.57 |
|
Add VAT on Unit Price |
4.5 % |
26.08 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
579.66
|
|
|
|
Say |
|
Item: 39B (A10G) Re-bar Plain (G40) |
|
Basis:1000
kg. |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
GI Wire |
8.000 |
kg |
90.00 |
720.00 |
|
Re-bar 40 Plain |
1050.000 |
kg |
23.00 |
24150.00 |
|
|
Sub-Total(A1) |
24870.00
|
179.15
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Re-bar Work |
1000.000 |
kg |
1.65 |
1650.00 |
|
|
Sub-Total(L0) |
1650.00
|
179.15
|
|
|
|
Total(1) |
|
358.30 |
|
Add over head on Total(1)
|
3.0 % |
10.75 |
|
|
|
Total(2) |
|
369.05 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
369.05 |
|
Add VAT on Unit Price |
4.5 % |
17.39 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
386.44
|
|
|
|
Say |
|
Item: 40 (C01) MS Angle Purlin |
|
Basis:1000
kg. |
C1.Steel Structures |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
MS angle |
1050.000 |
kg |
38.00 |
39900.00 |
|
|
Sub-Total(C1) |
39900.00
|
179.15
|
L5.Labour-MS Work |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Making Purlin,rafter, box |
1000.000 |
kg |
6.50 |
6500.00 |
|
|
Sub-Total(L5) |
6500.00
|
179.15
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Welding Electrode VM 8-no |
2.000 |
pack |
520.00 |
1040.00 |
|
|
Sub-Total(M1) |
1040.00
|
179.15
|
|
|
|
Total(1) |
|
537.45 |
|
Add over head on Total(1)
|
3.0 % |
16.12 |
|
|
|
Total(2) |
|
553.57 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
553.57 |
|
Add VAT on Unit Price |
4.5 % |
26.08 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
579.66
|
|
|
|
Say |
|
Item: 41 (C03A) MS Window |
|
Basis:18
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
1.000 |
cft |
13.00 |
13.00 |
|
Cement |
0.100 |
bag |
343.00 |
34.30 |
|
|
Sub-Total(A1) |
47.30
|
28.29
|
C2.MS/SS Work i/c matr |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
MS Window |
18.000 |
sft |
100.00 |
1800.00 |
|
|
Sub-Total(C2) |
1800.00
|
1076.40
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Ordinary Labour Supply |
0.500 |
nos. |
100.00 |
50.00 |
|
Head Mason Supply |
0.500 |
nos. |
200.00 |
100.00 |
|
|
Sub-Total(L0) |
150.00
|
89.70
|
S1.Sub-contractor-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Painting to MS surface |
18.000 |
sft |
5.00 |
90.00 |
|
|
Sub-Total(S1) |
90.00
|
53.82
|
|
|
|
Total(1) |
|
1248.21 |
|
Add over head on Total(1)
|
3.0 % |
37.45 |
|
|
|
Total(2) |
|
1285.65 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
1285.65 |
|
Add VAT on Unit Price |
4.5 % |
60.58 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
1346.23
|
|
|
|
Say |
|
Item: 43 (A10F) Re-bar (G40) |
|
Basis:1000
kg. |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Re-bar - G40 |
1050.000 |
kg |
38.50 |
40425.00 |
|
GI Wire |
8.000 |
kg |
90.00 |
720.00 |
|
|
Sub-Total(A1) |
41145.00
|
53.82
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Re-bar Work |
1000.000 |
kg |
1.65 |
1650.00 |
|
|
Sub-Total(L0) |
1650.00
|
53.82
|
|
|
|
Total(1) |
|
107.64 |
|
Add over head on Total(1)
|
3.0 % |
3.23 |
|
|
|
Total(2) |
|
110.87 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
110.87 |
|
Add VAT on Unit Price |
4.5 % |
5.22 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
116.09
|
|
|
|
Say |
|
Item: 44 (A09C1) Sale of Old Office |
|
Basis:1
no. |
S1.Sub-contractor-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sale of Old Office |
1.000 |
no. |
-80000.00 |
-80000.00 |
|
|
Sub-Total(S1) |
-80000.00
|
-80000.00
|
|
|
|
Total(1) |
|
-80000.00 |
|
Add over head on Total(1)
|
3.0 % |
-2400.00 |
|
|
|
Total(2) |
|
-82400.00 |
|
Add Profit on Total(2) |
0.0 % |
0.00
|
|
|
|
Total(3) |
|
-82400.00 |
|
Add VAT on Unit Price |
4.5 % |
-3882.72 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
-86282.72
|
|
|
|
Say |
|