Return Main Menu

Project Overhead Tank of Generator Room
Item: 01 (A18F) Dismantling of Rcc beam(.3x.3)
Basis:1 no.
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Dismantling beam(.3x.3)
1.000
no
1000.00
1000.00
Rod welded
1.000
no
100.00
100.00
Rubbish remove
1.000
no
100.00
100.00
Sub-Total(L1)
1200.00
1200.00
Total(1)
1200.00
Add over head on Total(1)
5.0 %
60.00
Total(2)
1260.00
Add Profit on Total(2)
8.0 %
100.80
Total(3)
1360.80
Add VAT on Unit Price
4.5 %
66.92
Add Income Tax on Unit Price
4.0 %
59.49
Unit Price
1487.21
Say
1487
per NO
Item: 02 (A18) Dismantling of 250 Br-wall
Basis:1 cft
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Dismantle B/W 250mm thk
1.000
cft
5.00
5.00
Rubbish cleaning
1.000
cft
5.00
5.00
Sub-Total(L1)
10.00
353.15
Total(1)
353.15
Add over head on Total(1)
5.0 %
17.66
Total(2)
370.81
Add Profit on Total(2)
8.0 %
29.66
Total(3)
400.47
Add VAT on Unit Price
4.5 %
19.70
Add Income Tax on Unit Price
4.0 %
17.51
Unit Price
437.67
Say
438
per M3
Item: 03 (A18A) Dismantling of Rcc Slab/Floor
Basis:1 cft
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Dismantling RCC
1.000
cft
30.00
30.00
Sub-Total(L1)
30.00
1059.45
Total(1)
1059.45
Add over head on Total(1)
5.0 %
52.97
Total(2)
1112.42
Add Profit on Total(2)
8.0 %
88.99
Total(3)
1201.42
Add VAT on Unit Price
4.5 %
59.09
Add Income Tax on Unit Price
4.0 %
52.52
Unit Price
1313.02
Say
1313
per M3
Item: 03A (A18H1) Dismantling of Lime Terracing
Basis:1 sft
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
0.160
nos.
100.00
16.00
Sub-Total(L0)
16.00
172.22
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cheisel - Hammer
0.100
no
55.00
5.50
Sub-Total(M1)
5.50
59.20
Total(1)
231.43
Add over head on Total(1)
5.0 %
11.57
Total(2)
243.00
Add Profit on Total(2)
8.0 %
19.44
Total(3)
262.44
Add VAT on Unit Price
4.5 %
12.91
Add Income Tax on Unit Price
4.0 %
11.47
Unit Price
286.82
Say
287
per M2
Item: 03B (A09E3) Dismantle of Pipe Support
Basis:1 no.
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
0.500
nos.
100.00
50.00
Sub-Total(L0)
50.00
50.00
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cheisel - Hammer
0.100
no
55.00
5.50
Sub-Total(M1)
5.50
5.50
Total(1)
55.50
Add over head on Total(1)
5.0 %
2.78
Total(2)
58.28
Add Profit on Total(2)
8.0 %
4.66
Total(3)
62.94
Add VAT on Unit Price
4.5 %
3.10
Add Income Tax on Unit Price
4.0 %
2.75
Unit Price
68.78
Say
69
per NO.
Item: 04 (A12B) Plaster 12mm thick (1:4)
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local - Mymensingh
7.500
cft
13.00
97.50
Cement
1.000
bag
343.00
343.00
Sub-Total(A1)
440.50
47.42
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Plaster Work
100.000
sft
3.00
300.00
Sub-Total(L1)
300.00
32.29
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Scaffolding
1.000
set
100.00
100.00
Sub-Total(M1)
100.00
10.76
Total(1)
90.47
Add over head on Total(1)
5.0 %
4.52
Total(2)
94.99
Add Profit on Total(2)
8.0 %
7.60
Total(3)
102.59
Add VAT on Unit Price
4.5 %
5.05
Add Income Tax on Unit Price
4.0 %
4.49
Unit Price
112.13
Say
112
per M2
Item: 05 (A08C) RCC (1:1.5:3) in Column
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement
22.000
bag
343.00
7546.00
Sand - Sylhet
46.000
cft
24.00
1104.00
Stone-chips
91.000
cft
80.00
7280.00
Sub-Total(A1)
15930.00
5625.68
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mini Dumper
100.000
cft
2.00
200.00
M/C-Vibrator,S-structure
100.000
cft
5.00
500.00
Sub-Total(E1)
700.00
247.21
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour Supply
1.000
nos.
100.00
100.00
RCC Casting-Superstructur
100.000
sft
10.00
1000.00
FormWork:24-33ft from PL
305.000
sft
10.00
3050.00
Sub-Total(L0)
4150.00
1465.57
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Forms
305.000
sft
5.00
1525.00
Hessain cloth
323.000
sft
1.00
323.00
Sub-Total(M1)
1848.00
652.62
Total(1)
7991.08
Add over head on Total(1)
5.0 %
399.55
Total(2)
8390.63
Add Profit on Total(2)
8.0 %
671.25
Total(3)
9061.88
Add VAT on Unit Price
4.5 %
445.67
Add Income Tax on Unit Price
4.0 %
396.15
Unit Price
9903.70
Say
9904
per M3
Item: 06 (A10A) Re-bar Grade 60
Basis:1000 kg.
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
GI Wire
10.000
kg
90.00
900.00
Re-bar G60
1050.000
kg
40.20
42210.00
Sub-Total(A1)
43110.00
652.62
L0.Labour - Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Re-bar Work
1000.000
kg
1.65
1650.00
Local carrying Rod
0.000
kg
0.25
0.00
Sub-Total(L0)
1650.00
652.62
Total(1)
1305.24
Add over head on Total(1)
5.0 %
65.26
Total(2)
1370.50
Add Profit on Total(2)
8.0 %
109.64
Total(3)
1480.14
Add VAT on Unit Price
4.5 %
72.79
Add Income Tax on Unit Price
4.0 %
64.71
Unit Price
1617.64
Say
1618
per TON
Item: 07 (A13F) Weather coat paint
Basis:100 sft
A3.Material-Paint
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Plastron Sealer
0.500
Ltr
160.00
80.00
Enamel paint
0.250
Ltr
170.00
42.50
Snowcel
2.500
kg
7.60
19.00
Thinner-T6/T7
0.500
Ltr
46.00
23.00
Weather Coat (ColorBank)
1.420
Ltr
227.85
323.55
Sub-Total(A3)
488.05
52.53
L6.Labour Paints
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Weather coat painting
100.000
sft
4.00
400.00
Sub-Total(L6)
400.00
43.06
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Scaffolding
1.000
set
100.00
100.00
Sub-Total(M1)
100.00
10.76
Total(1)
106.35
Add over head on Total(1)
5.0 %
5.32
Total(2)
111.67
Add Profit on Total(2)
8.0 %
8.93
Total(3)
120.60
Add VAT on Unit Price
4.5 %
5.93
Add Income Tax on Unit Price
4.0 %
5.27
Unit Price
131.81
Say
132
per M2
Item: 08 (A18B) Stage making for O-tank
Basis:1 no.
Total(1)
0.00
Add over head on Total(1)
5.0 %
5.32
Total(2)
111.67
Add Profit on Total(2)
8.0 %
8.93
Total(3)
120.60
Add VAT on Unit Price
4.5 %
5.93
Add Income Tax on Unit Price
4.0 %
5.27
Unit Price
131.81
Say
132
per NO