Return Main Menu

QC Lab Roof Admin Bldg.
Bill Cost
Actual Cost
Profit
Offer12345:2004-09-12 Total : Tk.2,527,965 Material
1,274,008
1,364,727
-6.65 %
Purchase : 2004-10-06 Total : Tk.1,261,450 Labour
338,791
252,912
33.96%
Bill123456:2005-03-02 Total : Tk.2,143,773 Equipment
30,817
0
0.00%
Certify123: 2005-03-06 Total : Tk.1,049,671 Other
187,071
296,232
-36.85 %
Pay 12345: Total : Tk.696,265 Overhead
114,610
57,351
99.84 %
oh: 5.0% Profit:8.0% vat:4.5% it:0.0 % Total Profit =8.75% Total
1,945,297
1,971,222
-1.32 %
Photograph Taken : Start : Finish :83.21%
Code
Item
Unit
BOQ Qty
Bill Qty
Actual Qty
Supp Qty
BOQ Rate
Actual Rate
BOQ Cost
Bill Cost
Actual Cost
Materials-Civil
A102 Brick
1,190
1,156
11,800
0
3.70
3.50
4,403
4,277
41,300
A103 Sand - Local - Mymensingh
200
187
1,019
0
13.00
13.00
2,601
2,428
13,245
A105 Cement
1,035
970
1,228
1,000
246.00
295.00
254,679
238,501
362,260
A106 Sand - Sylhet
2,055
1,928
2,254
0
18.00
22.50
36,983
34,711
50,709
A107 Stone-chips
4,210
3,940
3,635
0
70.00
70.00
294,693
275,797
254,450
A112 GI Wire
215
184
195
0
70.00
50.00
15,050
12,884
9,750
A114 Re-bar G60
22,575
19,326
17,160
21,500
36.50
36.50
823,988
705,410
626,340
A132 Wood - Mango
0
0
14
0
0.00
350.00
0
0
4,764
A135 Febond SBR
0
0
69
0
0.00
80.00
0
0
5,520
A146 Sika plastcrete plus
58
60
0
0
0.00
0.00
0
0
0
 
Total
1,432,397
1,274,008
1,368,338
Plumbing/Sanitr Pipe
B108 uPVC Pipe 150 dia
0
0
280
0
0.00
115.00
0
0
32,200
B112 uPVC Pipe 100mm dia
0
0
60
0
0.00
58.00
0
0
3,480
B114 uPVC Bend 100mm dia
0
0
5
0
0.00
180.00
0
0
900
B117 uPVC Bend 150mm dia
0
0
3
0
0.00
560.00
0
0
1,680
B147 uPVC End Cap -150 dia
0
0
2
0
0.00
850.00
0
0
1,700
B152 Solvent cement -500 ml
0
0
2
0
0.00
490.00
0
0
980
B153 uPVC R.Tee - 150x100
0
0
21
0
0.00
950.00
0
0
19,950
 
Total
0
0
60,890
MS/SS Work i/c matr
C222 Hollow Metal Door work
0
0
26
0
0.00
300.00
0
0
7,794
 
Total
0
0
7,794
Equipment-Civil
E102 Mixer m/c and vibrator
4,238
4,012
0
0
5.00
0.00
21,189
20,062
0
E103 Mini Dumper
4,626
4,330
0
0
2.00
0.00
9,253
8,659
0
E105 Welding M/c
1,050
1,020
0
0
0.50
0.00
525
510
0
E126 M/C-Vibrator,S-structure
388
317
0
0
5.00
0.00
1,942
1,586
0
 
Total
32,909
30,817
0
Labour - Civil
L001 Re-bar Work
21,500
18,406
15,743
0
2.00
1.65
43,000
36,812
25,976
L004 Ordinary Labour Supply
1,247
1,230
686
0
100.00
95.00
124,677
122,988
65,170
L006 O.T. (5 hr.) - Labour
0
0
19
0
0.00
50.00
0
0
950
L008 Dismentling F/W/Mar tile
678
659
0
0
4.00
0.00
2,713
2,636
0
L011 Carpenter Helper
17
17
0
0
150.00
0.00
2,550
2,475
0
L012 RCC Casting-Superstructur
1,978
1,581
0
0
10.00
0.00
19,776
15,807
0
L023 Poiting:15.5-27ft Scaffol
0
0
3,820
0
0.00
1.00
0
0
3,820
L025 FormWork:24-33ft from PL
7,809
6,296
0
0
10.00
0.00
78,085
62,962
0
L028 125mm thick Brick Work
226
220
0
0
5.00
0.00
1,131
1,098
0
L051 Rcc S-Casting slop
2,649
2,749
2,769
0
10.00
6.50
26,486
27,489
18,000
L054 Form work slop 24-33ft
6,410
6,652
0
0
10.00
0.00
64,097
66,524
0
L069 Formwork Col-2nd Floor
0
0
1,869
0
0.00
6.50
0
0
12,146
L070 From slab-2nd flr-Fix
0
0
8,992
0
0.00
5.00
0
0
44,962
L079 Rod binder supply
0
0
-49
0
0.00
110.00
0
0
-5,390
L083 Only shutter oppening
0
0
446
0
0.00
2.00
0
0
892
L084 Form work parapet wall
0
0
2,818
0
0.00
7.00
0
0
19,727
L088 250mm B/work-45ft-ht
0
0
33
0
0.00
5.00
0
0
166
L089 125mm B/work-23ft
0
0
1,806
0
0.00
4.75
0
0
8,580
L096 Ceiling plaster-58.5ft-ht
0
0
1,293
0
0.00
5.00
0
0
6,465
L097 Inside plaster-33ft-ht
0
0
1,651
0
0.00
4.25
0
0
7,018
L098 Outside plaster-72.5ft-ht
0
0
1,966
0
0.00
5.00
0
0
9,828
 
Total
362,515
338,791
218,311
Labour Paints
L656 Bontile work incl-paint
0
0
1,525
0
0.00
20.00
0
0
30,492
 
Total
0
0
30,492
Misc.-Civil
M102 Steel Forms
14,218
12,949
0
0
5.00
0.00
71,091
64,743
0
M106 Steel Scaffolding
178
176
0
0
100.00
0.00
17,767
17,557
0
M109 Welding Electrode VM 8-no
35
34
10
0
500.00
350.00
17,500
17,000
3,500
M114 Grinding Disk-175
0
0
151
0
0.00
55.00
0
0
8,305
M120 Diamond cuting disk-175mm
0
0
1
0
0.00
2,250.00
0
0
2,250
M123 Steel pipe with B-plate
170
130
0
0
11.00
0.00
1,865
1,433
0
M125 B-plate with pipe
530
550
0
0
16.00
0.00
8,476
8,797
0
M126 Wood shutter-3time
23
17
0
0
350.00
0.00
7,911
6,079
0
M128 Steel beam,S-structure
408
399
0
0
40.00
0.00
16,330
15,974
0
M129 Stone Cutting Disc - 175
0
0
29
0
0.00
110.00
0
0
3,190
M130 Diamond Cuting Disc- 175
0
0
0
0
2,200.00
0.00
616
598
0
M131 Diamond Cutiing Disc -100
0
0
2
0
0.00
600.00
0
0
1,200
M133 Cheisel - Hammer
748
739
0
0
55.00
0.00
41,147
40,672
0
M150 Plastocerte Plus
0
59
20
0
0.00
150.00
0
0
3,000
M153 Hessain cloth
13,968
14,219
0
0
1.00
0.00
13,968
14,219
0
 
Total
196,670
187,071
21,445
Alum,SS/MS,FalseCeil
S287 Al Win F/Sliding W- R-gls
0
0
971
0
0.00
250.00
0
0
242,863
 
Total
0
0
242,863
 
Total(1)
2,024,491
1,830,688
1,950,132
Add Overhead on Total(1)
5.0 %
101,225
91,534
Total(2)
2,125,716
1,922,222
Add Profit on Total(2)
8.0 %
170,057
153,778
Total(3)
2,125,716
1,922,222
Add vat on Total Cost
4.5 %
108,178
97,822
Add Income Tax on Total Cost
0.0 %
108,178
97,822
Total Cost
2,403,951
2,173,822