Project Solvent Store at Technology Park |
Item: 02 (A01C) Earth Excavation |
|
Basis:100
cft |
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Earth Work in Excavation |
100.000 |
cft |
1.80 |
180.00 |
|
|
Sub-Total(L1) |
180.00
|
63.57
|
|
|
|
Total(1) |
|
63.57 |
|
Add over head on Total(1)
|
3.0 % |
1.91 |
|
|
|
Total(2) |
|
65.47 |
|
Add Profit on Total(2) |
8.0 % |
5.24
|
|
|
|
Total(3) |
|
70.71 |
|
Add VAT on Unit Price |
4.5 % |
3.33 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
74.04
|
|
|
|
Say |
|
Item: 25K (A02H) BFS with m-joint(1:4)-3% pudlu |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Brick |
300.000 |
no. |
3.80 |
1140.00 |
|
Sand - Local - Mymensingh |
5.000 |
cft |
13.00 |
65.00 |
|
Cement |
2.000 |
bag |
343.00 |
686.00 |
|
Pudloo |
3.000 |
kg |
70.00 |
210.00 |
|
|
Sub-Total(A1) |
2101.00
|
226.15
|
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
BFS with Morter joint |
100.000 |
sft |
1.50 |
150.00 |
|
|
Sub-Total(L1) |
150.00
|
16.15
|
|
|
|
Total(1) |
|
242.30 |
|
Add over head on Total(1)
|
3.0 % |
7.27 |
|
|
|
Total(2) |
|
249.57 |
|
Add Profit on Total(2) |
8.0 % |
19.97
|
|
|
|
Total(3) |
|
269.53 |
|
Add VAT on Unit Price |
4.5 % |
12.70 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
282.23
|
|
|
|
Say |
|
Item: 19 (A03D1) 38mm patent stone (1:1.5:3) |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
3.440 |
cft |
13.00 |
44.72 |
|
Cement |
2.750 |
bag |
343.00 |
943.25 |
|
Sand - Sylhet |
3.440 |
cft |
24.00 |
82.56 |
|
Brick-chips |
10.310 |
cft |
40.00 |
412.40 |
|
|
Sub-Total(A1) |
1482.93
|
159.62
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mixer m/c and vibrator |
12.500 |
cft |
2.00 |
25.00 |
|
Mini Dumper |
12.500 |
cft |
2.00 |
25.00 |
|
|
Sub-Total(E1) |
50.00
|
5.38
|
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
CC Work |
12.500 |
cft |
5.00 |
62.50 |
|
|
Sub-Total(L1) |
62.50
|
6.73
|
|
|
|
Total(1) |
|
171.73 |
|
Add over head on Total(1)
|
3.0 % |
5.15 |
|
|
|
Total(2) |
|
176.88 |
|
Add Profit on Total(2) |
8.0 % |
14.15
|
|
|
|
Total(3) |
|
191.03 |
|
Add VAT on Unit Price |
4.5 % |
9.00 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
200.04
|
|
|
|
Say |
|
Item: 03 (A03F) (1.3.6) Mass Concrete |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Cement |
12.000 |
bag |
343.00 |
4116.00 |
|
Sand - Sylhet |
45.000 |
cft |
24.00 |
1080.00 |
|
Stone-chips |
90.000 |
cft |
80.00 |
7200.00 |
|
|
Sub-Total(A1) |
12396.00
|
4377.65
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mixer m/c and vibrator |
100.000 |
cft |
2.00 |
200.00 |
|
|
Sub-Total(E1) |
200.00
|
70.63
|
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
CC Work |
100.000 |
cft |
5.00 |
500.00 |
|
|
Sub-Total(L1) |
500.00
|
176.58
|
|
|
|
Total(1) |
|
4624.85 |
|
Add over head on Total(1)
|
3.0 % |
138.75 |
|
|
|
Total(2) |
|
4763.60 |
|
Add Profit on Total(2) |
8.0 % |
381.09
|
|
|
|
Total(3) |
|
5144.69 |
|
Add VAT on Unit Price |
4.5 % |
242.42 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
5387.11
|
|
|
|
Say |
|
Item: 04 (A03G) 50mm DPC (1:1.5:3) |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
7.500 |
cft |
13.00 |
97.50 |
|
Cement |
4.000 |
bag |
343.00 |
1372.00 |
|
Stone-chips |
15.000 |
cft |
80.00 |
1200.00 |
|
Plastocrete super-Sika |
1.000 |
kg |
155.00 |
155.00 |
|
|
Sub-Total(A1) |
2824.50
|
304.03
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mixer m/c and vibrator |
16.700 |
cft |
2.00 |
33.40 |
|
|
Sub-Total(E1) |
33.40
|
3.60
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
D.P.C. |
100.000 |
sft |
3.00 |
300.00 |
|
|
Sub-Total(L0) |
300.00
|
32.29
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Wood shutter-3time |
1.110 |
cft |
350.00 |
388.50 |
|
|
Sub-Total(M1) |
388.50
|
41.82
|
|
|
|
Total(1) |
|
381.73 |
|
Add over head on Total(1)
|
3.0 % |
11.45 |
|
|
|
Total(2) |
|
393.19 |
|
Add Profit on Total(2) |
8.0 % |
31.45
|
|
|
|
Total(3) |
|
424.64 |
|
Add VAT on Unit Price |
4.5 % |
20.01 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
444.65
|
|
|
|
Say |
|
Item: 25A (A06B1) Brickwork with existing brick |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
40.000 |
cft |
13.00 |
520.00 |
|
Cement |
5.000 |
bag |
343.00 |
1715.00 |
|
|
Sub-Total(A1) |
2235.00
|
789.29
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
250mm Brickwork upto 7 ft |
100.000 |
cft |
4.25 |
425.00 |
|
|
Sub-Total(L0) |
425.00
|
150.09
|
|
|
|
Total(1) |
|
939.38 |
|
Add over head on Total(1)
|
3.0 % |
28.18 |
|
|
|
Total(2) |
|
967.56 |
|
Add Profit on Total(2) |
8.0 % |
77.40
|
|
|
|
Total(3) |
|
1044.97 |
|
Add VAT on Unit Price |
4.5 % |
49.24 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
1094.20
|
|
|
|
Say |
|
Item: 09 (A06C) 250mm thick B-wall (1:5) - Supers |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Brick |
1200.000 |
no. |
3.80 |
4560.00 |
|
Sand - Local - Mymensingh |
40.000 |
cft |
13.00 |
520.00 |
|
Cement |
6.000 |
bag |
343.00 |
2058.00 |
|
|
Sub-Total(A1) |
7138.00
|
2520.78
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
B/w:15.5-27ft Scffld(Part |
100.000 |
cft |
6.00 |
600.00 |
|
|
Sub-Total(L0) |
600.00
|
211.89
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Scaffolding |
1.000 |
set |
100.00 |
100.00 |
|
|
Sub-Total(M1) |
100.00
|
35.32
|
|
|
|
Total(1) |
|
2767.99 |
|
Add over head on Total(1)
|
3.0 % |
83.04 |
|
|
|
Total(2) |
|
2851.03 |
|
Add Profit on Total(2) |
8.0 % |
228.08
|
|
|
|
Total(3) |
|
3079.11 |
|
Add VAT on Unit Price |
4.5 % |
145.09 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
3224.20
|
|
|
|
Say |
|
Item: 08 (A06F) 125 B/Wall (1:4) |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Brick |
500.000 |
no. |
3.80 |
1900.00 |
|
Sand - Local - Mymensingh |
17.000 |
cft |
13.00 |
221.00 |
|
Cement |
3.000 |
bag |
343.00 |
1029.00 |
|
|
Sub-Total(A1) |
3150.00
|
339.07
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
125mm thick Brick Work |
100.000 |
sft |
6.00 |
600.00 |
|
|
Sub-Total(L0) |
600.00
|
64.58
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Scaffolding |
0.000 |
set |
100.00 |
0.00 |
|
|
Sub-Total(M1) |
0.00
|
0.00
|
|
|
|
Total(1) |
|
403.65 |
|
Add over head on Total(1)
|
3.0 % |
12.11 |
|
|
|
Total(2) |
|
415.76 |
|
Add Profit on Total(2) |
8.0 % |
33.26
|
|
|
|
Total(3) |
|
449.02 |
|
Add VAT on Unit Price |
4.5 % |
21.16 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
470.18
|
|
|
|
Say |
|
Item: 01A (A08A) RCC(1:1.5:3) in Pile (400x400) |
|
Basis:60
rft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Cement |
23.000 |
bag |
343.00 |
7889.00 |
|
Sand - Sylhet |
43.000 |
cft |
24.00 |
1032.00 |
|
Stone-chips |
86.000 |
cft |
80.00 |
6880.00 |
|
|
Sub-Total(A1) |
15801.00
|
0.00
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mini Dumper |
102.713 |
cft |
2.00 |
205.43 |
|
Batching Plant , Vibrator |
102.713 |
cft |
8.00 |
821.70 |
|
Transit mixer |
0.000 |
cft |
10.00 |
0.00 |
|
|
Sub-Total(E1) |
1027.13
|
0.00
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Formwork upto 10ft from P |
241.840 |
sft |
8.00 |
1934.72 |
|
Sand Screening |
43.000 |
cft |
1.00 |
43.00 |
|
RCC Casting. |
102.713 |
cft |
8.00 |
821.70 |
|
|
Sub-Total(L0) |
2799.42
|
0.00
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Pile Shutter (steel) |
241.840 |
sft |
12.00 |
2902.08 |
|
Cost of Pre-casr yard |
59.642 |
rft |
8.00 |
477.14 |
|
Local carring - Cement |
23.000 |
bag |
1.00 |
23.00 |
|
Stome-chips screening |
0.000 |
cft |
1.00 |
0.00 |
|
Form oil,Grinding Disk et |
59.642 |
rft |
1.00 |
59.64 |
|
|
Sub-Total(M1) |
3461.86
|
0.00
|
|
|
|
Total(1) |
|
0.00 |
|
Add over head on Total(1)
|
3.0 % |
0.00 |
|
|
|
Total(2) |
|
0.00 |
|
Add Profit on Total(2) |
8.0 % |
0.00
|
|
|
|
Total(3) |
|
0.00 |
|
Add VAT on Unit Price |
4.5 % |
0.00 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
0.00
|
|
|
|
Say |
|
Item: 06A (A08B1) RCC(1:1.5:3) in Pile Cap |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
14.330 |
cft |
13.00 |
186.29 |
|
Cement |
22.000 |
bag |
343.00 |
7546.00 |
|
Sand - Sylhet |
28.670 |
cft |
24.00 |
688.08 |
|
Stone-chips |
86.000 |
cft |
80.00 |
6880.00 |
|
|
Sub-Total(A1) |
15300.37
|
5403.33
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mini Dumper |
100.000 |
cft |
2.00 |
200.00 |
|
Batching Plant , Vibrator |
100.000 |
cft |
8.00 |
800.00 |
|
|
Sub-Total(E1) |
1000.00
|
353.15
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Formwork upto 10ft from P |
89.310 |
sft |
8.00 |
714.48 |
|
Sand Screening |
43.000 |
cft |
1.00 |
43.00 |
|
RCC Casting. |
100.000 |
cft |
8.00 |
800.00 |
|
|
Sub-Total(L0) |
1557.48
|
550.02
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Forms |
61.820 |
sft |
5.00 |
309.10 |
|
|
Sub-Total(M1) |
309.10
|
109.16
|
|
|
|
Total(1) |
|
6415.66 |
|
Add over head on Total(1)
|
3.0 % |
192.47 |
|
|
|
Total(2) |
|
6608.13 |
|
Add Profit on Total(2) |
8.0 % |
528.65
|
|
|
|
Total(3) |
|
7136.78 |
|
Add VAT on Unit Price |
4.5 % |
336.29 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
7473.07
|
|
|
|
Say |
|
Item: 06B (A08C) RCC (1:1.5:3) in Column |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Cement |
22.000 |
bag |
343.00 |
7546.00 |
|
Sand - Sylhet |
46.000 |
cft |
24.00 |
1104.00 |
|
Stone-chips |
91.000 |
cft |
80.00 |
7280.00 |
|
|
Sub-Total(A1) |
15930.00
|
5625.68
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mini Dumper |
100.000 |
cft |
2.00 |
200.00 |
|
M/C-Vibrator,S-structure |
100.000 |
cft |
5.00 |
500.00 |
|
|
Sub-Total(E1) |
700.00
|
247.21
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Ordinary Labour Supply |
1.000 |
nos. |
100.00 |
100.00 |
|
RCC Casting-Superstructur |
100.000 |
sft |
10.00 |
1000.00 |
|
FormWork:24-33ft from PL |
305.000 |
sft |
10.00 |
3050.00 |
|
|
Sub-Total(L0) |
4150.00
|
1465.57
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Forms |
305.000 |
sft |
5.00 |
1525.00 |
|
Hessain cloth |
323.000 |
sft |
1.00 |
323.00 |
|
|
Sub-Total(M1) |
1848.00
|
652.62
|
|
|
|
Total(1) |
|
7991.08 |
|
Add over head on Total(1)
|
3.0 % |
239.73 |
|
|
|
Total(2) |
|
8230.81 |
|
Add Profit on Total(2) |
8.0 % |
658.46
|
|
|
|
Total(3) |
|
8889.28 |
|
Add VAT on Unit Price |
4.5 % |
418.87 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
9308.14
|
|
|
|
Say |
|
Item: 06C (A08E) RCC (1:1.5:3) in Suspended slab |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Cement |
22.000 |
bag |
343.00 |
7546.00 |
|
Sand - Sylhet |
43.000 |
cft |
24.00 |
1032.00 |
|
Stone-chips |
86.000 |
cft |
80.00 |
6880.00 |
|
|
Sub-Total(A1) |
15458.00
|
5458.99
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mixer m/c and vibrator |
100.000 |
cft |
2.00 |
200.00 |
|
Mini Dumper |
0.000 |
cft |
2.00 |
0.00 |
|
|
Sub-Total(E1) |
200.00
|
70.63
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Formwork upto 10ft from P |
240.000 |
sft |
8.00 |
1920.00 |
|
RCC Casting. |
100.000 |
cft |
8.00 |
800.00 |
|
|
Sub-Total(L0) |
2720.00
|
960.57
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
wood use 5-time-Garjan |
0.500 |
cft |
850.00 |
425.00 |
|
B-plate with pipe |
0.000 |
no |
16.00 |
0.00 |
|
Steel form,S-structure |
240.000 |
sft |
10.00 |
2400.00 |
|
Steel beam,S-structure |
0.000 |
no |
40.00 |
0.00 |
|
Wood use-6time mango |
1.200 |
cft |
350.00 |
420.00 |
|
|
Sub-Total(M1) |
3245.00
|
1145.97
|
|
|
|
Total(1) |
|
7636.16 |
|
Add over head on Total(1)
|
3.0 % |
229.08 |
|
|
|
Total(2) |
|
7865.25 |
|
Add Profit on Total(2) |
8.0 % |
629.22
|
|
|
|
Total(3) |
|
8494.47 |
|
Add VAT on Unit Price |
4.5 % |
400.26 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
8894.73
|
|
|
|
Say |
|
Item: 23 (A08H) Rcc Ins. pit (500x500x500)-in-in |
|
Basis:1
no. |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Filling Sand |
8.580 |
cft |
8.50 |
72.93 |
|
Brick |
27.000 |
no. |
3.80 |
102.60 |
|
Sand - Local - Mymensingh |
5.400 |
cft |
13.00 |
70.20 |
|
Cement |
3.000 |
bag |
343.00 |
1029.00 |
|
Stone-chips |
10.500 |
cft |
80.00 |
840.00 |
|
Re-bar - G40 |
40.000 |
kg |
38.50 |
1540.00 |
|
|
Sub-Total(A1) |
3654.73
|
3654.73
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mixer m/c and vibrator |
9.820 |
cft |
2.00 |
19.64 |
|
|
Sub-Total(E1) |
19.64
|
19.64
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Re-bar Work |
33.000 |
kg |
1.65 |
54.45 |
|
|
Sub-Total(L0) |
54.45
|
54.45
|
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Earth Work in Excavation |
13.000 |
cft |
1.80 |
23.40 |
|
Filling |
13.000 |
cft |
1.00 |
13.00 |
|
Plaster Work |
26.910 |
sft |
3.00 |
80.73 |
|
RCC Work |
11.410 |
cft |
6.00 |
68.46 |
|
Form work |
35.000 |
sft |
8.00 |
280.00 |
|
|
Sub-Total(L1) |
465.59
|
465.59
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Wood shutter-3time |
1.000 |
cft |
350.00 |
350.00 |
|
|
Sub-Total(M1) |
350.00
|
350.00
|
|
|
|
Total(1) |
|
4544.41 |
|
Add over head on Total(1)
|
3.0 % |
136.33 |
|
|
|
Total(2) |
|
4680.74 |
|
Add Profit on Total(2) |
8.0 % |
374.46
|
|
|
|
Total(3) |
|
5055.20 |
|
Add VAT on Unit Price |
4.5 % |
238.20 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
5293.40
|
|
|
|
Say |
|
Item: 06E (A08YC) Lintel Sunshade (1:2:4) |
|
Basis:100
cft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
22.500 |
cft |
13.00 |
292.50 |
|
Cement |
18.000 |
bag |
343.00 |
6174.00 |
|
Sand - Sylhet |
22.500 |
cft |
24.00 |
540.00 |
|
Stone-chips |
90.000 |
cft |
80.00 |
7200.00 |
|
|
Sub-Total(A1) |
14206.50
|
5017.03
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mixer m/c and vibrator |
100.000 |
cft |
2.00 |
200.00 |
|
|
Sub-Total(E1) |
200.00
|
70.63
|
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
RCC Work |
100.000 |
cft |
6.00 |
600.00 |
|
Form work |
490.190 |
sft |
8.00 |
3921.52 |
|
|
Sub-Total(L1) |
4521.52
|
1596.77
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Scaffolding |
1.000 |
set |
100.00 |
100.00 |
|
|
Sub-Total(M1) |
100.00
|
35.32
|
|
|
|
Total(1) |
|
6719.75 |
|
Add over head on Total(1)
|
3.0 % |
201.59 |
|
|
|
Total(2) |
|
6921.34 |
|
Add Profit on Total(2) |
8.0 % |
553.71
|
|
|
|
Total(3) |
|
7475.04 |
|
Add VAT on Unit Price |
4.5 % |
352.23 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
7827.27
|
|
|
|
Say |
|
Item: 06D (A08Z0) Parapet (1:1.5:3) |
|
Basis:282
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
14.333 |
cft |
13.00 |
186.33 |
|
Cement |
22.000 |
bag |
343.00 |
7546.00 |
|
Sand - Sylhet |
28.667 |
cft |
24.00 |
688.01 |
|
Stone-chips |
86.000 |
cft |
80.00 |
6880.00 |
|
|
Sub-Total(A1) |
15300.34
|
584.02
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mixer m/c and vibrator |
100.000 |
cft |
2.00 |
200.00 |
|
|
Sub-Total(E1) |
200.00
|
7.63
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
RCC Casting-Superstructur |
100.000 |
sft |
10.00 |
1000.00 |
|
FormWork:24-33ft from PL |
564.000 |
sft |
10.00 |
5640.00 |
|
|
Sub-Total(L0) |
6640.00
|
253.45
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Forms |
564.000 |
sft |
5.00 |
2820.00 |
|
|
Sub-Total(M1) |
2820.00
|
107.64
|
|
|
|
Total(1) |
|
952.74 |
|
Add over head on Total(1)
|
3.0 % |
28.58 |
|
|
|
Total(2) |
|
981.32 |
|
Add Profit on Total(2) |
8.0 % |
78.51
|
|
|
|
Total(3) |
|
1059.83 |
|
Add VAT on Unit Price |
4.5 % |
49.94 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
1109.77
|
|
|
|
Say |
|
Item: 25I (A09F) Dismantling - 250mm Brick Wall |
|
Basis:1
cft |
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Dismatle - B/W |
1.000 |
cft |
3.50 |
3.50 |
|
|
Sub-Total(L1) |
3.50
|
123.60
|
|
|
|
Total(1) |
|
123.60 |
|
Add over head on Total(1)
|
3.0 % |
3.71 |
|
|
|
Total(2) |
|
127.31 |
|
Add Profit on Total(2) |
8.0 % |
10.18
|
|
|
|
Total(3) |
|
137.50 |
|
Add VAT on Unit Price |
4.5 % |
6.48 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
143.97
|
|
|
|
Say |
|
Item: 25J (A09O) P-Protection with 50 p-cast slab |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
2.443 |
cft |
13.00 |
31.76 |
|
Cement |
3.740 |
bag |
343.00 |
1282.82 |
|
Sand - Sylhet |
4.886 |
cft |
24.00 |
117.26 |
|
Stone-chips |
14.620 |
cft |
80.00 |
1169.60 |
|
Wire Mesh |
105.000 |
sft |
7.00 |
735.00 |
|
|
Sub-Total(A1) |
3336.44
|
359.13
|
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Pre-cast block fitting |
45.860 |
no |
25.00 |
1146.50 |
|
|
Sub-Total(L1) |
1146.50
|
123.41
|
|
|
|
Total(1) |
|
482.54 |
|
Add over head on Total(1)
|
3.0 % |
14.48 |
|
|
|
Total(2) |
|
497.02 |
|
Add Profit on Total(2) |
8.0 % |
39.76
|
|
|
|
Total(3) |
|
536.78 |
|
Add VAT on Unit Price |
4.5 % |
25.29 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
562.08
|
|
|
|
Say |
|
Item: 07 (A10A) Re-bar Grade 60 |
|
Basis:1000
kg. |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
GI Wire |
10.000 |
kg |
90.00 |
900.00 |
|
Re-bar G60 |
1050.000 |
kg |
40.20 |
42210.00 |
|
|
Sub-Total(A1) |
43110.00
|
123.41
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Re-bar Work |
1000.000 |
kg |
1.65 |
1650.00 |
|
Local carrying Rod |
0.000 |
kg |
0.25 |
0.00 |
|
|
Sub-Total(L0) |
1650.00
|
123.41
|
|
|
|
Total(1) |
|
246.82 |
|
Add over head on Total(1)
|
3.0 % |
7.40 |
|
|
|
Total(2) |
|
254.22 |
|
Add Profit on Total(2) |
8.0 % |
20.34
|
|
|
|
Total(3) |
|
274.56 |
|
Add VAT on Unit Price |
4.5 % |
12.94 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
287.50
|
|
|
|
Say |
|
Item: 01C (A10B) Re-bar (G60)-Precast Pile 400x400 |
|
Basis:1000
kg. |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
GI Wire |
8.500 |
kg |
90.00 |
765.00 |
|
Re-bar G60 |
1050.000 |
kg |
40.20 |
42210.00 |
|
|
Sub-Total(A1) |
42975.00
|
123.41
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Re-bar Work |
1000.000 |
kg |
1.65 |
1650.00 |
|
Rebar Carrying |
1000.000 |
kg |
0.35 |
350.00 |
|
|
Sub-Total(L0) |
2000.00
|
123.41
|
|
|
|
Total(1) |
|
246.82 |
|
Add over head on Total(1)
|
3.0 % |
7.40 |
|
|
|
Total(2) |
|
254.22 |
|
Add Profit on Total(2) |
8.0 % |
20.34
|
|
|
|
Total(3) |
|
274.56 |
|
Add VAT on Unit Price |
4.5 % |
12.94 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
287.50
|
|
|
|
Say |
|
Item: 21 (A11H) Aluminium Louver |
|
Basis:1
sft |
S2.Alum,SS/MS,FalseCeil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Aluminium Louver |
1.000 |
sft |
310.00 |
310.00 |
|
|
Sub-Total(S2) |
310.00
|
3336.84
|
|
|
|
Total(1) |
|
3336.84 |
|
Add over head on Total(1)
|
3.0 % |
100.11 |
|
|
|
Total(2) |
|
3436.95 |
|
Add Profit on Total(2) |
8.0 % |
274.96
|
|
|
|
Total(3) |
|
3711.90 |
|
Add VAT on Unit Price |
4.5 % |
174.91 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
3886.81
|
|
|
|
Say |
|
Item: 25L (A11H2) Flyproof Net |
|
Basis:1
sft |
S2.Alum,SS/MS,FalseCeil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Fly Proof Net |
1.000 |
sft |
25.00 |
25.00 |
|
|
Sub-Total(S2) |
25.00
|
269.10
|
|
|
|
Total(1) |
|
269.10 |
|
Add over head on Total(1)
|
3.0 % |
8.07 |
|
|
|
Total(2) |
|
277.17 |
|
Add Profit on Total(2) |
8.0 % |
22.17
|
|
|
|
Total(3) |
|
299.35 |
|
Add VAT on Unit Price |
4.5 % |
14.11 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
313.45
|
|
|
|
Say |
|
Item: 12 (A12A) Plaster(1:5) 20mm thick |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
8.250 |
cft |
13.00 |
107.25 |
|
Cement |
1.100 |
bag |
343.00 |
377.30 |
|
|
Sub-Total(A1) |
484.55
|
52.16
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
OutPlaster 30.5ft |
100.000 |
sft |
4.50 |
450.00 |
|
|
Sub-Total(L0) |
450.00
|
48.44
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Scaffolding |
1.500 |
set |
100.00 |
150.00 |
|
|
Sub-Total(M1) |
150.00
|
16.15
|
|
|
|
Total(1) |
|
116.74 |
|
Add over head on Total(1)
|
3.0 % |
3.50 |
|
|
|
Total(2) |
|
120.24 |
|
Add Profit on Total(2) |
8.0 % |
9.62
|
|
|
|
Total(3) |
|
129.86 |
|
Add VAT on Unit Price |
4.5 % |
6.12 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
135.98
|
|
|
|
Say |
|
Item: 13 (A12E) 8mm thick plaster(1:4) |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand - Local - Mymensingh |
5.000 |
cft |
13.00 |
65.00 |
|
Cement |
1.000 |
bag |
343.00 |
343.00 |
|
|
Sub-Total(A1) |
408.00
|
43.92
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
InPlaster 44.5ft |
100.000 |
sft |
4.00 |
400.00 |
|
|
Sub-Total(L0) |
400.00
|
43.06
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Scaffolding |
0.600 |
set |
100.00 |
60.00 |
|
|
Sub-Total(M1) |
60.00
|
6.46
|
|
|
|
Total(1) |
|
93.43 |
|
Add over head on Total(1)
|
3.0 % |
2.80 |
|
|
|
Total(2) |
|
96.23 |
|
Add Profit on Total(2) |
8.0 % |
7.70
|
|
|
|
Total(3) |
|
103.93 |
|
Add VAT on Unit Price |
4.5 % |
4.90 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
108.83
|
|
|
|
Say |
|
Item: 11 (A12I1) NCF |
|
Basis:100
sft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Cement |
0.500 |
bag |
343.00 |
171.50 |
|
|
Sub-Total(A1) |
171.50
|
18.46
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Head Mason Supply |
0.500 |
nos. |
200.00 |
100.00 |
|
|
Sub-Total(L0) |
100.00
|
10.76
|
|
|
|
Total(1) |
|
29.22 |
|
Add over head on Total(1)
|
3.0 % |
0.88 |
|
|
|
Total(2) |
|
30.10 |
|
Add Profit on Total(2) |
8.0 % |
2.41
|
|
|
|
Total(3) |
|
32.51 |
|
Add VAT on Unit Price |
4.5 % |
1.53 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
34.04
|
|
|
|
Say |
|
Item: 14 (A13F) Weather coat paint |
|
Basis:100
sft |
A3.Material-Paint |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Plastron Sealer |
0.500 |
Ltr |
160.00 |
80.00 |
|
Enamel paint |
0.250 |
Ltr |
170.00 |
42.50 |
|
Snowcel |
2.500 |
kg |
7.60 |
19.00 |
|
Thinner-T6/T7 |
0.500 |
Ltr |
46.00 |
23.00 |
|
Weather Coat (ColorBank) |
1.420 |
Ltr |
227.85 |
323.55 |
|
|
Sub-Total(A3) |
488.05
|
52.53
|
L6.Labour Paints |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Weather coat painting |
100.000 |
sft |
4.00 |
400.00 |
|
|
Sub-Total(L6) |
400.00
|
43.06
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Scaffolding |
1.000 |
set |
100.00 |
100.00 |
|
|
Sub-Total(M1) |
100.00
|
10.76
|
|
|
|
Total(1) |
|
106.35 |
|
Add over head on Total(1)
|
3.0 % |
3.19 |
|
|
|
Total(2) |
|
109.54 |
|
Add Profit on Total(2) |
8.0 % |
8.76
|
|
|
|
Total(3) |
|
118.31 |
|
Add VAT on Unit Price |
4.5 % |
5.57 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
123.88
|
|
|
|
Say |
|
Item: 15 (A13G) Epoxy paint to wall (New) |
|
Basis:100
sft |
A3.Material-Paint |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Epoxy Primer |
2.000 |
Ltr |
170.00 |
340.00 |
|
Epoxy Enamel |
3.080 |
Ltr |
387.00 |
1191.96 |
|
Thinner-T6/T7 |
1.600 |
Ltr |
46.00 |
73.60 |
|
Chalk powder |
1.330 |
kg |
18.00 |
23.94 |
|
Mosaic stone |
0.200 |
no |
110.00 |
22.00 |
|
Scrap |
1.000 |
L.s |
30.00 |
30.00 |
|
|
Sub-Total(A3) |
1681.50
|
181.00
|
L6.Labour Paints |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Epoxy Paint to wall |
100.000 |
sft |
10.00 |
1000.00 |
|
|
Sub-Total(L6) |
1000.00
|
107.64
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Scaffolding |
1.000 |
set |
100.00 |
100.00 |
|
|
Sub-Total(M1) |
100.00
|
10.76
|
|
|
|
Total(1) |
|
299.40 |
|
Add over head on Total(1)
|
3.0 % |
8.98 |
|
|
|
Total(2) |
|
308.38 |
|
Add Profit on Total(2) |
8.0 % |
24.67
|
|
|
|
Total(3) |
|
333.05 |
|
Add VAT on Unit Price |
4.5 % |
15.69 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
348.75
|
|
|
|
Say |
|
Item: 01B (A15) Pre-cast Pile Driving (400x400) |
|
Basis:60
rft |
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Pile driving equipment |
1.000 |
set |
2000.00 |
2000.00 |
|
Fuel (diesel for piling) |
19.500 |
Ltr |
33.00 |
643.50 |
|
Lubricant |
3.900 |
Ltr |
115.00 |
448.50 |
|
Crane |
59.642 |
rft |
31.00 |
1848.90 |
|
Trailer |
59.642 |
rft |
21.00 |
1252.48 |
|
|
Sub-Total(E1) |
6193.38
|
10.76
|
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Pile shifting, driving |
59.642 |
rft |
143.00 |
8528.81 |
|
|
Sub-Total(L1) |
8528.81
|
10.76
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Hardware materials |
1.000 |
LS |
140.00 |
140.00 |
|
|
Sub-Total(M1) |
140.00
|
10.76
|
|
|
|
Total(1) |
|
32.29 |
|
Add over head on Total(1)
|
3.0 % |
0.97 |
|
|
|
Total(2) |
|
33.26 |
|
Add Profit on Total(2) |
8.0 % |
2.66
|
|
|
|
Total(3) |
|
35.92 |
|
Add VAT on Unit Price |
4.5 % |
1.69 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
37.61
|
|
|
|
Say |
|
Item: 01D (A18L) Pile head breaking |
|
Basis:10
cft |
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Dismantling RCC Pile head |
1.000 |
cft |
30.00 |
30.00 |
|
|
Sub-Total(L1) |
30.00
|
104.17
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Stone Cutting Disc - 175 |
1.000 |
no |
70.00 |
70.00 |
|
Diamond Cuting Disc- 175 |
0.100 |
no |
2200.00 |
220.00 |
|
Cheisel - Hammer |
1.000 |
no |
55.00 |
55.00 |
|
|
Sub-Total(M1) |
345.00
|
1198.00
|
|
|
|
Total(1) |
|
1302.18 |
|
Add over head on Total(1)
|
3.0 % |
39.07 |
|
|
|
Total(2) |
|
1341.24 |
|
Add Profit on Total(2) |
8.0 % |
107.30
|
|
|
|
Total(3) |
|
1448.54 |
|
Add VAT on Unit Price |
4.5 % |
68.26 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
1516.80
|
|
|
|
Say |
|
Item: 25F (A22A) Ins. pit A type 500x500-in-in |
|
Basis:1
no. |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Brick |
21.000 |
no. |
3.80 |
79.80 |
|
Sand - Local - Mymensingh |
2.520 |
cft |
13.00 |
32.76 |
|
Polythene |
0.120 |
kg |
77.00 |
9.24 |
|
Cement |
3.160 |
bag |
343.00 |
1083.88 |
|
Sand - Sylhet |
4.000 |
cft |
24.00 |
96.00 |
|
Stone-chips |
11.930 |
cft |
80.00 |
954.40 |
|
Re-bar - G40 |
31.940 |
kg |
38.50 |
1229.69 |
|
GI Wire |
0.220 |
kg |
90.00 |
19.80 |
|
|
Sub-Total(A1) |
3505.57
|
3505.57
|
B1.Plumbing/Sanitr Pipe |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
CI Cover 300 mm dia |
1.000 |
no. |
750.00 |
750.00 |
|
|
Sub-Total(B1) |
750.00
|
750.00
|
C1.Steel Structures |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Galvanized Angle 38x38 |
1.720 |
rft |
125.00 |
215.00 |
|
MS Grating 200x75 |
1.000 |
no. |
100.00 |
100.00 |
|
|
Sub-Total(C1) |
315.00
|
315.00
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Re-bar Work |
30.420 |
kg |
1.65 |
50.19 |
|
Formwork upto 10ft from P |
35.830 |
sft |
8.00 |
286.64 |
|
Dismentling F/W/Mar tile |
10.760 |
sft |
10.00 |
107.60 |
|
Neat Cement Finishing |
10.760 |
sft |
1.00 |
10.76 |
|
RCC Casting. |
13.660 |
cft |
8.00 |
109.28 |
|
|
Sub-Total(L0) |
564.47
|
564.47
|
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Earth Work in Excavation |
55.440 |
cft |
1.80 |
99.79 |
|
Filling |
28.300 |
cft |
1.00 |
28.30 |
|
Brck flat soling |
6.880 |
sft |
0.60 |
4.13 |
|
Patent stone with NCF |
2.690 |
sft |
3.00 |
8.07 |
|
|
Sub-Total(L1) |
140.29
|
140.29
|
L4.Labour-Sanitary |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Manhole Cover fixing |
1.000 |
no. |
300.00 |
300.00 |
|
|
Sub-Total(L4) |
300.00
|
300.00
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Forms |
35.830 |
sft |
5.00 |
179.15 |
|
|
Sub-Total(M1) |
179.15
|
179.15
|
|
|
|
Total(1) |
|
5754.48 |
|
Add over head on Total(1)
|
3.0 % |
172.63 |
|
|
|
Total(2) |
|
5927.12 |
|
Add Profit on Total(2) |
8.0 % |
474.17
|
|
|
|
Total(3) |
|
6401.29 |
|
Add VAT on Unit Price |
4.5 % |
301.63 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
6702.92
|
|
|
|
Say |
|
Item: 25G (A22B) Ins. pit B type 750x750-in-in |
|
Basis:1
no. |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Brick |
32.000 |
no. |
3.80 |
121.60 |
|
Sand - Local - Mymensingh |
3.780 |
cft |
13.00 |
49.14 |
|
Polythene |
0.180 |
kg |
77.00 |
13.86 |
|
Cement |
4.740 |
bag |
343.00 |
1625.82 |
|
Sand - Sylhet |
6.000 |
cft |
24.00 |
144.00 |
|
Stone-chips |
17.900 |
cft |
80.00 |
1432.00 |
|
Re-bar - G40 |
48.300 |
kg |
38.50 |
1859.55 |
|
GI Wire |
0.330 |
kg |
90.00 |
29.70 |
|
|
Sub-Total(A1) |
5275.67
|
5275.67
|
B1.Plumbing/Sanitr Pipe |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
CI Cover 300 mm dia |
1.000 |
no. |
750.00 |
750.00 |
|
|
Sub-Total(B1) |
750.00
|
750.00
|
C1.Steel Structures |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Galvanized Angle 38x38 |
2.580 |
rft |
125.00 |
322.50 |
|
MS Grating 200x75 |
1.000 |
no. |
100.00 |
100.00 |
|
|
Sub-Total(C1) |
422.50
|
422.50
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Mixer m/c and vibrator |
20.490 |
cft |
2.00 |
40.98 |
|
|
Sub-Total(E1) |
40.98
|
40.98
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Re-bar Work |
46.000 |
kg |
1.65 |
75.90 |
|
Formwork upto 10ft from P |
53.740 |
sft |
8.00 |
429.92 |
|
Dismentling F/W/Mar tile |
16.140 |
sft |
10.00 |
161.40 |
|
Neat Cement Finishing |
16.140 |
sft |
1.00 |
16.14 |
|
RCC Casting. |
20.490 |
cft |
8.00 |
163.92 |
|
|
Sub-Total(L0) |
847.28
|
847.28
|
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Earth Work in Excavation |
83.160 |
cft |
1.80 |
149.69 |
|
Filling |
42.450 |
cft |
1.00 |
42.45 |
|
Brck flat soling |
11.860 |
sft |
0.60 |
7.12 |
|
Patent stone with NCF |
4.035 |
sft |
3.00 |
12.11 |
|
|
Sub-Total(L1) |
211.36
|
211.36
|
L4.Labour-Sanitary |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Manhole Cover fixing |
1.000 |
no. |
300.00 |
300.00 |
|
|
Sub-Total(L4) |
300.00
|
300.00
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Forms |
53.740 |
sft |
5.00 |
268.70 |
|
|
Sub-Total(M1) |
268.70
|
268.70
|
|
|
|
Total(1) |
|
8116.49 |
|
Add over head on Total(1)
|
3.0 % |
243.49 |
|
|
|
Total(2) |
|
8359.98 |
|
Add Profit on Total(2) |
8.0 % |
668.80
|
|
|
|
Total(3) |
|
9028.78 |
|
Add VAT on Unit Price |
4.5 % |
425.44 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
9454.22
|
|
|
|
Say |
|
Item: 25H (A22C) Ins. pit C type 1000x1000-in-in |
|
Basis:1
no. |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Brick |
55.000 |
no. |
3.80 |
209.00 |
|
Sand - Local - Mymensingh |
5.040 |
cft |
13.00 |
65.52 |
|
Polythene |
0.240 |
kg |
77.00 |
18.48 |
|
Cement |
6.320 |
bag |
343.00 |
2167.76 |
|
Sand - Sylhet |
8.000 |
cft |
24.00 |
192.00 |
|
Stone-chips |
23.860 |
cft |
80.00 |
1908.80 |
|
GI Wire |
0.440 |
kg |
90.00 |
39.60 |
|
Re-bar G60 |
63.880 |
kg |
40.20 |
2567.98 |
|
|
Sub-Total(A1) |
7169.14
|
7169.14
|
B1.Plumbing/Sanitr Pipe |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
CI Cover 300 mm dia |
1.000 |
no. |
750.00 |
750.00 |
|
|
Sub-Total(B1) |
750.00
|
750.00
|
C1.Steel Structures |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Galvanized Angle 38x38 |
1.720 |
rft |
125.00 |
215.00 |
|
MS Grating 200x75 |
1.000 |
no. |
100.00 |
100.00 |
|
|
Sub-Total(C1) |
315.00
|
315.00
|
L0.Labour - Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Re-bar Work |
60.840 |
kg |
1.65 |
100.39 |
|
Formwork upto 10ft from P |
71.660 |
sft |
8.00 |
573.28 |
|
Dismentling F/W/Mar tile |
21.520 |
sft |
10.00 |
215.20 |
|
Neat Cement Finishing |
21.520 |
sft |
1.00 |
21.52 |
|
RCC Casting. |
27.320 |
cft |
8.00 |
218.56 |
|
|
Sub-Total(L0) |
1128.95
|
1128.95
|
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Earth Work in Excavation |
110.880 |
cft |
1.80 |
199.58 |
|
Filling |
56.600 |
cft |
1.00 |
56.60 |
|
Brck flat soling |
18.190 |
sft |
0.60 |
10.91 |
|
Patent stone with NCF |
5.380 |
sft |
3.00 |
16.14 |
|
|
Sub-Total(L1) |
283.24
|
283.24
|
L4.Labour-Sanitary |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Manhole Cover fixing |
1.000 |
no. |
300.00 |
300.00 |
|
|
Sub-Total(L4) |
300.00
|
300.00
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Steel Forms |
71.660 |
sft |
5.00 |
358.30 |
|
|
Sub-Total(M1) |
358.30
|
358.30
|
|
|
|
Total(1) |
|
10304.62 |
|
Add over head on Total(1)
|
3.0 % |
309.14 |
|
|
|
Total(2) |
|
10613.76 |
|
Add Profit on Total(2) |
8.0 % |
849.10
|
|
|
|
Total(3) |
|
11462.86 |
|
Add VAT on Unit Price |
4.5 % |
540.13 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
12002.99
|
|
|
|
Say |
|
Item: 20 (B01A) uPVC Pipe - 150mm dia |
|
Basis:319
rft |
B1.Plumbing/Sanitr Pipe |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
uPVC Pipe 150 dia |
328.280 |
rft |
115.00 |
37752.20 |
|
uPVC Bend 150mm dia |
3.000 |
no. |
560.00 |
1680.00 |
|
uPVC Tee - 150mm dia |
21.000 |
no |
950.00 |
19950.00 |
|
uPVC End Cap -150 dia |
2.000 |
no |
920.00 |
1840.00 |
|
Clamp |
73.000 |
no |
35.00 |
2555.00 |
|
Standing Urinal |
1.000 |
no |
150.00 |
150.00 |
|
Hole making (150 dia) |
21.000 |
no |
350.00 |
7350.00 |
|
S-cement tube |
5.000 |
no |
190.00 |
950.00 |
|
Solvent cement -500 ml |
2.000 |
pot |
490.00 |
980.00 |
|
|
Sub-Total(B1) |
73207.20
|
358.30
|
L4.Labour-Sanitary |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
uPVC Pipe Fitting -150mm |
318.720 |
rft |
20.00 |
6374.40 |
|
|
Sub-Total(L4) |
6374.40
|
358.30
|
|
|
|
Total(1) |
|
716.60 |
|
Add over head on Total(1)
|
3.0 % |
21.50 |
|
|
|
Total(2) |
|
738.10 |
|
Add Profit on Total(2) |
8.0 % |
59.05
|
|
|
|
Total(3) |
|
797.15 |
|
Add VAT on Unit Price |
4.5 % |
37.56 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
834.71
|
|
|
|
Say |
|
Item: 18 (C01A) MS Angle Truss |
|
Basis:1000
kg. |
C1.Steel Structures |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
MS angle |
1050.000 |
kg |
38.00 |
39900.00 |
|
|
Sub-Total(C1) |
39900.00
|
358.30
|
L5.Labour-MS Work |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Truss making |
1000.000 |
kg |
8.00 |
8000.00 |
|
|
Sub-Total(L5) |
8000.00
|
358.30
|
M1.Misc.-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Welding Electrode VM 8-no |
2.000 |
pack |
520.00 |
1040.00 |
|
|
Sub-Total(M1) |
1040.00
|
358.30
|
|
|
|
Total(1) |
|
1074.90 |
|
Add over head on Total(1)
|
3.0 % |
32.25 |
|
|
|
Total(2) |
|
1107.15 |
|
Add Profit on Total(2) |
8.0 % |
88.57
|
|
|
|
Total(3) |
|
1195.72 |
|
Add VAT on Unit Price |
4.5 % |
56.34 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
1252.06
|
|
|
|
Say |
|
Item: 25B (C09) Fibre glass sheet |
|
Basis:100
sft |
C1.Steel Structures |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
MS angle |
53.000 |
kg |
38.00 |
2014.00 |
|
Fibre glass sheet |
147.330 |
sft |
65.00 |
9576.45 |
|
J-Hook |
60.000 |
no |
2.50 |
150.00 |
|
|
Sub-Total(C1) |
11740.45
|
1263.74
|
E1.Equipment-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Welding M/c |
50.480 |
kg |
0.50 |
25.24 |
|
|
Sub-Total(E1) |
25.24
|
2.72
|
L5.Labour-MS Work |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Making Purlin,rafter, box |
50.480 |
kg |
6.50 |
328.12 |
|
Fibre glass roofing |
100.000 |
sft |
6.00 |
600.00 |
|
|
Sub-Total(L5) |
928.12
|
99.90
|
S1.Sub-contractor-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Painting to MS angle |
27.650 |
sft |
6.00 |
165.90 |
|
|
Sub-Total(S1) |
165.90
|
17.86
|
|
|
|
Total(1) |
|
1384.22 |
|
Add over head on Total(1)
|
3.0 % |
41.53 |
|
|
|
Total(2) |
|
1425.75 |
|
Add Profit on Total(2) |
8.0 % |
114.06
|
|
|
|
Total(3) |
|
1539.81 |
|
Add VAT on Unit Price |
4.5 % |
72.56 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
1612.36
|
|
|
|
Say |
|
Item: 10 (C17) Mtorized Roling Shutter |
|
Basis:1
sft |
S3.Subcontractor-Misc |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Motorized Rolling Shutter |
1.000 |
sft |
600.00 |
600.00 |
|
|
Sub-Total(S3) |
600.00
|
6458.40
|
|
|
|
Total(1) |
|
6458.40 |
|
Add over head on Total(1)
|
3.0 % |
193.75 |
|
|
|
Total(2) |
|
6652.15 |
|
Add Profit on Total(2) |
8.0 % |
532.17
|
|
|
|
Total(3) |
|
7184.32 |
|
Add VAT on Unit Price |
4.5 % |
338.53 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
7522.85
|
|
|
|
Say |
|
Item: 16 (C25) Zink Alum Color Bond Roofing |
|
Basis:1
sft |
C2.MS/SS Work i/c matr |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Zink Alum.Color Bond Roof |
1.000 |
sft |
45.00 |
45.00 |
|
|
Sub-Total(C2) |
45.00
|
484.38
|
|
|
|
Total(1) |
|
484.38 |
|
Add over head on Total(1)
|
3.0 % |
14.53 |
|
|
|
Total(2) |
|
498.91 |
|
Add Profit on Total(2) |
8.0 % |
39.91
|
|
|
|
Total(3) |
|
538.82 |
|
Add VAT on Unit Price |
4.5 % |
25.39 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
564.21
|
|
|
|
Say |
|
Item: 17 (C25A) Zink Alum Color Ridge |
|
Basis:1
rft |
C2.MS/SS Work i/c matr |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Zink Alum.Color BondRidge |
1.000 |
rft |
100.00 |
100.00 |
|
|
Sub-Total(C2) |
100.00
|
484.38
|
|
|
|
Total(1) |
|
484.38 |
|
Add over head on Total(1)
|
3.0 % |
14.53 |
|
|
|
Total(2) |
|
498.91 |
|
Add Profit on Total(2) |
8.0 % |
39.91
|
|
|
|
Total(3) |
|
538.82 |
|
Add VAT on Unit Price |
4.5 % |
25.39 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
564.21
|
|
|
|
Say |
|
Item: 25C (F000) 150mm RCC Pipe |
|
Basis:1
rft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Brick |
3.000 |
no. |
3.80 |
11.40 |
|
Sand - Local - Mymensingh |
0.540 |
cft |
13.00 |
7.02 |
|
Cement |
0.216 |
bag |
343.00 |
74.09 |
|
Brick-chips |
1.080 |
cft |
40.00 |
43.20 |
|
|
Sub-Total(A1) |
135.71
|
484.38
|
B1.Plumbing/Sanitr Pipe |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
RCC Pipe 6" dia |
1.050 |
rft |
66.00 |
69.30 |
|
150mm dia Socket |
0.250 |
no. |
50.00 |
12.50 |
|
|
Sub-Total(B1) |
81.80
|
484.38
|
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Earth Work in Excavation |
2.640 |
cft |
1.80 |
4.75 |
|
Brck flat soling |
1.000 |
sft |
0.60 |
0.60 |
|
CC Work |
1.200 |
cft |
5.00 |
6.00 |
|
150mm dia RCC Pipe |
1.000 |
rft |
20.00 |
20.00 |
|
|
Sub-Total(L1) |
31.35
|
484.38
|
|
|
|
Total(1) |
|
1453.14 |
|
Add over head on Total(1)
|
3.0 % |
43.59 |
|
|
|
Total(2) |
|
1496.73 |
|
Add Profit on Total(2) |
8.0 % |
119.74
|
|
|
|
Total(3) |
|
1616.47 |
|
Add VAT on Unit Price |
4.5 % |
76.17 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
1692.64
|
|
|
|
Say |
|
Item: 25D (F001) 225 mm dia Rcc pipe(Capital) |
|
Basis:1
rft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Brick |
3.000 |
no. |
3.80 |
11.40 |
|
Sand - Local - Mymensingh |
0.040 |
cft |
13.00 |
0.52 |
|
Cement |
0.030 |
bag |
343.00 |
10.29 |
|
Brick-chips |
0.080 |
cft |
40.00 |
3.20 |
|
|
Sub-Total(A1) |
25.41
|
484.38
|
B1.Plumbing/Sanitr Pipe |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
RCC Pipe 9" dia |
1.050 |
rft |
108.00 |
113.40 |
|
|
Sub-Total(B1) |
113.40
|
484.38
|
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Earth Work in Excavation |
2.650 |
cft |
1.80 |
4.77 |
|
Brck flat soling |
1.000 |
sft |
0.60 |
0.60 |
|
CC Work |
0.135 |
cft |
5.00 |
0.68 |
|
225mm dia RCC pipe |
1.000 |
rft |
25.00 |
25.00 |
|
|
Sub-Total(L1) |
31.05
|
484.38
|
|
|
|
Total(1) |
|
1453.14 |
|
Add over head on Total(1)
|
3.0 % |
43.59 |
|
|
|
Total(2) |
|
1496.73 |
|
Add Profit on Total(2) |
8.0 % |
119.74
|
|
|
|
Total(3) |
|
1616.47 |
|
Add VAT on Unit Price |
4.5 % |
76.17 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
1692.64
|
|
|
|
Say |
|
Item: 25E (F002) 300 mm dia Rcc pipe (Capital) |
|
Basis:1
rft |
A1.Materials-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Brick |
4.000 |
no. |
3.80 |
15.20 |
|
Sand - Local - Mymensingh |
0.050 |
cft |
13.00 |
0.65 |
|
Cement |
0.030 |
bag |
343.00 |
10.29 |
|
Brick-chips |
0.120 |
cft |
40.00 |
4.80 |
|
|
Sub-Total(A1) |
30.94
|
484.38
|
B1.Plumbing/Sanitr Pipe |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
RCC Pipe 12" dia |
1.050 |
rft |
210.00 |
220.50 |
|
|
Sub-Total(B1) |
220.50
|
484.38
|
L1.Labour-Civil |
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Earth Work in Excavation |
3.530 |
cft |
1.80 |
6.35 |
|
Brck flat soling |
1.330 |
sft |
0.60 |
0.80 |
|
CC Work |
0.200 |
cft |
5.00 |
1.00 |
|
300mm dia RCC pipe |
1.000 |
rft |
33.00 |
33.00 |
|
|
Sub-Total(L1) |
41.15
|
484.38
|
|
|
|
Total(1) |
|
1453.14 |
|
Add over head on Total(1)
|
3.0 % |
43.59 |
|
|
|
Total(2) |
|
1496.73 |
|
Add Profit on Total(2) |
8.0 % |
119.74
|
|
|
|
Total(3) |
|
1616.47 |
|
Add VAT on Unit Price |
4.5 % |
76.17 |
Add Income Tax on Unit Price
|
0.0 % |
0.00 |
|
|
|
Unit Price |
|
1692.64
|
|
|
|
Say |
|