Return Main Menu

Project C.C Block Covering and drain cover
Item: 02 (A01) Earth work in Excavation
Basis:1000 cft
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Earth Work in Excavation
1000.000
cft
1.80
1800.00
Sub-Total(L1)
1800.00
63.57
Total(1)
63.57
Add over head on Total(1)
2.5 %
1.59
Total(2)
65.16
Add Profit on Total(2)
8.0 %
5.21
Total(3)
70.37
Add VAT on Unit Price
4.5 %
3.46
Add Income Tax on Unit Price
4.0 %
3.08
Unit Price
76.91
Say
77
per M3
Item: 05 (A02A) Brick Flat Soling- Road
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Filling Sand
5.000
cft
8.50
42.50
Brick
300.000
no.
3.80
1140.00
Sub-Total(A1)
1182.50
127.28
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
0.100
nos.
100.00
10.00
Head Mason Supply
0.250
nos.
200.00
50.00
Sub-Total(L0)
60.00
6.46
Total(1)
133.74
Add over head on Total(1)
2.5 %
3.34
Total(2)
137.09
Add Profit on Total(2)
8.0 %
10.97
Total(3)
148.05
Add VAT on Unit Price
4.5 %
7.28
Add Income Tax on Unit Price
4.0 %
6.47
Unit Price
161.81
Say
162
per M2
Item: 06 (A02F) Single layer polythene
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Polythene
1.500
kg
77.00
115.50
Sub-Total(A1)
115.50
12.43
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
0.020
nos.
100.00
2.00
Sub-Total(L0)
2.00
0.22
Total(1)
12.65
Add over head on Total(1)
2.5 %
0.32
Total(2)
12.96
Add Profit on Total(2)
8.0 %
1.04
Total(3)
14.00
Add VAT on Unit Price
4.5 %
0.69
Add Income Tax on Unit Price
4.0 %
0.61
Unit Price
15.30
Say
15
per M2
Item: 07 (A03B) Pre-cast CC (1:1.5:3) Block-50mm
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
2.443
cft
13.00
31.76
Cement
3.740
bag
343.00
1282.82
Sand - Sylhet
4.886
cft
24.00
117.26
Stone-chips
14.620
cft
80.00
1169.60
Wire Mesh
105.000
sft
7.00
735.00
Sub-Total(A1)
3336.44
359.13
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Pre-cast block fitting
45.860
no
25.00
1146.50
Sub-Total(L1)
1146.50
123.41
Total(1)
482.54
Add over head on Total(1)
2.5 %
12.06
Total(2)
494.61
Add Profit on Total(2)
8.0 %
39.57
Total(3)
534.18
Add VAT on Unit Price
4.5 %
26.27
Add Income Tax on Unit Price
4.0 %
23.35
Unit Price
583.80
Say
584
per M2
Item: 08A (A03D) 40mm Thick Patent Stone with NCF
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
5.400
cft
13.00
70.20
Cement
2.660
bag
343.00
912.38
Brick-chips
10.800
cft
40.00
432.00
Sub-Total(A1)
1414.58
152.27
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
12.000
cft
2.00
24.00
Sub-Total(E1)
24.00
2.58
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
CC (50mm) With NCF
100.000
sft
3.00
300.00
Sub-Total(L1)
300.00
32.29
Total(1)
187.14
Add over head on Total(1)
2.5 %
4.68
Total(2)
191.82
Add Profit on Total(2)
8.0 %
15.35
Total(3)
207.16
Add VAT on Unit Price
4.5 %
10.19
Add Income Tax on Unit Price
4.0 %
9.06
Unit Price
226.41
Say
226
per M2
Item: 08B (A03E) 75 mm thick CC with NCF
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
3.750
cft
13.00
48.75
Cement
5.000
bag
343.00
1715.00
Sand - Sylhet
7.500
cft
24.00
180.00
Brick-chips
22.500
cft
40.00
900.00
Sub-Total(A1)
2843.75
306.10
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
25.000
cft
2.00
50.00
Sub-Total(E1)
50.00
5.38
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
CC Work
25.000
cft
5.00
125.00
Sub-Total(L1)
125.00
13.46
Total(1)
324.94
Add over head on Total(1)
2.5 %
8.12
Total(2)
333.06
Add Profit on Total(2)
8.0 %
26.64
Total(3)
359.71
Add VAT on Unit Price
4.5 %
17.69
Add Income Tax on Unit Price
4.0 %
15.72
Unit Price
393.12
Say
393
per M2
Item: 04 (A05) Sand Filling
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Filling Sand
130.000
cft
8.50
1105.00
Sub-Total(A1)
1105.00
390.23
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mini Roller Compaction
100.000
cft
1.00
100.00
Mini Dumper
130.000
cft
2.00
260.00
Payloader
0.000
day
8000.00
0.00
Dump Truck
0.000
day
8300.00
0.00
Sub-Total(E1)
360.00
127.13
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
0.800
nos.
100.00
80.00
Sub-Total(L0)
80.00
28.25
Total(1)
545.62
Add over head on Total(1)
2.5 %
13.64
Total(2)
559.26
Add Profit on Total(2)
8.0 %
44.74
Total(3)
604.00
Add VAT on Unit Price
4.5 %
29.70
Add Income Tax on Unit Price
4.0 %
26.40
Unit Price
660.11
Say
660
per M3
Item: 03 (A05E) Back Filling With Roller
Basis:100 cft
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Roller hire ch. i/c fuel
0.050
day
6500.00
325.00
Wheel Loader-Road
0.010
day
10000.00
100.00
Gradder-Road
0.001
day
10000.00
10.00
Sub-Total(E1)
435.00
153.62
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
1.000
nos.
100.00
100.00
Sub-Total(L0)
100.00
35.32
Total(1)
188.94
Add over head on Total(1)
2.5 %
4.72
Total(2)
193.66
Add Profit on Total(2)
8.0 %
15.49
Total(3)
209.15
Add VAT on Unit Price
4.5 %
10.29
Add Income Tax on Unit Price
4.0 %
9.14
Unit Price
228.58
Say
229
per M3
Item: 15H (A06A1) 125mm Brick Work ex Brick
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
17.000
cft
13.00
221.00
Cement
2.600
bag
343.00
891.80
Sub-Total(A1)
1112.80
119.78
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
1.000
nos.
100.00
100.00
Head Mason Supply
1.000
nos.
200.00
200.00
Sub-Total(L0)
300.00
32.29
Total(1)
152.07
Add over head on Total(1)
2.5 %
3.80
Total(2)
155.88
Add Profit on Total(2)
8.0 %
12.47
Total(3)
168.35
Add VAT on Unit Price
4.5 %
8.28
Add Income Tax on Unit Price
4.0 %
7.36
Unit Price
183.98
Say
184
per M2
Item: 09 (A08G) Rcc Slab (1:2:4) with 1.5% rod
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
15.000
cft
13.00
195.00
Cement
18.000
bag
343.00
6174.00
Sand - Sylhet
30.000
cft
24.00
720.00
Brick-chips
90.000
cft
40.00
3600.00
Re-bar - G40
350.000
kg
38.50
13475.00
Sub-Total(A1)
24164.00
8533.52
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
100.000
cft
2.00
200.00
Sub-Total(E1)
200.00
70.63
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Re-bar Work
333.000
kg
1.65
549.45
Sub-Total(L0)
549.45
194.04
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
RCC Work
100.000
cft
6.00
600.00
Form work
20.000
sft
8.00
160.00
Sub-Total(L1)
760.00
268.39
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Forms
20.000
sft
5.00
100.00
Sub-Total(M1)
100.00
35.32
Total(1)
9101.89
Add over head on Total(1)
2.5 %
227.55
Total(2)
9329.44
Add Profit on Total(2)
8.0 %
746.36
Total(3)
10075.80
Add VAT on Unit Price
4.5 %
495.53
Add Income Tax on Unit Price
4.0 %
440.47
Unit Price
11011.80
Say
11012
per M3
Item: 10 (A08H) Rcc Ins. pit (500x500x500)-in-in
Basis:1 no.
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Filling Sand
8.580
cft
8.50
72.93
Brick
27.000
no.
3.80
102.60
Sand - Local - Mymensingh
5.400
cft
13.00
70.20
Cement
3.000
bag
343.00
1029.00
Stone-chips
10.500
cft
80.00
840.00
Re-bar - G40
40.000
kg
38.50
1540.00
Sub-Total(A1)
3654.73
3654.73
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
9.820
cft
2.00
19.64
Sub-Total(E1)
19.64
19.64
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Re-bar Work
33.000
kg
1.65
54.45
Sub-Total(L0)
54.45
54.45
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Earth Work in Excavation
13.000
cft
1.80
23.40
Filling
13.000
cft
1.00
13.00
Plaster Work
26.910
sft
3.00
80.73
RCC Work
11.410
cft
6.00
68.46
Form work
35.000
sft
8.00
280.00
Sub-Total(L1)
465.59
465.59
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Wood shutter-3time
1.000
cft
350.00
350.00
Sub-Total(M1)
350.00
350.00
Total(1)
4544.41
Add over head on Total(1)
2.5 %
113.61
Total(2)
4658.02
Add Profit on Total(2)
8.0 %
372.64
Total(3)
5030.66
Add VAT on Unit Price
4.5 %
247.41
Add Income Tax on Unit Price
4.0 %
219.92
Unit Price
5497.99
Say
5498
per NO
Item: 13 (A08I) Ins. cover slab (1000x1000)
Basis:1 no.
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
1.000
cft
13.00
13.00
Cement
1.000
bag
343.00
343.00
Sand - Sylhet
1.500
cft
24.00
36.00
Stone-chips
5.000
cft
80.00
400.00
Re-bar - G40
24.740
kg
38.50
952.49
Sub-Total(A1)
1744.49
1744.49
C1.Steel Structures
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS angle
23.780
kg
38.00
903.64
Sub-Total(C1)
903.64
903.64
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Re-bar Work
23.560
kg
1.65
38.87
Sub-Total(L0)
38.87
38.87
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
RCC Work
5.570
cft
6.00
33.42
Co-Slab fixing at ins-pit
1.000
no
150.00
150.00
Sub-Total(L1)
183.42
183.42
L5.Labour-MS Work
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS angle fixing for slab
22.660
kg
10.00
226.60
Sub-Total(L5)
226.60
226.60
Total(1)
3097.02
Add over head on Total(1)
2.5 %
77.43
Total(2)
3174.45
Add Profit on Total(2)
8.0 %
253.96
Total(3)
3428.41
Add VAT on Unit Price
4.5 %
168.61
Add Income Tax on Unit Price
4.0 %
149.88
Unit Price
3746.89
Say
3747
per NO
Item: 15F (A08S1) Pre-cast RCC Kerb fitting
Basis:2 rft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
7.000
no.
3.80
26.60
Sand - Local - Mymensingh
1.000
cft
13.00
13.00
Cement
0.120
bag
343.00
41.16
Brick-chips
0.600
cft
40.00
24.00
Sub-Total(A1)
104.76
226.60
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
1.000
nos.
100.00
100.00
Head Mason Supply
0.150
nos.
200.00
30.00
Sub-Total(L0)
130.00
226.60
Total(1)
453.20
Add over head on Total(1)
2.5 %
11.33
Total(2)
464.53
Add Profit on Total(2)
8.0 %
37.16
Total(3)
501.69
Add VAT on Unit Price
4.5 %
24.67
Add Income Tax on Unit Price
4.0 %
21.93
Unit Price
548.30
Say
548
per RM
Item: 15G (A09E4) Dismatle Precast Slab and Refitti
Basis:1 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
0.020
cft
13.00
0.26
Cement
0.005
bag
343.00
1.72
Sub-Total(A1)
1.98
21.26
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
0.010
nos.
100.00
1.00
Head Mason Supply
0.020
nos.
200.00
4.00
Sub-Total(L0)
5.00
53.82
Total(1)
75.08
Add over head on Total(1)
2.5 %
1.88
Total(2)
76.96
Add Profit on Total(2)
8.0 %
6.16
Total(3)
83.11
Add VAT on Unit Price
4.5 %
4.09
Add Income Tax on Unit Price
4.0 %
3.63
Unit Price
90.83
Say
91
per M2
Item: 15A (A12B) Plaster 12mm thick (1:4)
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
7.500
cft
13.00
97.50
Cement
1.000
bag
343.00
343.00
Sub-Total(A1)
440.50
47.42
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Plaster Work
100.000
sft
3.00
300.00
Sub-Total(L1)
300.00
32.29
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Scaffolding
1.000
set
100.00
100.00
Sub-Total(M1)
100.00
10.76
Total(1)
90.47
Add over head on Total(1)
2.5 %
2.26
Total(2)
92.73
Add Profit on Total(2)
8.0 %
7.42
Total(3)
100.15
Add VAT on Unit Price
4.5 %
4.93
Add Income Tax on Unit Price
4.0 %
4.38
Unit Price
109.46
Say
109
per M2
Item: 15B (A12I) Plaster With NCF
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
7.500
cft
13.00
97.50
Cement
1.500
bag
343.00
514.50
Sub-Total(A1)
612.00
65.88
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
0.500
nos.
100.00
50.00
Head Mason Supply
1.500
nos.
200.00
300.00
Sub-Total(L0)
350.00
37.67
Total(1)
103.55
Add over head on Total(1)
2.5 %
2.59
Total(2)
106.14
Add Profit on Total(2)
8.0 %
8.49
Total(3)
114.63
Add VAT on Unit Price
4.5 %
5.64
Add Income Tax on Unit Price
4.0 %
5.01
Unit Price
125.28
Say
125
per M2
Item: 01 (A18I) Dismantling CC, BFS, HBB
Basis:100 sft
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
1.500
nos.
100.00
150.00
Sub-Total(L0)
150.00
16.15
Total(1)
16.15
Add over head on Total(1)
2.5 %
0.40
Total(2)
16.55
Add Profit on Total(2)
8.0 %
1.32
Total(3)
17.87
Add VAT on Unit Price
4.5 %
0.88
Add Income Tax on Unit Price
4.0 %
0.78
Unit Price
19.53
Say
20
per M2
Item: 14 (A19) Guard post inl. all materials
Basis:1 no.
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
240.000
no.
3.80
912.00
Sand - Local - Mymensingh
25.620
cft
13.00
333.06
Cement
17.000
bag
343.00
5831.00
Sand - Sylhet
17.500
cft
24.00
420.00
Brick-chips
60.000
cft
40.00
2400.00
Re-bar - G40
150.000
kg
38.50
5775.00
Surki
3.500
cft
35.00
122.50
Stone Lime
27.870
kg
6.50
181.16
Sub-Total(A1)
15974.72
15974.72
A2.Material-Mosaic/Tile
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
C-Tiles CT-03 (150x150)
206.000
no
12.50
2575.00
Sub-Total(A2)
2575.00
2575.00
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
59.000
cft
2.00
118.00
Sub-Total(E1)
118.00
118.00
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Re-bar Work
261.000
kg
1.65
430.65
Sub-Total(L0)
430.65
430.65
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Earth Work in Excavation
38.000
cft
1.80
68.40
Filling
32.000
cft
1.00
32.00
Brck flat soling
8.720
sft
0.60
5.23
Brick Work-125mm
16.880
sft
3.50
59.08
Plaster Work
151.000
sft
3.00
453.00
RCC Work
59.000
cft
6.00
354.00
Form work
136.000
sft
8.00
1088.00
Back filling with compact
32.000
cft
2.00
64.00
Sub-Total(L1)
2123.71
2123.71
L2.Labour-Tile/Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ceramic bricks work
47.470
sft
20.00
949.40
Sub-Total(L2)
949.40
949.40
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Forms
90.375
sft
5.00
451.88
Wood shutter-3time
3.650
cft
350.00
1277.50
Sub-Total(M1)
1729.38
1729.38
S1.Sub-contractor-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Plastic-Weather paint
151.000
sft
10.00
1510.00
Sub-Total(S1)
1510.00
1510.00
S3.Subcontractor-Misc
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Alum fixed window
32.290
sft
170.00
5489.30
Alum swing door
17.000
sft
450.00
7650.00
Sub-Total(S3)
13139.30
13139.30
Total(1)
38550.15
Add over head on Total(1)
2.5 %
963.75
Total(2)
39513.91
Add Profit on Total(2)
8.0 %
3161.11
Total(3)
42675.02
Add VAT on Unit Price
4.5 %
2098.77
Add Income Tax on Unit Price
4.0 %
1865.57
Unit Price
46639.36
Say
46639
per NO
Item: 15E (A24) Buolder Supply
Basis:1 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Boulder
1.000
cft
55.00
55.00
Sub-Total(A1)
55.00
592.02
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
0.100
nos.
100.00
10.00
Sub-Total(L0)
10.00
107.64
Total(1)
699.66
Add over head on Total(1)
2.5 %
17.49
Total(2)
717.15
Add Profit on Total(2)
8.0 %
57.37
Total(3)
774.52
Add VAT on Unit Price
4.5 %
38.09
Add Income Tax on Unit Price
4.0 %
33.86
Unit Price
846.47
Say
846
per M2
Item: 11 (B01B1) uPVC Pipe pipe fitting -100mm
Basis:1 rft
L4.Labour-Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
uPVC Pipe fitting-100 mm
1.000
rft
15.00
15.00
Sub-Total(L4)
15.00
107.64
Total(1)
107.64
Add over head on Total(1)
2.5 %
2.69
Total(2)
110.33
Add Profit on Total(2)
8.0 %
8.83
Total(3)
119.16
Add VAT on Unit Price
4.5 %
5.86
Add Income Tax on Unit Price
4.0 %
5.21
Unit Price
130.23
Say
130
per RM
Item: 15D (B15A1) 25mm GI Pipe fitting-Labour Chage
Basis:1 rft
L4.Labour-Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
GI Pipe fiting - 25mm dia
1.000
rft
11.00
11.00
Sub-Total(L4)
11.00
107.64
Total(1)
107.64
Add over head on Total(1)
2.5 %
2.69
Total(2)
110.33
Add Profit on Total(2)
8.0 %
8.83
Total(3)
119.16
Add VAT on Unit Price
4.5 %
5.86
Add Income Tax on Unit Price
4.0 %
5.21
Unit Price
130.23
Say
130
per RM
Item: 15C (B15A2) 25mm GI Pipe Opening
Basis:1 rft
L4.Labour-Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
GI Pipe Opening
1.000
rft
1.00
1.00
Sub-Total(L4)
1.00
107.64
Total(1)
107.64
Add over head on Total(1)
2.5 %
2.69
Total(2)
110.33
Add Profit on Total(2)
8.0 %
8.83
Total(3)
119.16
Add VAT on Unit Price
4.5 %
5.86
Add Income Tax on Unit Price
4.0 %
5.21
Unit Price
130.23
Say
130
per RM
Item: 12 (C07A) SS grating (300x250)
Basis:1 no.
C1.Steel Structures
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
SS Grating (300x250)
1.000
no
1200.00
1200.00
Sub-Total(C1)
1200.00
1200.00
Total(1)
1200.00
Add over head on Total(1)
2.5 %
30.00
Total(2)
1230.00
Add Profit on Total(2)
8.0 %
98.40
Total(3)
1328.40
Add VAT on Unit Price
4.5 %
65.33
Add Income Tax on Unit Price
4.0 %
58.07
Unit Price
1451.80
Say
1452
per NO
Item: 15I (D06A) Pre-cast Kerb (Concord)
Basis:1 rft
Total(1)
0.00
Add over head on Total(1)
2.5 %
30.00
Total(2)
1230.00
Add Profit on Total(2)
8.0 %
98.40
Total(3)
1328.40
Add VAT on Unit Price
4.5 %
65.33
Add Income Tax on Unit Price
4.0 %
58.07
Unit Price
1451.80
Say
1452
per RM
Item: 15J (D06B) MS Pocket Door at IV Front Load-U
Basis:1 sft
Total(1)
0.00
Add over head on Total(1)
2.5 %
30.00
Total(2)
1230.00
Add Profit on Total(2)
8.0 %
98.40
Total(3)
1328.40
Add VAT on Unit Price
4.5 %
65.33
Add Income Tax on Unit Price
4.0 %
58.07
Unit Price
1451.80
Say
1452
per M2
Item: 15K (D06C) Dismantling for Punch making with
Basis:1 no.
Total(1)
0.00
Add over head on Total(1)
2.5 %
30.00
Total(2)
1230.00
Add Profit on Total(2)
8.0 %
98.40
Total(3)
1328.40
Add VAT on Unit Price
4.5 %
65.33
Add Income Tax on Unit Price
4.0 %
58.07
Unit Price
1451.80
Say
1452
per NOS.
Item: 15L (D06D) Existing Pit Remodelling
Basis:1 no.
Total(1)
0.00
Add over head on Total(1)
2.5 %
30.00
Total(2)
1230.00
Add Profit on Total(2)
8.0 %
98.40
Total(3)
1328.40
Add VAT on Unit Price
4.5 %
65.33
Add Income Tax on Unit Price
4.0 %
58.07
Unit Price
1451.80
Say
1452
per NOS.
Item: 15M (D06E) Guard Post Remove/Installl
Basis:1 no.
Total(1)
0.00
Add over head on Total(1)
2.5 %
30.00
Total(2)
1230.00
Add Profit on Total(2)
8.0 %
98.40
Total(3)
1328.40
Add VAT on Unit Price
4.5 %
65.33
Add Income Tax on Unit Price
4.0 %
58.07
Unit Price
1451.80
Say
1452
per NO.
Item: 15N (D06F) MS Grating at drain Top
Basis:1 no.
Total(1)
0.00
Add over head on Total(1)
2.5 %
30.00
Total(2)
1230.00
Add Profit on Total(2)
8.0 %
98.40
Total(3)
1328.40
Add VAT on Unit Price
4.5 %
65.33
Add Income Tax on Unit Price
4.0 %
58.07
Unit Price
1451.80
Say
1452
per NO.