Project Fencing Work Around Solvent Store |
Item: 01 (A01D) E/Cuting with shoring,soil remove |
|
Basis:100
cft |
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Earth Work in Excavation |
100.000 |
cft |
1.80 |
180.00 |
|
|
Sub-Total(L1) |
180.00
|
63.57
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Shoring for Excavation |
38.440 |
sft |
2.15 |
82.65 |
|
|
Sub-Total(M1) |
82.65
|
29.19
|
|
|
|
Total(1) |
|
92.75 |
|
Add over head on Total(1)
|
5.0 % |
4.64 |
|
|
|
Total(2) |
|
97.39 |
|
Add Profit on Total(2) |
10.0 % |
9.74
|
|
|
|
Total(3) |
|
107.13 |
|
Add VAT on Unit Price |
4.5 % |
5.27 |
Add Income Tax on Unit Price
|
4.0 % |
4.68 |
|
|
|
Unit Price |
|
117.08
|
|
|
|
Say |
|
Item: 02A (A08B2) RCC (1:2:4) in Footing |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
22.500 |
cft |
13.00 |
292.50 |
|
Cement |
18.000 |
bag |
343.00 |
6174.00 |
|
Sand - Sylhet |
22.500 |
cft |
24.00 |
540.00 |
|
Stone-chips |
90.000 |
cft |
80.00 |
7200.00 |
|
|
Sub-Total(A1) |
14206.50
|
5017.03
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mixer m/c and vibrator |
100.000 |
cft |
2.00 |
200.00 |
|
|
Sub-Total(E1) |
200.00
|
70.63
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Form work Foot-col-Str |
61.820 |
sft |
6.00 |
370.92 |
|
RCC Casting. |
100.000 |
cft |
8.00 |
800.00 |
|
|
Sub-Total(L0) |
1170.92
|
413.51
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Forms |
61.820 |
sft |
5.00 |
309.10 |
|
|
Sub-Total(M1) |
309.10
|
109.16
|
|
|
|
Total(1) |
|
5610.32 |
|
Add over head on Total(1)
|
5.0 % |
280.52 |
|
|
|
Total(2) |
|
5890.84 |
|
Add Profit on Total(2) |
10.0 % |
589.08
|
|
|
|
Total(3) |
|
6479.92 |
|
Add VAT on Unit Price |
4.5 % |
318.68 |
Add Income Tax on Unit Price
|
4.0 % |
283.28 |
|
|
|
Unit Price |
|
7081.89
|
|
|
|
Say |
|
Item: 02B (A08D1) RCC (1:2:4) in GB-Boundary |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
22.500 |
cft |
13.00 |
292.50 |
|
Cement |
18.000 |
bag |
343.00 |
6174.00 |
|
Sand - Sylhet |
22.500 |
cft |
24.00 |
540.00 |
|
Stone-chips |
90.000 |
cft |
80.00 |
7200.00 |
|
|
Sub-Total(A1) |
14206.50
|
5017.03
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mixer m/c and vibrator |
100.000 |
cft |
2.00 |
200.00 |
|
Mini Dumper |
100.000 |
cft |
2.00 |
200.00 |
|
|
Sub-Total(E1) |
400.00
|
141.26
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Form work Foot-col-Str |
340.960 |
sft |
6.00 |
2045.76 |
|
|
Sub-Total(L0) |
2045.76
|
722.46
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Forms |
340.960 |
sft |
5.00 |
1704.80 |
|
|
Sub-Total(M1) |
1704.80
|
602.05
|
|
|
|
Total(1) |
|
6482.80 |
|
Add over head on Total(1)
|
5.0 % |
324.14 |
|
|
|
Total(2) |
|
6806.94 |
|
Add Profit on Total(2) |
10.0 % |
680.69
|
|
|
|
Total(3) |
|
7487.63 |
|
Add VAT on Unit Price |
4.5 % |
368.24 |
Add Income Tax on Unit Price
|
4.0 % |
327.33 |
|
|
|
Unit Price |
|
8183.20
|
|
|
|
Say |
|
Item: 02C (A08Z3) RCC (1:2:4) in Wall - 125mm |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
22.500 |
cft |
13.00 |
292.50 |
|
Cement |
18.000 |
bag |
343.00 |
6174.00 |
|
Sand - Sylhet |
22.500 |
cft |
24.00 |
540.00 |
|
Stone-chips |
90.000 |
cft |
80.00 |
7200.00 |
|
|
Sub-Total(A1) |
14206.50
|
5017.03
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mixer m/c and vibrator |
100.000 |
cft |
2.00 |
200.00 |
|
|
Sub-Total(E1) |
200.00
|
70.63
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Formwork upto 10ft from P |
476.200 |
sft |
8.00 |
3809.60 |
|
RCC Casting. |
100.000 |
cft |
8.00 |
800.00 |
|
|
Sub-Total(L0) |
4609.60
|
1627.88
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Forms |
476.200 |
sft |
5.00 |
2381.00 |
|
|
Sub-Total(M1) |
2381.00
|
840.85
|
|
|
|
Total(1) |
|
7556.39 |
|
Add over head on Total(1)
|
5.0 % |
377.82 |
|
|
|
Total(2) |
|
7934.21 |
|
Add Profit on Total(2) |
10.0 % |
793.42
|
|
|
|
Total(3) |
|
8727.63 |
|
Add VAT on Unit Price |
4.5 % |
429.23 |
Add Income Tax on Unit Price
|
4.0 % |
381.54 |
|
|
|
Unit Price |
|
9538.39
|
|
|
|
Say |
|
Item: 03 (A10F) Re-bar (G40) |
|
Basis:1000
kg. |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Re-bar - G40 |
1050.000 |
kg |
38.50 |
40425.00 |
|
GI Wire |
8.000 |
kg |
90.00 |
720.00 |
|
|
Sub-Total(A1) |
41145.00
|
840.85
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Re-bar Work |
1000.000 |
kg |
1.65 |
1650.00 |
|
|
Sub-Total(L0) |
1650.00
|
840.85
|
|
|
|
Total(1) |
|
1681.70 |
|
Add over head on Total(1)
|
5.0 % |
84.09 |
|
|
|
Total(2) |
|
1765.79 |
|
Add Profit on Total(2) |
10.0 % |
176.58
|
|
|
|
Total(3) |
|
1942.36 |
|
Add VAT on Unit Price |
4.5 % |
95.53 |
Add Income Tax on Unit Price
|
4.0 % |
84.91 |
|
|
|
Unit Price |
|
2122.80
|
|
|
|
Say |
|
Item: 04 (A12B) Plaster 12mm thick (1:4) |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
7.500 |
cft |
13.00 |
97.50 |
|
Cement |
1.000 |
bag |
343.00 |
343.00 |
|
|
Sub-Total(A1) |
440.50
|
47.42
|
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Plaster Work |
100.000 |
sft |
3.00 |
300.00 |
|
|
Sub-Total(L1) |
300.00
|
32.29
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Scaffolding |
1.000 |
set |
100.00 |
100.00 |
|
|
Sub-Total(M1) |
100.00
|
10.76
|
|
|
|
Total(1) |
|
90.47 |
|
Add over head on Total(1)
|
5.0 % |
4.52 |
|
|
|
Total(2) |
|
94.99 |
|
Add Profit on Total(2) |
10.0 % |
9.50
|
|
|
|
Total(3) |
|
104.49 |
|
Add VAT on Unit Price |
4.5 % |
5.14 |
Add Income Tax on Unit Price
|
4.0 % |
4.57 |
|
|
|
Unit Price |
|
114.20
|
|
|
|
Say |
|
Item: 05 (A13F) Weather coat paint |
|
Basis:100
sft |
A3.Material-Paint |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Plastron Sealer |
0.500 |
Ltr |
160.00 |
80.00 |
|
Enamel paint |
0.250 |
Ltr |
170.00 |
42.50 |
|
Snowcel |
2.500 |
kg |
7.60 |
19.00 |
|
Thinner-T6/T7 |
0.500 |
Ltr |
46.00 |
23.00 |
|
Weather Coat (ColorBank) |
1.420 |
Ltr |
227.85 |
323.55 |
|
|
Sub-Total(A3) |
488.05
|
52.53
|
L6.Labour Paints |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Weather coat painting |
100.000 |
sft |
4.00 |
400.00 |
|
|
Sub-Total(L6) |
400.00
|
43.06
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Scaffolding |
1.000 |
set |
100.00 |
100.00 |
|
|
Sub-Total(M1) |
100.00
|
10.76
|
|
|
|
Total(1) |
|
106.35 |
|
Add over head on Total(1)
|
5.0 % |
5.32 |
|
|
|
Total(2) |
|
111.67 |
|
Add Profit on Total(2) |
10.0 % |
11.17
|
|
|
|
Total(3) |
|
122.84 |
|
Add VAT on Unit Price |
4.5 % |
6.04 |
Add Income Tax on Unit Price
|
4.0 % |
5.37 |
|
|
|
Unit Price |
|
134.25
|
|
|
|
Say |
|
Item: 06 (C20) Chain Link Wire Fencing (12 BWG) |
|
Basis:1
sft |
S2.Alum,SS/MS,FalseCeil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
GI Fenc i/c MS Pipe-1~1.5 |
1.000 |
sft |
70.00 |
70.00 |
|
|
Sub-Total(S2) |
70.00
|
753.48
|
|
|
|
Total(1) |
|
753.48 |
|
Add over head on Total(1)
|
5.0 % |
37.67 |
|
|
|
Total(2) |
|
791.15 |
|
Add Profit on Total(2) |
10.0 % |
79.12
|
|
|
|
Total(3) |
|
870.27 |
|
Add VAT on Unit Price |
4.5 % |
42.80 |
Add Income Tax on Unit Price
|
4.0 % |
38.04 |
|
|
|
Unit Price |
|
951.11
|
|
|
|
Say |
|
Item: 07A (A02M) Brick Flat Soling with Polythene |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Filling Sand |
5.000 |
cft |
8.50 |
42.50 |
|
Brick |
300.000 |
no. |
3.80 |
1140.00 |
|
Polythene |
1.500 |
kg |
77.00 |
115.50 |
|
|
Sub-Total(A1) |
1298.00
|
139.72
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Ordinary Labour Supply |
0.200 |
nos. |
100.00 |
20.00 |
|
Head Mason Supply |
0.200 |
nos. |
200.00 |
40.00 |
|
|
Sub-Total(L0) |
60.00
|
6.46
|
|
|
|
Total(1) |
|
146.18 |
|
Add over head on Total(1)
|
5.0 % |
7.31 |
|
|
|
Total(2) |
|
153.48 |
|
Add Profit on Total(2) |
10.0 % |
15.35
|
|
|
|
Total(3) |
|
168.83 |
|
Add VAT on Unit Price |
4.5 % |
8.30 |
Add Income Tax on Unit Price
|
4.0 % |
7.38 |
|
|
|
Unit Price |
|
184.52
|
|
|
|
Say |
|
Item: 07B (A02N) Turfing |
|
Basis:100
sft |
S1.Sub-contractor-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Turfing |
100.000 |
sft |
1.00 |
100.00 |
|
|
Sub-Total(S1) |
100.00
|
10.76
|
|
|
|
Total(1) |
|
10.76 |
|
Add over head on Total(1)
|
5.0 % |
0.54 |
|
|
|
Total(2) |
|
11.30 |
|
Add Profit on Total(2) |
10.0 % |
1.13
|
|
|
|
Total(3) |
|
12.43 |
|
Add VAT on Unit Price |
4.5 % |
0.61 |
Add Income Tax on Unit Price
|
4.0 % |
0.54 |
|
|
|
Unit Price |
|
13.59
|
|
|
|
Say |
|
Item: 07C (A09F3) Chiiping of RCC Wall |
|
Basis:1
sft |
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Ordinary Labour Supply |
0.005 |
nos. |
100.00 |
0.50 |
|
|
Sub-Total(L0) |
0.50
|
5.38
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Cheisel - Hammer |
0.010 |
no |
55.00 |
0.55 |
|
|
Sub-Total(M1) |
0.55
|
5.92
|
|
|
|
Total(1) |
|
11.30 |
|
Add over head on Total(1)
|
5.0 % |
0.57 |
|
|
|
Total(2) |
|
11.87 |
|
Add Profit on Total(2) |
10.0 % |
1.19
|
|
|
|
Total(3) |
|
13.05 |
|
Add VAT on Unit Price |
4.5 % |
0.64 |
Add Income Tax on Unit Price
|
4.0 % |
0.57 |
|
|
|
Unit Price |
|
14.27
|
|
|
|
Say |
|
Item: 07D (C22) Gate with MS Pipe-50/25mm |
|
Basis:93
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
1.000 |
cft |
13.00 |
13.00 |
|
Cement |
0.250 |
bag |
343.00 |
85.75 |
|
|
Sub-Total(A1) |
98.75
|
11.43
|
C2.MS/SS Work i/c matr |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Gate with MS Pipe-50/25mm |
93.000 |
sft |
250.00 |
23250.00 |
|
|
Sub-Total(C2) |
23250.00
|
2691.00
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Ordinary Labour Supply |
1.000 |
nos. |
100.00 |
100.00 |
|
Head Mason Supply |
1.000 |
nos. |
200.00 |
200.00 |
|
|
Sub-Total(L0) |
300.00
|
34.72
|
|
|
|
Total(1) |
|
2737.15 |
|
Add over head on Total(1)
|
5.0 % |
136.86 |
|
|
|
Total(2) |
|
2874.01 |
|
Add Profit on Total(2) |
10.0 % |
287.40
|
|
|
|
Total(3) |
|
3161.41 |
|
Add VAT on Unit Price |
4.5 % |
155.48 |
Add Income Tax on Unit Price
|
4.0 % |
138.20 |
|
|
|
Unit Price |
|
3455.09
|
|
|
|
Say |
|