Return Main Menu

Project BPL Project Store at Technology Park
Item: 01 (A01) Earth work in Excavation
Basis:1000 cft
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Earth Work in Excavation
1000.000
cft
1.80
1800.00
Sub-Total(L1)
1800.00
63.57
Total(1)
63.57
Add over head on Total(1)
3.0 %
1.91
Total(2)
65.47
Add Profit on Total(2)
8.0 %
5.24
Total(3)
70.71
Add VAT on Unit Price
4.5 %
3.33
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
74.04
Say
74
per M3
Item: 02 (A05) Sand Filling
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Filling Sand
130.000
cft
8.50
1105.00
Sub-Total(A1)
1105.00
390.23
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mini Roller Compaction
100.000
cft
1.00
100.00
Mini Dumper
130.000
cft
2.00
260.00
Payloader
0.000
day
8000.00
0.00
Dump Truck
0.000
day
8300.00
0.00
Sub-Total(E1)
360.00
127.13
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
0.800
nos.
100.00
80.00
Sub-Total(L0)
80.00
28.25
Total(1)
545.62
Add over head on Total(1)
3.0 %
16.37
Total(2)
561.99
Add Profit on Total(2)
8.0 %
44.96
Total(3)
606.94
Add VAT on Unit Price
4.5 %
28.60
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
635.54
Say
636
per M3
Item: 03A (A02B) Brick Flat Soling
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Filling Sand
5.000
cft
8.50
42.50
Brick
300.000
no.
3.80
1140.00
Sub-Total(A1)
1182.50
127.28
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
0.100
nos.
100.00
10.00
Head Mason Supply
0.250
nos.
200.00
50.00
Sub-Total(L0)
60.00
6.46
Total(1)
133.74
Add over head on Total(1)
3.0 %
4.01
Total(2)
137.75
Add Profit on Total(2)
8.0 %
11.02
Total(3)
148.78
Add VAT on Unit Price
4.5 %
7.01
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
155.79
Say
156
per M2
Item: 03B (A02A) Brick Flat Soling- Road
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Filling Sand
5.000
cft
8.50
42.50
Brick
300.000
no.
3.80
1140.00
Sub-Total(A1)
1182.50
127.28
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
0.100
nos.
100.00
10.00
Head Mason Supply
0.250
nos.
200.00
50.00
Sub-Total(L0)
60.00
6.46
Total(1)
133.74
Add over head on Total(1)
3.0 %
4.01
Total(2)
137.75
Add Profit on Total(2)
8.0 %
11.02
Total(3)
148.78
Add VAT on Unit Price
4.5 %
7.01
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
155.79
Say
156
per M2
Item: 04 (A03O) HBB
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Filling Sand
8.000
cft
8.50
68.00
Brick
500.000
no.
3.80
1900.00
Sub-Total(A1)
1968.00
211.84
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
0.200
nos.
100.00
20.00
Head Mason Supply
0.500
nos.
200.00
100.00
Sub-Total(L0)
120.00
12.92
Total(1)
224.75
Add over head on Total(1)
3.0 %
6.74
Total(2)
231.49
Add Profit on Total(2)
8.0 %
18.52
Total(3)
250.01
Add VAT on Unit Price
4.5 %
11.78
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
261.80
Say
262
per M2
Item: 05 (A03P) Brick on Edging
Basis:100 rft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Filling Sand
5.000
cft
8.50
42.50
Brick
270.000
no.
3.80
1026.00
Sub-Total(A1)
1068.50
12.92
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
0.400
nos.
100.00
40.00
Head Mason Supply
0.300
nos.
200.00
60.00
Sub-Total(L0)
100.00
12.92
Total(1)
25.83
Add over head on Total(1)
3.0 %
0.78
Total(2)
26.61
Add Profit on Total(2)
8.0 %
2.13
Total(3)
28.74
Add VAT on Unit Price
4.5 %
1.35
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
30.09
Say
30
per RM
Item: 06 (A02E) Double Layer Polythene
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Polythene
3.000
kg
77.00
231.00
Sub-Total(A1)
231.00
24.86
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Polythene laying
200.000
sft
0.20
40.00
Sub-Total(L1)
40.00
4.31
Total(1)
29.17
Add over head on Total(1)
3.0 %
0.88
Total(2)
30.05
Add Profit on Total(2)
8.0 %
2.40
Total(3)
32.45
Add VAT on Unit Price
4.5 %
1.53
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
33.98
Say
34
per M2
Item: 07 (A03C) CC (1:2:4) 75mm thick with NCF
Basis:100 cft
Total(1)
0.00
Add over head on Total(1)
3.0 %
0.88
Total(2)
30.05
Add Profit on Total(2)
8.0 %
2.40
Total(3)
32.45
Add VAT on Unit Price
4.5 %
1.53
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
33.98
Say
34
per M3
Item: 08 (A08) RCC (1:2:4) in Floor on Grade
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
15.000
cft
13.00
195.00
Cement
18.000
bag
343.00
6174.00
Sand - Sylhet
30.000
cft
24.00
720.00
Brick-chips
90.000
cft
40.00
3600.00
Sub-Total(A1)
10689.00
3774.82
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Formwork upto 10ft from P
50.000
sft
8.00
400.00
RCC Casting.
100.000
cft
8.00
800.00
Sub-Total(L0)
1200.00
423.78
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Forms
50.000
sft
5.00
250.00
Sub-Total(M1)
250.00
88.29
Total(1)
4286.89
Add over head on Total(1)
3.0 %
128.61
Total(2)
4415.49
Add Profit on Total(2)
8.0 %
353.24
Total(3)
4768.73
Add VAT on Unit Price
4.5 %
224.70
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
4993.44
Say
4993
per M3
Item: 09 (A10F) Re-bar (G40)
Basis:1000 kg.
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Re-bar - G40
1050.000
kg
38.50
40425.00
GI Wire
8.000
kg
90.00
720.00
Sub-Total(A1)
41145.00
88.29
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Re-bar Work
1000.000
kg
1.65
1650.00
Sub-Total(L0)
1650.00
88.29
Total(1)
176.58
Add over head on Total(1)
3.0 %
5.30
Total(2)
181.87
Add Profit on Total(2)
8.0 %
14.55
Total(3)
196.42
Add VAT on Unit Price
4.5 %
9.26
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
205.68
Say
206
per MT
Item: 10 (C12A) 100mm dia MS Pipe- Old
Basis:14 rft
C1.Steel Structures
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS Pipe 100mm dia Old
14.814
rft
100.00
1481.40
12mm dia Rowl bolt
8.000
no
25.00
200.00
Sub-Total(C1)
1681.40
88.29
L5.Labour-MS Work
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
100mm dia MS Pipe fitting
14.108
rft
8.00
112.86
Sub-Total(L5)
112.86
88.29
S1.Sub-contractor-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Painting to MS Pipe
14.700
sft
6.00
88.20
Sub-Total(S1)
88.20
88.29
Total(1)
264.86
Add over head on Total(1)
3.0 %
7.95
Total(2)
272.81
Add Profit on Total(2)
8.0 %
21.82
Total(3)
294.63
Add VAT on Unit Price
4.5 %
13.88
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
308.52
Say
309
per RM
Item: 11 (C06) MS Plates
Basis:1000 kg.
C1.Steel Structures
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
M.S plate
1050.000
kg
45.00
47250.00
Sub-Total(C1)
47250.00
88.29
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Welding Electrode VM 8-no
1.000
pack
520.00
520.00
Sub-Total(M1)
520.00
88.29
S1.Sub-contractor-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Painting to MS angle
34.500
sft
6.00
207.00
Sub-Total(S1)
207.00
88.29
S2.Alum,SS/MS,FalseCeil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Welder Supply
10.000
nos.
200.00
2000.00
Sub-Total(S2)
2000.00
88.29
Total(1)
353.15
Add over head on Total(1)
3.0 %
10.59
Total(2)
363.74
Add Profit on Total(2)
8.0 %
29.10
Total(3)
392.84
Add VAT on Unit Price
4.5 %
18.51
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
411.36
Say
411
per TON
Item: 12 (C26) 12mm Dia Bolt with nut 300mm L
Basis:1 no.
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Re-bar 40 Plain
0.320
kg
23.00
7.36
Sub-Total(A1)
7.36
7.36
C1.Steel Structures
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
10 dia Nut - bolt
1.000
no
8.00
8.00
Sub-Total(C1)
8.00
8.00
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Welding Electrode VM 8-no
0.010
pack
520.00
5.20
Sub-Total(M1)
5.20
5.20
S2.Alum,SS/MS,FalseCeil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Welder Supply
0.050
nos.
200.00
10.00
Sub-Total(S2)
10.00
10.00
Total(1)
30.56
Add over head on Total(1)
3.0 %
0.92
Total(2)
31.48
Add Profit on Total(2)
8.0 %
2.52
Total(3)
33.99
Add VAT on Unit Price
4.5 %
1.60
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
35.60
Say
36
per NO.
Item: 13 (C01A) MS Angle Truss
Basis:1000 kg.
C1.Steel Structures
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS angle
1050.000
kg
38.00
39900.00
Sub-Total(C1)
39900.00
10.00
L5.Labour-MS Work
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Truss making
1000.000
kg
8.00
8000.00
Sub-Total(L5)
8000.00
10.00
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Welding Electrode VM 8-no
2.000
pack
520.00
1040.00
Sub-Total(M1)
1040.00
10.00
Total(1)
30.00
Add over head on Total(1)
3.0 %
0.90
Total(2)
30.90
Add Profit on Total(2)
8.0 %
2.47
Total(3)
33.37
Add VAT on Unit Price
4.5 %
1.57
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
34.94
Say
35
per TON
Item: 14 (C14A) CI Sheet Roofing (38x38x5 Purlin)
Basis:100 sft
C1.Steel Structures
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS angle
53.000
kg
38.00
2014.00
J-Hook
65.000
no
2.50
162.50
CI Sheet 0.45mm
0.700
Bun
3000.00
2100.00
Sub-Total(C1)
4276.50
460.32
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Welding M/c
50.480
kg
0.50
25.24
Sub-Total(E1)
25.24
2.72
L5.Labour-MS Work
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Making Purlin,rafter, box
50.480
kg
6.50
328.12
Sub-Total(L5)
328.12
35.32
S1.Sub-contractor-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Painting to MS angle
27.650
sft
6.00
165.90
Sub-Total(S1)
165.90
17.86
S2.Alum,SS/MS,FalseCeil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
CI Sheet roofing
100.000
sft
2.75
275.00
Sub-Total(S2)
275.00
29.60
Total(1)
545.82
Add over head on Total(1)
3.0 %
16.37
Total(2)
562.19
Add Profit on Total(2)
8.0 %
44.98
Total(3)
607.17
Add VAT on Unit Price
4.5 %
28.61
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
635.78
Say
636
per M2
Item: 15 (C14B) CI Sheet Roofing (75x75x6 Purlin)
Basis:100 sft
C1.Steel Structures
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS angle
106.000
kg
38.00
4028.00
J-Hook
65.000
no
2.50
162.50
CI Sheet 0.45mm
0.700
Bun
3000.00
2100.00
Sub-Total(C1)
6290.50
677.11
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Welding M/c
100.960
kg
0.50
50.48
Sub-Total(E1)
50.48
5.43
L5.Labour-MS Work
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Making Purlin,rafter, box
100.960
kg
6.50
656.24
Sub-Total(L5)
656.24
70.64
S1.Sub-contractor-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Painting to MS angle
55.300
sft
6.00
331.80
Sub-Total(S1)
331.80
35.71
S2.Alum,SS/MS,FalseCeil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
CI Sheet roofing
100.000
sft
2.75
275.00
Sub-Total(S2)
275.00
29.60
Total(1)
818.50
Add over head on Total(1)
3.0 %
24.55
Total(2)
843.05
Add Profit on Total(2)
8.0 %
67.44
Total(3)
910.50
Add VAT on Unit Price
4.5 %
42.90
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
953.40
Say
953
per M2
Item: 16 (C03A) MS Window
Basis:18 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
1.000
cft
13.00
13.00
Cement
0.100
bag
343.00
34.30
Sub-Total(A1)
47.30
28.29
C2.MS/SS Work i/c matr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS Window
18.000
sft
100.00
1800.00
Sub-Total(C2)
1800.00
1076.40
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
0.500
nos.
100.00
50.00
Head Mason Supply
0.500
nos.
200.00
100.00
Sub-Total(L0)
150.00
89.70
S1.Sub-contractor-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Painting to MS surface
18.000
sft
5.00
90.00
Sub-Total(S1)
90.00
53.82
Total(1)
1248.21
Add over head on Total(1)
3.0 %
37.45
Total(2)
1285.65
Add Profit on Total(2)
8.0 %
102.85
Total(3)
1388.50
Add VAT on Unit Price
4.5 %
65.43
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
1453.93
Say
1454
per M2
Item: 17 (A11R0) MS Door Shutter Angle Frame
Basis:52 sft
S2.Alum,SS/MS,FalseCeil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS Swing Door i/c C.Sheet
51.600
sft
260.00
13416.00
Sub-Total(S2)
13416.00
2798.64
Total(1)
2798.64
Add over head on Total(1)
3.0 %
83.96
Total(2)
2882.60
Add Profit on Total(2)
8.0 %
230.61
Total(3)
3113.21
Add VAT on Unit Price
4.5 %
146.70
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
3259.90
Say
3260
per M2
Item: 18A (A02O) Levelling, Dressing
Basis:100 sft
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
1.000
nos.
100.00
100.00
Sub-Total(L0)
100.00
10.76
Total(1)
10.76
Add over head on Total(1)
3.0 %
0.32
Total(2)
11.09
Add Profit on Total(2)
8.0 %
0.89
Total(3)
11.97
Add VAT on Unit Price
4.5 %
0.56
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
12.54
Say
13
per M2
Item: 18B (C09) Fibre glass sheet
Basis:100 sft
C1.Steel Structures
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS angle
53.000
kg
38.00
2014.00
Fibre glass sheet
147.330
sft
65.00
9576.45
J-Hook
60.000
no
2.50
150.00
Sub-Total(C1)
11740.45
1263.74
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Welding M/c
50.480
kg
0.50
25.24
Sub-Total(E1)
25.24
2.72
L5.Labour-MS Work
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Making Purlin,rafter, box
50.480
kg
6.50
328.12
Fibre glass roofing
100.000
sft
6.00
600.00
Sub-Total(L5)
928.12
99.90
S1.Sub-contractor-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Painting to MS angle
27.650
sft
6.00
165.90
Sub-Total(S1)
165.90
17.86
Total(1)
1384.22
Add over head on Total(1)
3.0 %
41.53
Total(2)
1425.75
Add Profit on Total(2)
8.0 %
114.06
Total(3)
1539.81
Add VAT on Unit Price
4.5 %
72.56
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
1612.36
Say
1612
per M2
Item: 18C (A02H) BFS with m-joint(1:4)-3% pudlu
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
300.000
no.
3.80
1140.00
Sand - Local - Mymensingh
5.000
cft
13.00
65.00
Cement
2.000
bag
343.00
686.00
Pudloo
3.000
kg
70.00
210.00
Sub-Total(A1)
2101.00
226.15
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
BFS with Morter joint
100.000
sft
1.50
150.00
Sub-Total(L1)
150.00
16.15
Total(1)
242.30
Add over head on Total(1)
3.0 %
7.27
Total(2)
249.57
Add Profit on Total(2)
8.0 %
19.97
Total(3)
269.53
Add VAT on Unit Price
4.5 %
12.70
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
282.23
Say
282
per M2
Item: 18D (A03O1) Plinth Protection HBB
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
500.000
no.
3.80
1900.00
Sand - Local - Mymensingh
16.000
cft
13.00
208.00
Cement
2.600
bag
343.00
891.80
Sub-Total(A1)
2999.80
322.90
Total(1)
322.90
Add over head on Total(1)
3.0 %
9.69
Total(2)
332.59
Add Profit on Total(2)
8.0 %
26.61
Total(3)
359.19
Add VAT on Unit Price
4.5 %
16.93
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
376.12
Say
376
per M2
Item: 18E (A02P) 75mm CC With Polythene Sheet
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
3.750
cft
13.00
48.75
Polythene
3.000
kg
77.00
231.00
Cement
5.000
bag
343.00
1715.00
Sand - Sylhet
7.500
cft
24.00
180.00
Brick-chips
22.500
cft
40.00
900.00
Sub-Total(A1)
3074.75
330.97
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
25.000
cft
2.00
50.00
Sub-Total(E1)
50.00
5.38
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
RCC Casting.
25.000
cft
8.00
200.00
Sub-Total(L0)
200.00
21.53
Total(1)
357.88
Add over head on Total(1)
3.0 %
10.74
Total(2)
368.61
Add Profit on Total(2)
8.0 %
29.49
Total(3)
398.10
Add VAT on Unit Price
4.5 %
18.76
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
416.86
Say
417
per M2