Return Main Menu

Project Sheet roofing of Gas Meter room
Item: 01 (C09) Fibre glass sheet
Basis:100 sft
C1.Steel Structures
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS angle
53.000
kg
38.00
2014.00
Fibre glass sheet
147.330
sft
65.00
9576.45
J-Hook
60.000
no
2.50
150.00
Sub-Total(C1)
11740.45
1263.74
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Welding M/c
50.480
kg
0.50
25.24
Sub-Total(E1)
25.24
2.72
L5.Labour-MS Work
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Making Purlin,rafter, box
50.480
kg
6.50
328.12
Fibre glass roofing
100.000
sft
6.00
600.00
Sub-Total(L5)
928.12
99.90
S1.Sub-contractor-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Painting to MS angle
27.650
sft
6.00
165.90
Sub-Total(S1)
165.90
17.86
Total(1)
1384.22
Add over head on Total(1)
2.5 %
34.61
Total(2)
1418.82
Add Profit on Total(2)
8.0 %
113.51
Total(3)
1532.33
Add VAT on Unit Price
4.5 %
72.20
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
1604.53
Say
1605
per M2
Item: 02 (C10) (50x50x5mm) angle box
Basis:1 rft
C1.Steel Structures
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS angle
2.520
kg
38.00
95.76
Sub-Total(C1)
95.76
17.86
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Welding M/c
2.400
kg
0.50
1.20
Sub-Total(E1)
1.20
17.86
L5.Labour-MS Work
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Making Purlin,rafter, box
2.400
kg
6.50
15.60
Sub-Total(L5)
15.60
17.86
S1.Sub-contractor-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Painting to MS angle
0.600
sft
6.00
3.60
Sub-Total(S1)
3.60
17.86
Total(1)
71.43
Add over head on Total(1)
2.5 %
1.79
Total(2)
73.22
Add Profit on Total(2)
8.0 %
5.86
Total(3)
79.07
Add VAT on Unit Price
4.5 %
3.73
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
82.80
Say
83
per RM
Item: 03 (C11) (50x50x5mm) angle box vertical
Basis:1 no.
C1.Steel Structures
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS angle
2.165
kg
38.00
82.27
M.S pipe 2" dia
0.500
rft
65.00
32.50
10 dia Nut - bolt
9.500
no
8.00
76.00
Sub-Total(C1)
190.77
190.77
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Welding M/c
1.970
kg
0.50
0.99
Sub-Total(E1)
0.99
0.99
L5.Labour-MS Work
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Making Purlin,rafter, box
1.970
kg
6.50
12.81
Box fixing with hole cutt
1.000
no
75.00
75.00
Sub-Total(L5)
87.81
87.81
S1.Sub-contractor-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Painting to MS angle
0.500
sft
6.00
3.00
Painting to MS Pipe
0.260
sft
6.00
1.56
Sub-Total(S1)
4.56
4.56
Total(1)
284.12
Add over head on Total(1)
2.5 %
7.10
Total(2)
291.22
Add Profit on Total(2)
8.0 %
23.30
Total(3)
314.52
Add VAT on Unit Price
4.5 %
14.82
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
329.34
Say
329
per NO
Item: 04 (C12) 65mm dia M.S Pipe
Basis:14 rft
C1.Steel Structures
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
65mm dia M.S Pipe
14.814
rft
70.00
1036.98
M.S plate
8.258
kg
45.00
371.61
12mm dia Rowl bolt
8.000
no
25.00
200.00
Sub-Total(C1)
1608.59
4.56
L5.Labour-MS Work
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
65mm dia MS pipe fittings
14.108
rft
6.00
84.65
Sub-Total(L5)
84.65
4.56
S1.Sub-contractor-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Painting to MS angle
1.950
sft
6.00
11.70
Painting to MS Pipe
7.405
sft
6.00
44.43
Sub-Total(S1)
56.13
4.56
Total(1)
13.68
Add over head on Total(1)
2.5 %
0.34
Total(2)
14.02
Add Profit on Total(2)
8.0 %
1.12
Total(3)
15.14
Add VAT on Unit Price
4.5 %
0.71
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
15.86
Say
16
per RM
Item: 05 (C13) Enamel Painting to Old Fencing
Basis:100 sft
S1.Sub-contractor-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Paiting to old Fencing
100.000
sft
8.00
800.00
Sub-Total(S1)
800.00
86.11
Total(1)
86.11
Add over head on Total(1)
2.5 %
2.15
Total(2)
88.26
Add Profit on Total(2)
8.0 %
7.06
Total(3)
95.33
Add VAT on Unit Price
4.5 %
4.49
Add Income Tax on Unit Price
0.0 %
0.00
Unit Price
99.82
Say
100
per M2